Time Line (Ver. 5.0) Help Text - IBM format

COPYRIGHT NOTICE:

(c) Copyright 1991, Symantec Corporation, USA,
"All Rights Reserved.

This work is subject to copyright.  All rights are reserved, whether the
whole or part of the material is concerned, specifically those of
translation, reproduction, re-use of illustrations, broadcasting, and
storage in data banks or information retrieval services.

INSTRUCTIONS:

The Time Line help files, TLHELP5.TXT and TLHELP5.IDX, are stored in
the \TL5\TEXT directory.  To modify the help files, TLHELP5.TXT must
first be decompressed:
! Copy MAKEHELP.EXE from the \TL5\INSTALL directory.
! Copy TLHELP5.TXT and TLHELP5.IDX to backup filenames.
! Enter the command MAKEHELP/X HELPTEXT.TXT TLHELP5.

Edit the HELPTEXT.TXT file with a "full ASCII" editor.  Use an editor
that is designed to handle the full 256 ASCII characters, such as "Brief".

After editing, the HELPTEXT.TXT file must be compressed:
! Enter the command MAKEHELP HELPTEXT.TXT TLHELP5.
! This produces a new set of help files, TLHELP5.TXT and TLHELP5.IDX.

Use these directions while editing:

  A "$" in the leftmost column indicates a key.
!CAUTION:  These keys should never be changed!
  Keys for menu help:
! A "$" starts the key.
! Followed by "" (ASCII-227).
! Four letters from Menu prefix.
! Three letters from Menu name.
! Example:  Key for File/Save would be $FILESav
  Keys for form help:
! A "$" starts the key.
! Followed by "" (ASCII-226).
! Four letters indicating the form (usually, but not always the form name).
! A one- or two-digit number indicating the position of the field
#on the form (first field is "0").
! Example:  Key for Critical Path field on Filter Form would be $FLTR4
  Keys for view, list, and dialogue box help:
! Internally generated.
! The best way to find these keys is to search for a recognizable phrase
#from the current helptext.
  Keys for help on editable columns:
! Begin with "$"
! Come from phrases in the phrases file, word 21 of the column definition.
! Begin with "$TCOL" for Task columns.
! The number at the end of the key is the internal number of the column.
  A key preceded by "." is a subroutine (used more than once).
!When you change one of these, be sure that the change is appropriate
!in all situations where the routine is used.
  A slash (/) at the beginning of a line takes a "page break".
! Single slash takes break if not enough lines left to display remaining
#help.  (Usually, double screens of help can be shown in compressed mode.)
! Double slash ALWAYS takes break.
! Slash followed by a number takes break if fewer than that number of lines
#remain on current help box.
  Attributes (highlights) are added as follows:
! Enter a "" character (ASCII-253)
! Enter a letter indicating the attribute:
#s - usually green
#u - usually yellow
#w - usually red
#Note: color of attribute depends on current video configuration.
  Attributes carry to the end of each line, or until another attribute
!is encountered.
  Entering "" (two ASCII-253's) changes back to default attribute.
  Add an item to the index (under the key "$INDEX") as follows:
! Type the index entry into the list.
! On the same line, add a Help key to be displayed for the entry.
! Index entries must be manually alphabetized.
  Make a related-item menu (at bottom of help box) as follow:
! Enter "+", and the menu items, separated by commas.
! On the next line, enter "=", and the referenced help keys, separated
#by commas.

g

$TM.INDEX
^*INDEX
$INDEX
Using this index $INSTR
Using the Help system $ASSIHel
Introduction to Time Line $TM.INTRO
Technical Support $SUPTECH

Achievement rollup options $CALF7
ALAP task type $TASK13
Alphabetized listing of fields $FIELDS
ASAP task type $TASK13
Availability (resource) $RSRC6
Baseline $SCHEBas
Calculations $SCHECal
Calculator $CALC
Calendars $CALENDAR
  Master $SCHEMas
  Resource $RSRC5
Column Names $COLN
Combining schedules $FILECom
Configuring $MAINCon
  Disk file $CONFDis
  Date formats $CONFDat
  Graphics $CONFGra
  Printer $CONFPri
  Video $CONFVid
Consulting support $SUPTRCON
Contouring $CONTOUR
Copy and paste $COPYPAST
Corporate Support Program $SUPCORP
Costs $COST
  Fixed $COSTF
  Form $RESOForm
  Rates $RSRC7
  Unit $COSTU
  Variable $COSTV
Credits $.CREDITS
Critical path $CRITPATH
Cross project links $LINK2
Cursor movement $CURSOR
Customer services $SUPPORT
  Consulting support $SUPTRCON
  Corporate Support Program $SUPCORP
  Technical support $SUPTECH
  Training support $SUPTRCON
Date entry $.DTFRMTS
Dependencies $SCHEDep
  Adding $DEPEJoi
  Deleting $DEPEUnj
  Form $DEPEFor
  Instructions $DEPENS
  Listing $DEPELis
  Loops $LOOP
  Partial $DEPEFor
  PERT view $VIEWPer
  Showing $DEPESho
Duration-driven task $DRIVENBY
Effort-driven task $DRIVENBY
Erase $ERASE
  File $FILEEra
  Schedule $SCHEEra
Exit to DOS $UTILExi
Export $FILEXpo
Extracting schedules $EXTRACT
Field listing (all forms) $FIELDS
File management $MAINFil
  Combining $FILECom
  Erasing $FILEEra
  Exporting $FILEXpo
  Extracting schedules $EXTRACT
  Importing $FILEImp
  Previous versions $FILEPre
  Retrieving $FILERet
  Saving $FILESav
Filters $SCHEFil
  Clear $FILTCle
  Highlight $FILTHig
  Select $FILTSel
Fiscal year $12477
Fixed task type $TASK13
Float (slack) $SLACK
Force critical $TCOL112
Function key shortcuts $.FKEYS
Gantt view $VIEWGan
Getting started $FIRSTAID
Graphics $MAINGra
  Gantt chart $GRAPGan
  PERT chart $GRAPPer
  Title/notes keywords $HDGCODES
Hints for using Time Line $HINTS
Histogram view $VIEWHis
Import $FILEImp
International services $SUPINTNL
Journal notes $SCHEJou
Keyboard $.FKEYS
  Laptops $LAPTOPS
Keywords in reports $HDGCODES
Laptops $LAPTOPS
Layouts $LAYOUTS
  Gantt $SCHELay
  PERT $20800
Linked tasks $LINK2
Macros $UTILMac
  Hints for using macros $MACROHNT
Master calendar $SCHEMas
Moving around in Time Line $CURSOR
Multi-project scheduling $MULTI
Negative slack $CALF2
New schedule $ASSINew
Notes $NOTES
  Task $TASKNot
  Journal $SCHEJou
OBS $SUMM121
Options $SCHEOpt
Outline $OUTLINE
  Components $OUTLCOM
Percent Achieved rollup $CALF7
Partial dependency $DEPEFor
PERT view $VIEWPer
Plotter Cables/Settings $.PLOTCAB
Priority $TASK122
QuickPick $TASKSea
Reports $MAINRep
  Assignments $TABLAss
  Availability $TABLAva
  Calendar $TABLCal
  Cross tab $REPOCro
  Detail $REPODet
  Form $REPOFor
  Gantt $REPOGan
  Heading keywords $HDGCODES
  Histogram $REPOHis
  PERT $REPOPer
  Rate $TABLRat
  Resource $TABLRes
  Status $REPOSta
  Tasks $TABLTas
  Varying assignment $TABLVar
  Work tree $REPOWor
Resources $SCHERes
  Adding $3000
  Availabilities $RSRC6
  Calendars $RSRC5
  Contouring $CONTOUR
  Cost rates $RSRC7
  Form $RESOForm
  Histogram $VIEWHis
  Leveling $CALF5
  List $3000
Retrieving the schedule $FILERet
Rollup options $CALF7
Saving the schedule $FILESav
Searching for tasks $TASKSea
Separating spent and to go effort $CALF4
Slack (float) $SLACK
Sorting $SCHESor
Spreadsheet editing $SPRDVIEW
Start date restriction $TCOL113
Startup help $FIRSTAID
Summary task type $SUMMARY
Support $SUPPORT
Swap files $TLSWAP
Tasks $SCHETas
  Adding $TASKAdd
  Copying $TASKCop
  Deleting $TASKDel
  Editing $TASKEdi
  Form $TASKFor
Task type $TASK13
Technical support $SUPTECH
  Preparing to Call $CALLPREP
  Common Questions and Answers $Q&A
  Sending Materials for Analysis $CALLSEND
Temporary files $TLSWAP
Time Line team $.CREDITS
Tracking $TRACKING
  Baseline $SCHEBas
  Updating hints $.TRACK
Training and consulting $SUPTRCON
Undo $ASSI1-U
Updating the schedule $ASSIUpd
Utilities $MAINUti
Vacation calendars $RSRC5
Views $MAINVie
  Gantt $VIEWGan
  Histogram $VIEWHis
  PERT $VIEWPer
  Work Tree $VIEWWor
WBS $SUMM120
Windows, running Time Line under $WINDOWS
Work Tree view $VIEWWor
$.BAD5GP
C*1*

The parameters file, that defines the output device characteristics,
has an incorrect internal structure.

  You may be able to correct this by reinstalling your graphic devices
!(*.5GP files) from the distribution diskettes.
><.CALLTEK
$.CALLTEK
/3
  For technical assistance, in the USA or Canada, call 415-897-1445
!(M-F, 6am-5pm Pacific time).  In other countries, call your local
!Symantec office.
$.CHDG
This Key&Does This
s*"T
$.CREDITS
uCREDITS
sf

Andrew Layman$David Blair'Lee Davis)Chris Lofgren
$
Ed Klein)Roger Collins%Ken Rogoway'Chie Lin
Larry Azlin&Patty Gilbert%Patrick Rigney$Steve Alexander
Janet Somers%Tom Semple#

Jennifer Flaa$Kris Hearrell%Rob Bradshaw&Chris Musser
Gary McEwan&Mark Hemsley&Thomas Lindemuth"Cass Smith
Eric Schyberg$Peter Jones'Christina Drukala!Pink Foster  
$
Maureen Dillon#Cathy Shea(Irene Sample&Rita Dickey 
$
Ken Cadby(Kurt Sussman&Kimberly Alves$Carol Savary#
$
Carrie Requist#Beth Guthrie&John Gordon'Pam Fleming$
 
Sameh Tuwfik%Cyndie Cronkright!J.D. Majoulet%Jane Deutsch#
Kathy Baum
$.CUSTSER
For more information, please call Time Line customer services at
800-441-7234 in the US, or 800-626-8847 inside California.  From 
Canada, call us at 408-252-3570.  We're open from 7:00 am to 5:00 pm,
Pacific Time, Monday through Friday.
$.DEVSET
uConfigure Graphics
sh

><.PALLSET
>.CGEND
$.CGEND

  Graphics are printed from the Graphics menu choice.  (The "Reports"
!menu choice uses character mode.)
-  To continue
+Press [Enter]
=QUIT
$.PALLSET
/5
  Check your palette selections to ensure colors or grey scale choices
!match the device on which Time Line will print or plot your final
!output.

!Palettes are selected on the Graphics Gantt and PERT chart forms.
$.PALLFIL
/7
  Check your palette selections to ensure colors or grey scale choices
!match the device on which Time Line will print or plot your final
!output.  (Select a palette that matches the device you will use at print
!time.)

!Palettes are selected on the Graphics Gantt and PERT chart forms.
$CG.HPLS
uLaser Printer
sh

We recommend that you check the palette selections on the Graphics Gantt
and PERT charts forms to make sure they use grey scale choices.  Try the
LASER palette for starters.
>.CGEND
$CG.CANON
>CG.HPLS
$CG.PSST
>CG.HPLS
$CG.IBMLS
>CG.HPLS
$CG.SCODL
uSCODL Slide Output
sh
Reminder:

  When configuring slide output for use with a slide service, select
!output to file.

  If a film recorder is directly connected to your computer, select output
!to device.
><.PALLFIL
>.CGEND
$CG.CGMGE
uCGM Computer Graphics Metafile with indexed color output
sh
Use this generic (indexed) CGM device setting for products that do not
read the RGB settings directly.

We recommend that you try the direct RGB CGM device (CGM - Corel Draw!)
choice first.  If that works for your chosen product, continue to use
that; it will give the most accurate color reproduction.

If it does not work, try this "generic" CGM device. 
><.PALLFIL
>.CGEND
$CG.CGMCO
uComputer Graphics Metafile with RGB color output
sh
Use this RGB output CGM device setting for all products that can read
CGM files containing direct RBG codes.

We recommend that you try this direct RGB CGM device (CGM - Corel Draw!)
choice first.  If that works for your chosen product, continue to use
this; it will give the most accurate color reproduction.

If it does not work, try the "generic" (indexed) CGM device. 
><.PALLFIL
>.CGEND
$.PLOTCAB

Choose the plotter type below:

+Calcomp,Houston Instruments,HP
=.CABCMPL,.CABHI,.CABHP
$CG.CMPL1
uCalcomp Plotter
sh

><.PALLSET
><.CGEND
+Quit,Cables and Settings
=QUIT,.CABCMPL
$.CABCMPL
uCalcomp 1023 or 1025 Plotter cables and settings
sh
Calcomp Artisan (1023, 1025)
Cable configuration:
  CalComp part#: 11772-0250 (25 feet) or 11772-0102 (10 feet)
  If you use a CAD program, use the cable and#Cable: 25-25!9-25
  communications settings that you use with-1-1"2-3
  your CAD software. Otherwise, use a standard*2-2"3-2
  straight-through cable and the following settings:$3-3"5-7
Parameter Settings:E7-7!7  4
  Format: PCI,Baud Rate: 9600-4  4 8  5
  Byte Length: 8 bit%Stop Bits: 105  5 6  6
  Parity: No(none)'Handshake: Direct Control#6  6 1  8
  Sync Char: 2+Number Sync: 1.8  8"20
  End Message: 3)Checksum: disabled)20 20
/
uCalcomp 104x Plotter cables and settings
sh
Calcomp 104x
Cable configuration:
  CalComp part#: 11772-0250 (25 feet) or 11772-0102 (10 feet)
  If you use a CAD program, use the cable and communications settings
  that you use with your CAD software. Otherwise, use a standard 
  straight-through cable and the following settings:
Parameter Settings::Cable:  25-25!9-25
  Parity: 0.Bits/Char: 8/1-1"2-3
  Stop Bits: 1+Clock: 032-2"3-2
  Interface: 0+Listen address: 0=serial#3-3"5-7
  Host Baud Rate: 9600#Mode: 0-PCI Controller%7-7!7  4
  Term Muting: No(Checksum Enable: No'4  4 8  5
  Asynchronous: No'End of Message: 03(5  5 6  6
  Direct Control: Yes$XON/XOFF: No.6  6 1  8
  Term Baud Rate: 9600#Duplex: 018  8"20
  Turn Around Code: 0$Sync Code: 1-20 20
  Sync Code Value: 002
$CG.HIDMP
uHouston Instruments Plotter
sh

><.PALLSET
><.CGEND
+Quit,Cables and Settings
=QUIT,.CABHI
$.CABHI
uHouston Instruments Plotter cables and settings
sh
Houston Instruments DMP-612Cable:  25-25!9-25
Cable configuration:@-#!-"
  DMP part #:H1-1"2-2
%HR29-483F2-3"3-3
  If you use a CAD program, use the cable and(3-2"5-7
  communications settings that you use with*7-7!1
  your CAD software. Otherwise, use a standard'5-4!4
  null-modem cable and the settings below.*6#6
Parameter Settings:A8#9
  Baud Rate: 9600B20#
  UART Parity: BIT 8=0=22"
  Handshake RTS/DTR: Toggle8
$CG.HPP74
>CG.HPP75
$CG.HPP75
uHewlett-Packard Plotter
sh

><.PALLSET
><.CGEND

+Quit,Cables and Settings
=QUIT,.CABHP
$.CABHP
uHP Plotter cables and settings
sh
Cable configuration for all HP plotters:'Cable:  25-25!9-25
  HP part #:  24542G, 17255D/M9-#!-" 
  If you use a CAD program, use the cable and+1-1"2-2 
  communications settings that you use with your(2-3"3-3 
  CAD software. Otherwise, use a standard/3-2"5-7 
  null-modem cable.E7-7!7  4 
W4  4 8  5 
W5  5 6  6 
W6  6 1  8 
W8  8"20 
V20 20
/8
HP7550A

Parameter Settings:7
  Data Flow: Remote or Standalone)
  Bypass: Off,Duplex: Full#
  Handshake: Hardwire or Direct+
#(called Clear-to-Send in Time Line)"
  Parity: 8-bits or Off"Baud Rate: 9600
/8
HP7580B
HP7585B

Parameter settings:<
There are three sets of DIP switches and a%
rotary dial for Baud Rate. Use the dial to%
select a Baud Rate of 9600. Set the Interface"
Mode switch to RS-232-C.7
/8
DraftMaster (HP7595A)

Parameter Settings:?
  Dataflow: Remote or Standalone"Parity: 0%
  Baud Rate: 96001Bypass: Off#
  Duplex: Full4Monitor: Off"
  Hardwire: On (Clear-to-Send protocol in Time Line)
  Auto-Disc: OffB
$.DTFRMTS
uEntering Dates
sh

  Time Line recognizes many different ways of entering the date and time.
!MM/DD/YY!Mon DD, YY%(In other words, just about any date format
!MM-DD-YY!Month DD, Y""will do.  If you leave out the year, Time
!DD-Mon-YY  DD-Month-Y"#Line assumes the current year. Time of day
>can be entered, as well.  Use am/pm, or
!2pm"2:00pm"14:00%24-hour clock.)

  To have times appear with dates, select Date and Time on Options Form.

  Common words & math symbols can also be used.
! uWords such as today, tomorrow, yesterday, & asof can serve as dates.
! uMath symbols (+ and -) can add and subtract time from dates.
! uTime units (minute(mi), hour(h), day(d), week(w), month(mo), 
#year(y)) can be added and subtracted to dates.

  To change the way dates are displayed, select Configure / Date Formats.
/4
  If you have chosen to use Fiscal Years, entering a date without the 
!letters "FY" will indicate the calendar year, while dates containing
!"FY" will be fiscal years.
!With Fiscal Years, only date formats 1, 2, 3 and 4 can be used (change
"with Configure / Date Formats).
+Quit,Index,Date/Time,Configure,Fiscal Years
=Quit,Index,OPTN7,CONFDat,12477
$.FILESEQ
DOS establishes a maximum number of files that can be open at any one
time.  This limit can be changed by adding a line such as FILES=20 to
your \CONFIG.SYS file and rebooting.

We recommend 20.  Remember that RAM-resident programs such as Ready!
and SideKick use files themselves.  If you use RAM-resident programs,
you may need to increase this FILES limit.
$.FKEYS
+
"="<
" uHelp$S: Help Index%" uEdit$S: Task Notes$
 uF1 )C: Calendar Menu" uF2 )C: Task Form%
")A: Macro Menu%")A: Journal Notes!
"="<
" uSet%S: Part'l Depndency " uDepndency S: Show Depndncies 
 uF3  uDepndency C: Remove Depndency  uF4  uList$C: PERT View%
")A: Macro Insert#"<
"="<
" uTask$S: WBS QuickPick"" uLayout"S: Options Form"
 uF5  uSearch"C: CurCol QuickPick  uF6  uList$C: File Form%
" u(QuickPick)1")A: Macro List$
"="<
" uHighlight S: Select Filter"" uResource  S: Res/Cost List!
 uF7  uFilter"C: Highlight 2$ uF8  uHistogram C: Gantt View$
")A: Highlight 3$")A: of cursor task  
"="<
" uRecalc"S: Erase to End#" uAccept"S: Undo Last Chng  
 uF9 ,of Field/Line"uF10  uForm$C: Redo Last Undo  
"="<
"="<
$.HELP
uHelp
sh

$.HKEYS
+
"="<
" uHelp$S: Help Index%" uEdit$S: Task Notes$
 uF1 )C: Calendar Menu" uF2 )C: Task Form%
")A: Macro Menu%")A: Journal Notes!
"="<
" uSet%S: Part'l Depndency " uDepndency S: Show Depndncies 
 uF3  uDepndency C: Remove Depndency  uF4  uList7
")A: Macro Insert#"<
"="<
" uTask$S: WBS QuickPick"" uLayout"S: Options Form"
 uF5  uSearch"C: CurCol QuickPick  uF6  uList$C: File Form%
" u(QuickPick)1")A: Macro List$
"="<
" uHighlight S: Select Filter"" uHistogram S: Res/Cost List!
 uF7  uFilter"C: Highlight 2$ uF8  uNames#C: Gantt View$
")A: Highlight 3$")A: of cursor task  
"="<
" uRecalc"S: Erase to End#" uAccept"S: Undo Last Chng  
 uF9 ,of Field/Line"uF10  uForm$C: Redo Last Undo  
"="<
"="<
$.NETADMI
  Consult your network administrator.
$.NOHELP
uNo Help Available
sh

Sorry, but no additional help is available for this item.
$.PICKLIS
  Move up and down the list          [/], [PgUp/Dn], [Hm/End]
  Jump to an item with QuickPick        Type 1st letter(s) of name
  Reverse the QuickPick process        [Backspace]
  Select an item                [Enter] or [F10]
  Cancel selection process           [Esc]
$.PKEYS
"="<
" uHelp$S: Help Index%" uEdit$S: Task Notes$
 uF1 )C: Calendar Menu" uF2 )C: Task Form%
")A: Macro Menu%")A: Journal Notes!
"="<
" uSet%S: Part'l Depndency " uDepndency S: Show Depndncies 
 uF3  uDepndency C: Remove Depndency  uF4  uList7
")A: Macro Insert#"<
"="<
" uTask$S: WBS QuickPick"" uLayout"S: Options Form"
 uF5  uSearch6 uF6  uList$C: File Form%
" u(QuickPick)1")A: Macro List$
"="<
" uHighlight S: Select Filter"" uAlternate S: Res/Cost List!
 uF7  uFilter"C: Highlight 2$ uF8  uPERT$C: Gantt View$
")A: Highlight 3$" uLayout5
"="<
" uRecalc"S: Erase to End#" uAccept"S: Undo Last Chng  
 uF9 ,of Field/Line"uF10  uForm$C: Redo Last Undo  
"="<
"="<
$.PROBLEM
uProblem
sh
C*1*

$.STATS
uTime Line StatisticsD*DATEANDTIME(R)*
sh

Schedule file  : u*SCHEDULE*
Proj Directory : u*PROJECTDIR*
Pgm Directory  : u*EXEDIRECTORY* 
DOS Version": u*DOSVERSION*
MS Windows#: u*13*1
Serial number  : u*SERIAL*!
  
Tasks(: u*1(L)*%Resources!: u*2*
 
Currently available memory ("-Na-" means "None Available"):

  DOS ., : u*3*
  XMS UMB Free%: u*4*
$EMB Free/Total : u*5*/u*6* (Total free before Time Line ran)
  EMS Free/Total#: u*7*/u*8*
  HMA Free/Total#: u*9*/u*10*
VIDEO Free/Total#: u*11*/u*12*
+Quit,Memory Analysis,Run Line Parameters
=Quit,.MEMORYA,.RUNPARM
$.MEMORYA
uTime Line Memory Analysis  sDOS Memory: *3*
sh

You have u*3* of DOS memory available.  DOS memory is the storage on the
memory chips inside your computer located from 0 to 640K and is the
principal memory available to all executing programs and their data.

Increasing the amount of this kind of memory will increase the size of
schedules that will fit in Time Line and also improve the program speed.
Each 1K increase will allow approximately ten additional tasks.

sHow to increase DOS memory:
 Eliminate unnecessary TSR programs.
 Remove unused device drivers from your config.sys file.
 Reduce the BUFFERS in your config.sys file.
 Remove unneeded network drivers.  Time Line does not require NETBIOS.
 Avoid using large shell programs, such as Microsoft Windows (r).
 Use a memory manager such as QEMM, 386Max or LANSpace.

See Appendix C in the Time Line Manual for additional ideas.
/
uTime Line Memory Analysis  sXMS Memory: *4* UMB, *6* EMB, *9* HMA
sh

XMS memory is used by Time Line to store data and speed up the program.
It comes in three flavors: "HMA" (High Memory Area), "UMB" (Upper Memory
Area), and "EMB" (Extended Memory Blocks).

XMS storage is available to Time Line when you have a high-memory manager
installed such as the HIMEM.SYS program from Microsoft (included with
Time Line), or the QEMM (r) memory manager from Quarterdeck, or DOS 5.x.
Note: If HIMEM.SYS is used, however, the UMB is not available.

HMA and UMB memory increases the capacity of the Time Line program.
Time Line uses EMB as a disk cache to speed up the program.

You currently have u*4* of UMB memory left (not already in use), and
u*6* of EMB memory in use or available to Time Line.  If present,
HMA will have 64KB total available.  There is u*9* free HMA.
/
uTime Line Memory Analysis  sEMS Memory: *8*
sh

Expanded, or "EMS", memory is not as fast as conventional DOS memory, but
is still much faster than a mechanical disk drive, so Time Line uses this
to store data whenever it is available, greatly improving speed.

EMS memory is provided by add-in cards such as Above Board (from Intel)
and RAMPage Plus (from AST Research) or other LIM EMS compatible boards.

It is also provided by 386-memory managers such as QEMM and 386Max, and
is available under Windows 3.0 Enhanced mode.

You currently have u*8* of this memory installed and available to 
Time Line.
/
uTime Line Memory Analysis  sVideo Memory: *12*
sh

VIDEO memory increases the schedule capacity of the program.

VIDEO memory is memory "borrowed" from your video card.  If you have a VGA
or EGA card with at least 256KB of memory on it, Time Line can gain from
84 to 124KB of extra memory for its use.

The amount of VIDEO memory available to Time Line now is u*12*.

This memory is not available when you run under Windows (r), unless you
use the PIF file supplied with your Time Line program.  Using this PIF
file, Time Line, when run from under Windows, takes the full screen and
disallows the ALT-TAB key combination, so that this VIDEO memory will be
available to Time Line.
/
uTime Line Memory Analysis  sSummary
sh

Currently available memory ("-Na-" means "None Available"):
  DOS ., : *3*
  XMS UMB Free%: *4*
$EMB Free/Total : *5*/*6* (Total free before Time Line ran)
  EMS Free/Total#: *7*/*8*
  HMA Free/Total#: *9*/*10*
VIDEO Free/Total#: *11*/*12*

Appendix C in your Time Line Manual contains additional ideas for
increasing the memory available to the Time Line program and making it run
faster.

It also has suggestions for better configuring Time Line to run well with
a variety of network systems and programs such as Microsoft Windows, and
details about some specific hardware products.
/
uTime Line Memory Analysis  sXMSCHECK
sh
Your Time Line product is supplied with a program, XMSCHECK.EXE, that 
will analyze the available memory on your computer, perform a number of
reliability tests, and may recommend some options to improve capacity
or performance.  You may use this to test your computer hardware.

This program is located in the TL5\INSTALL directory.
><.CALLTEK
$.RUNPARM
uTime Line Run Line Parameters
sh

DISPLAY  IS u*(RUNPARM(DISPLAY))*

MACRO"IS u*(RUNPARM(MACROS))*

ADDIN"IS u*(RUNPARM(ADDIN))*

SWAPVOL  IS u*(RUNPARM(SWAPVOL))*

MEMSWAP  IS u*(RUNPARM(MEMSWAP))*

EMSPAGES IS u*(RUNPARM(EMSPAGES))*

PATH#IS u*(RUNPARM(PATH))*

USER#IS u*(RUNPARM(USER))*
$.SWAPDSK
  If you have EMS memory installed in your computer, you may be able
!to continue running this session of Time Line.
  This problem is caused by having insufficient space on the disk drive
!used for virtual memory swapping.  That drive is either the default
!drive on program startup, or (optionally) the drive given by the
!"SWAPVOL=" command line parameter.
  Time Line cannot continue running unless it has sufficient virtual
!swapping space.
/

What to do:

  Erase unneeded files from the swapping disk.  You may be able to use
!the "Utilities / Exit to DOS" command to do this.
  Quit Time Line, restarting it from a drive with more room.
  Quit Time Line, and restart it with a SWAPVOL=<roomier drive> option.
><.NETADMI
>.CALLTEK
$.TLSAMPL
WLSep1Oct 
W  Task Name%Task Type  Duration!Cost  4!11"18"25"2!
W A Product A%Summary"22 days!$8000  4"
W A"Design%ASAP%10 days!$1500  (.
W A"Manufacture  ASAP&8 days!$4000*&&
W A"Assemble#ASAP&4 days!$25002""
$.TRACK

uUpdating Hints=Print out with [Print Screen]

We recommend the following sequence when updating the schedule.

1. Change Force Future Tasks to "No", and Recalculation to "Manual" on 
!the Calculations Form.
2. If you are using a "manual" As-of Date, change the As-of Date to the
!date for which you are updating (Options Form).
3. Update the appropriate task information (using Assisted Update or
!the Needs Update filter).
4. Return Force Future Tasks to "Yes" on the Calculations Form, if desired.

A Status or Assignments Report, formatted as a turnaround document, helps
gather updated information.

  Group the report by resource to send to each team member, or by task
!if one person is responsible for all updating.
  Select columns such as percent achieved, duration, and end date.  Add
!blank columns ("B" following width) for any columns needing updates.
+Quit,Index,Force Future,Assisted Update,Needs Update
=Quit,Index,CALF1,ASSIUpd,FLTR14
$CALC1
uCalculator
sh
  Current value in field is placed in Calulator Form.  Change value by
!pressing [End], then entering operator(s) and number(s).
  Accepts the common arithmetic operators (+, -, *, /).
  Sequence of calculation: operations in parentheses, then multiplication
!and division, then addition and subtraction.
  When you leave ([F10] or [Enter]), result is placed in field.
+Quit,Index,Overview
=Quit,Index,CALC
$CALC
uCalculator
sh

Time Line has a built-in calculator that is accessed as follows:

  Press [F2] on a numeric field.
  The calculator appears as a one-line form.  The current field value is
!placed in the calculator as a starting entry.

  The following operators can be used in mathematic expressions.
!+ to add%- to subtract%* to multiply$/ to divide

  Multiplication and division are executed before addition and
!subtraction.  Operations in parentheses are done first, and can change
!the above order.  For example, "2 + 2 * 4 = 10" but "(2 + 2) * 4 = 16".
  Macros can take advantage of the calculator, with or without the form.
!For example, to multiply the current field by 2: {F2}{End}*2{F10}
  Math can be used in numeric fields (without using the Calculator).  For
!example, task duration could be entered "15 * 1.20".  (This would
!increase the current duration, 15, by 20 percent.)
+Quit,Index,Copy & Paste
=Quit,Index,COPYPAST
$CALENDAR
uCalendars
sh

Calendars control when work is scheduled.  The uMaster Calendar includes
the hours to be worked each day and dates to be worked through the year.
The uResource Calendars contain the periods of time each resource is
unavailable.

Several Time Line settings control whether a resource's unavailable time
is taken into account.  In general, however, for work to be scheduled:
  a work period must be available on the Workhours Calendar,
  the date must be a work date on the Dates Calendar,
  the resource must be available (the Resource Calendar).
+Quit,Index,Master Calendar,Resource Calendar
=Quit,Index,SCHEMas,RSRC5
$CALLPREP
uPreparing to Call Technical Support
sh

  If you encountered an error message, please try to record or remember
!the exact wording of the error message.
  If you encountered a problem after a certain series of events, try to
!record or remember the exact sequence that led up to the problem.
!If you are encountering memory problems, it would help the technician
!to know how much DOS memory was available before starting Time Line.
!Quit Time Line, enter sCHKDSK at the DOS prompt, note the last line.
  Know your computer's brand and model (and network brand and model if
!applicable).
  Please be in front of the computer when you call, with Time Line
!running, and with the schedule loaded.  Have a formatted disk available.
+Quit,Index,Sending Materials for Analysis
=Quit,Index,CALLSEND
$CALLSEND
uSending Materials to Symantec for Analysis
sh

If you mail a schedule to Symantec for analysis:

  In the Options Form [Sh/F6], set the As-of Date to "Manual" (the As-of
!Date will remain unchanged when the schedule is retrieved at Symantec).
  In a Journal Note [Alt/F2], record your name, daytime phone number, the
!description of the problem, and the sequence of events leading to the
!problem (method for reproducing the problem).
  Move the cursor to a specific task and/or spreadsheet cell if it will
!help illustrate your question or problem.
  Perform a File Save to save your Journal Notes and schedule options and
!settings.
  If your computer has a printer attached, go to the Utilities/Statistics
!screen and press [Print Screen].  Then press "R" to bring up the "Run
!Line Parameters", and press [Print Screen] again.  Include the printout
!among the items you mail to us.
/
If the technician requests them, please send these other files in addition
to the problem schedule file:

  sOther schedule files:  If the problem schedule contains links to
!other schedule files, send these other files as well.
  sTLCNFG5.DAT:  This file saves the global configuration options for
!Time Line, and is found in the \TL5 directory.
  sMacro Save File:  If the problem schedule uses macros, send the
!file in which the macros are saved when Utilities/Macro/Save is run.
  sAUTOEXEC.BAT and sCONFIG.SYS files:  Your computer uses these
!files to set itself up when you turn on the power.

These files can be placed on a diskette, or compressed with a file
compression utility (such as PKZIP), if uploading to the Symantec BBS.
$COLN
uColumn Names
sh

Time Line provides many different columns of data to describe tasks, such
as Task Name, Duration, and Proportional Percent Achieved.  User-specific
information can be entered, also, into any of 50 auxiliary columns.

Using the Custom Column Form ([F2] on column name), the name of the column
(plus associated information) can be changed:
   on the list
   on the Gantt view
   in reports
   in graphs.
$CONTOUR
uResource Contouring
sh

With resource contouring, you may specify that a task is to be worked on
only when the assigned resources are not working on higher-priority tasks.
You specify this condition by entering the following:
  Task Form,'sEffort in the Driven By field
4sSplit Assgn in the Unavail. field.
  Calculations Form, sYes in the Resource Leveling field.

For example, Bob is assigned 100% to a resource contoured task (Task A)
with three days of effort, scheduled to start on Monday.  He is also
assigned 50% to a higher-priority task (Task B) of two days, scheduled to
start Tuesday.  In this situation, Time Line:
  schedules Bob 100% to Task A on Monday
  schedules him 50% to both Task A and B on Tuesday and Wednesday
  schedules the remaining day of effort for Task A on Thursday.
$COPYPAST
uCopy and Paste
sh

You can copy information from one place, and paste it somewhere else.

  Copy a text or number field, and paste it into another field.
  Copy information from a layout column, and paste it into another column.
  Combine the above.  Copy field to column, or column to field.

Follow these steps to copy and paste form fields:

  Move to the field you want to copy, and press [Alt/C].
  Move to the other field, and press [Alt/V] to paste the information.

Follow these steps to copy and paste information from columns:

  Move to the cell (column and row) you want to copy.
  Press [F2] to edit the cell, then [Alt/C] to copy.  Press [Enter].
  Move to the other cell.
  Press [F2] to edit the cell, then [Alt/V] to paste.  Press [Enter].
$COST
uCosting
sh

Many factors can contribute to the cost of a project, such as:

  Resource assignments.
  Materials used.
  Equipment used and/or leased.
  Payments to outside contractors and vendors.

Time Line allows for the planning and tracking of all these costs, and
more.  Resources can be assigned a cost rate and the labor cost
automatically computed for each task.  Materials can be defined as uunit
ucosts  the cost per unit is defined, and a number of units allocated to
each task.  Similarly, Time Line allows entry of uvariable costs, such as
those associated with leasing, and ufixed costs, such as payments scheduled
for vendors and contractors.
+Quit,Index,Resources,Unit,Variable,Fixed
=Quit,Index,SCHERes,COSTU,COSTV,COSTF
$COSTF
uFixed Costs
sh

The fixed cost type is used to track miscellaneous project expenditures.

If the expense varies from task to task, and if it has no relationship to
the task's duration or a multiple of units, then it probably should be
defined as a fixed cost on the Resource/Cost Form.

To assign a fixed cost, pick its name from the Resource/Cost List.  Then,
on the Fixed Cost Assignment Form, enter a dollar amount.
$COSTU
uUnit Costs
sh

The unit cost type is used to track project materials, or any other
expense that can be calculated as a multiple of a basic unit.

If a "per unit" cost is known for a particular item, and the item can be
assigned to tasks as a multiple of that basic unit, then it should be
defined as a unit cost on the Resource/Cost Form.  Unit cost rates may
vary over time, and are changed on the Resource/Cost Form.

To assign a unit cost, pick its name from the Resource/Cost List.  Then,
on the Unit Cost Assignment Form, enter a number of units.  (The dollar
amount is calculated by multiplying the entered number of units by the
defined cost rate.)  Alternately, enter a dollar amount and have Time Line
calculate the equivalent number of units.
+Quit,Index,Varying Rates
=QUIT,INDEX,RSRC7
$COSTV
uVariable Costs
sh

The variable cost type is used to track periodic project expenditures.

If an expenditure has a direct relationship to the task's duration (such
as rental fees) and a periodic rate is known, then it should be defined as
a variable cost.  The rate of a variable cost can change over time, and
are changed on the Resource/Cost Form.

To assign a variable cost, pick its name from the Resource/Cost List.
Then, on the Variable Cost Assignment Form, enter a number and percentage
of assignment (usually 1 @ 100%).  (Time Line calculates the dollar amount
by multiplying the entered number/percentage by the defined cost rate and
the current duration of the task.)  Alternately, enter a period of time,
and have Time Line calculate the equivalent percentage of assignment.

wCAUTION: If variable costs are assigned as a period of time, the cost
'will not automatically vary as the task duration is changed.
'Only the percentage of assignment will vary.
+Quit,Index,Varying Rates
=QUIT,INDEX,RSRC7
$CRITPATH
uCritical Path
sh

Critical path is a key concept in project management.  It is defined as a
sequence of tasks that must be completed on time to meet the project
deadlines.  In other words, tasks on a critical path have no slack.
Delays in finishing them affect the end of the schedule or the start time
of a subsequent task marked as "Force Critical".

  u-& CRITICAL -&#-' NONCRITICAL -&
  Phase 1$C )#Phase 1&-  u<Ŀ
"Design#C -Design%,u  slack
"Machine"C"*Machine')u"
"Fabricate  C%#%Fabricate(#"  u<
"End&C*$End&C.

  Select default setting for "Force Critical" on Options Form.
  Change "Force Critical" for an existing task with the Force Critical
!column.
+Quit,Index,Options Form,Force Critical Column
=QUIT,INDEX,OPTN10,$TCOL112
$CURSOR
uCursor Movement
sh

Time Line provides several different areas for working.

  Menus
  Forms
  Lists
  Gantt Spreadsheet area
  Gantt Task Bar area and Histogram view
  PERT and Work Tree views

Since each of these areas provides different capabilities, several charts
of important keys are provided.  Select your choice from the menu below.
+Quit,Index,Menus,Forms,Lists,Sprdsht,Task Bar,PERT
=Quit,Index,CMENU,CFORM,CLIST,CSS,CBARS,CPERT
$CMENU
uMenus

><.CHDG
[Right Arrow]  Moves to the next menu item.
[Down Arrow] !"""  """""""
[Spacebar]  !"""  """""""
[Left Arrow]  Moves to the previous menu item.
[Up Arrow]  !"""  """&"""
[Backspace]  !"""  """&"""
[Enter]     Selects the highlighted menu item.

[1st Ltr of   Immediately selects menu item starting with that letter.
 menu item]
$CFORM
uForms

><.CHDG
[Enter]     Moves ahead 1 field.
[Down Arrow] !"#"!"!"
[Up Arrow]   Moves back 1 field.
[Right Arrow]  In text, right 1 character; in mult choice, 1 selection.
[Ctl/Right]   In text, right 1 word; in mult choice, to last selection.
[Left Arrow]  In text, left 1 character; in mult choice, 1 selection.
[Ctl/Left]   In text, left 1 word; in mult choice, to first selection.
[Tab]      Moves forward 1 section.
[Sh/Tab]    Moves back 1 section.
[Home]     Moves (1) 1st char, (2) 1st of section, (3) 1st of form.
[End]      Moves (1) last char, (2) last of section, (3) last of form.
[Ins]      In text, toggles from insert to overwrite mode.
[Del]      In text, deletes current character.
[Sh/F9]     In text, deletes to end of field.
[F10]      Saves changes and exits form.
[Esc]      Cancels changes and exits form.
$CLIST
uLists

><.CHDG
[Down Arrow]  Moves down 1 name.
[PgDn]    !"""!1 window.
[End]     !"""!to last name in list.
[Up Arrow]   Moves up 1 name.
[PgUp]    !"!"  1 window.
[Home]    !"!"  to 1st name in list.
[Enter]     Select the cursor name.
[F10]     """"#"#"
[Esc]      Cancel list, no pick.

[1st Ltr(s)   Jumps to first name starting with the entered letter(s).
 of Name]&(QuickPick)
[Backspace]   Backs up 1 letter during QuickPick
$CSS
uGantt View: Spreadsheet Area$(Pressing [Tab] jumps to Task Bar area.)

><.CHDG
[+]       Opens and reveals children of cursor task.
[-]       Closes and hides children of cursor task.
[*]/[+]     Opens entire family.
[*]/[-]     Closes entire family.
[*(CODE(\42))*]/[*]/[+]   Opens all families at all levels for entire outline.
[*(CODE(\42))*]/[*]/[-]   Closes all families at all levels for entire outline.

[Sh/Left]    Outdents cursor task.
[Sh/Right]   Indents cursor task.
[Sh/Up]     Moves cursor task up 1 line, within current family.
[Sh/Down]    Moves cursor task down 1 line, within current family.
[*]/[Sh/Up]   Moves cursor task to top of current family.
[*]/[Sh/Dn]   Moves cursor task to bottom of current family.
Note: Use Shift with numeric keypad arrows, or the numbers 8 (up),
$2 (down), 4 (left), and 6 (right).
/
><.CHDG
[]       Moves up 1 task.
[]       Moves down 1 task.
[*]/[]     Moves to first task in outline.
[*]/[]     Moves to last task in outline.
[PgUp]     Moves up 1 screen.
[PgDn]     Moves down 1 screen.
[Ctl/PgUp]   Moves up 1 task at current level (jumps over details).
[Ctl/PgDn]   Moves down 1 task at current level (jumps over details).
[*]/[PgUp]   Moves to first task at current level.
[*]/[PgDn]   Moves to last task at current level.
[Home]     Moves to cursor task's parent.
[*/Home]    Moves to first task in outline.
[End]      Moves to last task at same level, then next indent level.
[*]/[End]    Moves to last task in outline.
$CBARS
uGantt View: Task Bars Area  (These keys also apply to the Histogram view.)

><.CHDG
[Ctl/Home]   Jumps to As-of Date line (stays on current task).
[Ctl/End]    Jumps to beginning (then end) of current task bar.
[Right Arrow]  Moves right 1 time period - depends on scale.
[Ctl/Right]   Moves right 1 larger time period (week, month, year).
[Left Arrow]  Moves left 1 time period - depends on scale.
[Ctl/Left]   Moves left 1 larger time period (week, month, year).
[Tab]      Jumps to Spreadsheet area.
[Sh/Tab]    Always jumps to Spreadsheet area (even if already there).

Since Time Line synchronizes the Histogram view with the Task Bar area of
the Gantt view, these keys apply to both views.
$CPERT
uPERT and Work Tree Views

><.CHDG
[Tab]      Moves right task by task.
[Right Arrow] !"#"!1 column.
[Ctl/Right]  !"#"! screen.
[Sh/Tab]    Moves left task by task.
[Left Arrow] !"#"  1 column.
[Ctl/Left]  !"#"   screen.
[Up Arrow]   Moves up 1 row.
[Ctl/PgUp]  !"!"   screen.
[Down Arrow]  Moves down 1 row.
[Ctl/PgDn]  !"""! screen.
[Home]     Jumps to parent task.
[Ctl/End]    Jumps between start and end summaries in Traditional style.

All Gantt menus and function key shortcuts are available on PERT and Work
Tree views as well.  Press [/] for menus and [F1] for shortcuts.
$DEPENS
uDependency Instructions
sh

Action"Key:Procedure
% & W
Set#u[F3]#Mark predecessor (move to it and mark by pressing
/[Spacebar] once) or successor ([Spacebar] twice), then
/move to other task and press [F3].
Delete  u[Ctl/F3] Mark predecessor or successor, then move to other
/task and press [Ctl/F3].  (Or [Del] on Dependency List.)
Partial u[Sh/F3]  Mark predecessor or successor, then move to other
/task and press [Sh/F3].  (Or [F2] on Dependency List.)
Review  u[F4]#Display in list (also allows deleting & editing).
&u[Sh/F4]  Display predecessors/successor in colors.
PERT"u[Ctl/F4] Review dependencies in PERT view.
$DRIVENBY
uDuration- and Effort-driven Tasks
sh

Time Line keeps track of both duration and effort for each task.  Duration
is the length of time (calendar time) the task is scheduled to occur;
effort is the amount of work (resource assignments) to be done on the task.

  Mark a task "duration-driven" if you want to estimate the task timing
!in terms of a number of days in the work schedule.
  Mark a task "effort-driven" if you know the number of work hours the
!task requires, and want Time Line to calculate the duration.
  Split Spent/To Go Effort (Calculations Form) schedules completed work
!("spent" on Assignment Form) in the past, and uncompleted ("to go") in
!the future, producing a more realistic schedule.
  uCAUTION:  Time Line cannot schedule a duration-driven task if a
!resource is assigned at a greater percentage that its maximum
!availability.  When lowering availability on the Resource/Cost Form,
!check current assignments to avoid this condition.
+Quit,Index,Split Effort
=Quit,Index,CALF4
$EDITHELP
uNotepad
sh

  Move around the notepad, and control editing, with the following keys.

[Ctl/]  Move one word to right&[Tab]!Indent line
[Ctl/]  Move one word to left'[Ins]!Toggle insert/overstrike
[Home]"Beginning of line, then note  [Del]!Delete character
[End]#End of line, then note&[F3]"Delete current line
[PgDn]"Down one page/[Sh/F9] Delete to end of line
[PgUp]"Up one page1[F9]"Reformat paragraph

[F10]#Save changes and exit'[F7]"Read in an ASCII file
[Esc]#Abandon changes and exit$[F8]"Write out an ASCII file

  The contents of the notepad can be printed by writing out a file [F8],
!using the filename PRN (parallel printer).  When asked about over-
!writing the file, answer "Proceed".  Add an ASCII-12 character at any
!point in the note that you wish the printer to feed to top-of-form.
+Quit,Index,Report Heading Keywords
=Quit,Index,HDGCODES
$ERASE
uErase
sh

There are two distinctly different erase commands.

  File/Erase permanently removes a schedule (or other file) from disk.
  Schedule/Erase removes a schedule from memory, but does not affect the
!file on disk.
!sNOTE: If the schedule has not been saved to disk, Time Line prompts you
'to do so before erasing it from memory.
+Quit,Index,File/Erase,Schedule/Erase
=Quit,Index,FILEEra,SCHEEra
$EXTRACT
uFILE:  Extract
sh

Extract is an option of File/Save.  It saves a portion of your schedule
as a separate file, under a new name.  You can extract a family of tasks
or extract just those tasks currently shown with a select filter.

  To extract the current family:
! Position the cursor on the parent task.
! Select File/Save (Extract).
! On the File Save Form, enter a new filename.
! On the File Extract Form, change Tasks to "Cursor Family".
  To extract the tasks currently shown with a select filter:
! Choose a select filter name from the Select Filter List [Sh/F7].
! Select File/Save (Extract).
! On the File Save Form, enter a new filename.
! On the File Extract Form, change Tasks to "Entire Outline".
  To extract a portion of the WBS, place cursor on parent of family to
!extract, select Current Family.  Or select filter for portion of WBS.
  To reverse the process, use File/Combine.
+Quit,Index,File/Combine
=Quit,Index,FILECom
$FIELDS
uField Name1Form(s)
s4%K
Achievement0Task, Filter
Actual Effort/Cost, Use$Cross Tab Rpt, Histogram Rpt
Actuals, Entry of*Assignment (off of Task Form)
Advance to New Page(Gantt Rpt, Page Control (after rpt forms)
As-of Date1Options
Assignment1Task, Assignment Rpt, Status Rpt, Export,
;Import
Assignment, Default(Resource/Cost
Availability Profile'Resource/Cost
Baseline Bar, Show)Layout, Gantt Chart
Calculate Negative Slack#Calculations
Column Name0Layout, PERT Layout
Cost Rate2Resource/Cost
Cost Tracking.Options
Critical Path.Filter
Date Display/Options
Date Formatting,Configure / Date Formats menu
Date Range1Filter
Default Assignment)Resource/Cost
Dependency1Dependency, Export, Import
Dependency Lines+PERT Chart
Directory2File, File Access, File Save
Disk Filename.Report
DOS Filename/File, File Access, File Save
Driven By2Task
Duration3Task
Effort5Task
End Date3Task, Filter
End Dates, Format*Calendar Settings
Export Directory+Export
Export Format.Export
File Extension-Export, Import
Filter Name0Filter
Filters, Print Active&Report
Force Critical-Options
Force Future Tasks)Calculations
GRAPHICS
  Autoscale0Chart Size
  Borders2Gantt Chart
  Corners2Gantt Chart
  Horizontal Grid*Gantt Chart
  Legend3Chart Title
  Notes Area/Chart Title
  Palette Name-Gantt Chart, PERT Chart
  Preview on Screen(Chart Size
  Reduce/Enlarge to(Chart Size
  Resize to0Chart Size
  Spacing, Extra+Gantt Chart
  Task Bar Labels*Gantt Chart
  Task Boxes/PERT Chart
  Title & Legend+Gantt Chart, PERT Chart
  Title Area/Chart Title
  Vertical Grid,Gantt Chart
Highest Priority+Calculations
Honor Resource Calendars#Calculations
Import Directory+Import
Import Format.Import
Keyword4Task, Filter, Resource/Cost
Late, Predicted,Filter
Layout Name0Layout, PERT Layout, Gantt Chart, PERT Chart
Legend5Chart Title
Level this Resource?'Resource/Cost
Link to file/Task
Loop, Involved in*Filter
MACROS5Macro Menu
  Dialog Message+Macro Message
  Dialog Title-Macro Message
  Description.Primary Macro, Secondary Macro
  HotKey3Primary Macro, Secondary Macro, Macro Config
  Macro File/Macro File
  Menu Choices-Macro Menu
  Menu Message-Macro Menu
  Menu Prefix.Macro Menu
  Name5Primary Macro, Secondary Macro
  Path5Macro File
  Playback Speed+Macro Configuration
  Step Mode0Macro Configuration
Margins4Report
Maximum for Leveling'Resource/Cost
Milestones1Filter
Needs Update/Filter
Notes6Task, Resource/Cost, Layout, Filter, Options,
;PERT Layout, Detail Rpt, Chart Title
Notes, Print Options Form"Report
OBS8Task, Filter
Output Format.Report
Output to, Send,Report
Partial Dependencies'Dependency, Filter
PERT
  Box Outline.PERT Layout
  Box Placement,Options
  Dependency Lines)PERT Chart
  Layout Name.PERT Chart, PERT Layout
  Periodic PERT,PERT Chart
  Style4Options
Precision2Calendar Settings
Predecessor0Dependency, Detail Rpt
Pred/Succ Task Names'Detail Rpt
Predicted Late-Filter
Previous Schedule*File
Priority3Task
Priority, Highest*Calculations
Progress Data.Layout
Recalculation.Calculations
Reimport, Verify+Export
REPORTS
  Column Data.Resource Rpt
  Column Headings*Page Control (after rpt forms)
  Column Spacing+Page Control (after rpt forms)
  Daily Reporting Period#Status Rpt
  Date Range/Gantt Chart, Gantt Rpt, Assignment Rpt,
;Cross Tab Rpt, Histogram Rpt
  Filters, Print Active$Report
  Grid5Gantt Rpt
  Group by1Assignment Rpt, Detail Rpt, Status Rpt
  Heading2Report
  Headings/Legend*Gantt Rpt
  Ignore Left Margin'Page Control (after rpt forms)
  Include Past Due Tasks#Status Rpt
  Include Task Parentage#Status Rpt
  Margins2Report
  Monthly Reporting Period!Status Rpt
  Notes, Print Options Form  Report
  On-screen Res Histograms!Histogram Rpt
  One Task per Page(Detail Rpt
  Output Format,Report
  Page Breaks.Detail Rpt, Gantt Rpt, Page Control
  Page Footings,Page Control (after rpt forms)
  Page Headings,Detail Rpt, Page Control (after rpt forms)
  Period3Cross Tab Rpt, Histogram Rpt
  Print Zeros as+Page Control (after rpt forms)
  Report Data.Cross Tab Rpt, Histogram Rpt
  Report on (Res, Costs)#Cross Tab Rpt, Histogram Rpt, Resource Rpt
  Report Periods+Status Rpt
  Resource Columns)Assignment Rpt
  Resource Grouping(Assignment Rpt, Detail Rpt, Status Rpt
  Row Headings-Page Control (after rpt forms)
  Row Spacing.Page Control (after rpt forms)
  Send Output to+Report
  Show as Hourly Rate&Cross Tab Rpt, Histogram Rpt
  Show (Resources,Costs)#Assignment Rpt, Status Rpt
  Spacing2Gantt Rpt
  Suppress Section Headers!Detail Rpt
  Task Columns-Assignment Rpt, Status Rpt
  Task Data0Detail Rpt
  Total by Column*Cross Tab Rpt, Histogram Rpt
  Total by Row-Cross Tab Rpt, Histogram Rpt
  Unlimited Page Width%Page Control (after rpt forms)
  Weekly Reporting Period"Status Rpt
Resource Calendars, Honor"Calculations
Resource Leveling*Calculations
Resource vs. Time*Export
RESOURCES
  Availabilities+Resource/Cost
  Calendars0Resource/Cost
  Conflict1Filter
  Full Name0Resource/Cost
  Keyword Contains)Filter
  Leveling1Calculations
  Name5Resource/Cost
  Rate5Resource/Cost
  Resource1Histogram Resources
  Resource/Costs+Task, Filter, Export, Import
  Type5Resource/Cost
Responsible0Options
Scale6Layout, Gantt Chart
Schedule Name.Options
Slack Display.Layout
Sound6Configure/Sound
Split Spent/To Go Effort#Calculations
Standard Week Begins'Calendar Settings
Standard Year Begins'Calendar Settings
Standard Workday+Calendar Settings
Standard Workweek*Calendar Settings
Start Date1Task, Filter
Start Date Restriction%Options
Status5Task
Successor2Dependency, Detail Rpt
Task7Export, Import
Task Bars, Show,Layout
Task Form2Options
Task vs. Resource*Export
Task vs. Time.Export
TASKS
  Name5Task, Filter, Detail Rpt
  Type5Task
Undo/Redo Limit,Options
Unit of Measure,Resource/Cost
Update, Needs.Filter
Vacation Calendars)Resource/Cost
WBS8Task, Filter
Width6Layout, PERT Layout
$FIRSTAID
uGetting Started
sh

Welcome to Time Line Project Management Software.
May we take a few moments to help you get started?  We'll show you:

  How to use the Time Line tutorial.
  How to get help while using Time Line.
  How to begin a new schedule.
  How to set up for your monitor, your printer, and for graphics.

sNOTE: This Startup Help message appears each time you start Time Line
$UNTIL you save a schedule.  If you wish to review the material after
$saving a schedule, select "Startup Help" from the Help Index [Sh/F1].

(To print a screen to your printer, press the Print Screen key.)

To ucontinue with this section, press uM or the [Enter] key for More.
To ustart using Time Line,$press uQ for Quit.

/
uUsing the Time Line Tutorial
sh

The Time Line Tutorial is an excellent introduction to the product.  It
guides you through commonly-used areas of the program and shows you how to
perform routine tasks, while it catches your mistakes.  The tutorial
increases the confidence with which you'll approach your first Time Line
scheduling.  You can proceed at your own pace, and review at any time.

To run the tutorial:

  From the Main Menu, select Assist.
  From the Assist menu, select Tutorial.
  Follow the on-screen instructions given by the tutorial.

/
uGetting Help While Using Time Line
sh

When you start learning Time Line, much will be new.  As you progress, you
may need a reminder now and then.  In both circumstances, help is as close
as the [F1] key.

u$"Press it on a umenu selection for an explanation of that area.
u  F1  "Press it on a uform field for a description of that field.
u$"Press it just about uanywhere in Time Line for a helpful hint.

While reading the Help screens, you may want to explore the related topics
offered at the bottom of the screen.  Just pick them from the menu.

There's even an index of important topics.  [Sh/F1] gets you there.

u#ҷ!$"Press it to pop up an ualphabetized list of topics.
uShift +   F1  "Press it from uanywhere in Time Line.
u#ʼ!$"Return to your starting point by pressing u[Esc].

/
><AssiNew

/
uQuickPlan and QuickGraph
sh

uQuickPlan  allows you to automatically generate a Time Line schedule
(for use with QuickGraph.  The QuickPlan macro guides you
(through a custom menu system to create project tasks.

  To load from the Main Menu, select Utilities/Macros/Load.  Select the
!macro named QUICKPLN.5M0.  
  To run the QuickPlan macro, press [Alt/Q].

uQuickGraph allows you to create a presentation quality chart quickly.
(You may use an existing schedule or one created by QuickPlan.

  From the Main Menu, select Utilities/Macros/Load (QUICKGRP.5M0).
  To run the QuickGraph macro, press [Alt/Q].

sNOTE:  QUICKPLN.5M0 and QUICKGRP.5M0 are located in the directory
%from which you started Time Line.  In most cases, this is C:\TL5.

/
uSetting Up for your Monitor
sh

As shipped, Time Line is ready to run on an IBM PC or compatible with a
color monitor.  If you wish to change your monitor setup, you can do so
by following these introductory messages.

To change your video settings:

  Press u/ to bring up the Main Menu.
  Select uConfigure.
  Select uVideo.
  Select your computer type.
  Specify whether your monitor can display colors or not.  (If you have
!a mono graphics monitor, select Monochrome.)
  For the remaining options, follow the instructions under the menus.
  When asked if you are finished setting up Video, answer uYes.
  To save your video setup permanently, press u/ (for Main Menu),
!uF (for File), uS (for Save), uO (for Options Only).

/
uSetting Up for your Printer
sh

Following these introductory messages, let Time Line know what printer
you are using.

To set up for your printer:

  Press u/ to bring up the Main Menu.
  Select uConfigure.
  Select uPrinter.
  Select your printer from the list.  Press [F1] for help in moving
!around the list and selecting your printer.  If your printer doesn't
!appear in the list, select one it emulates or "DOS ASCII printer".
  If your printer is connected to your computer's first parallel port,
!press u[F10] to complete printer setup.  If connected to another port,
!change the Setup Communications Form and press [F10].
  To save your printer setup permanently, press u/ (for Main Menu),
!uF (for File), uS (for Save), uO (for Options Only).

/
uSetting Up for Project Presentations
sh

If you have a graphics monitor, Time Line can display two types of charts
on screen.  The charts can be output to laser and dot matrix printers, and
to plotters.

To set up to print graphics:

  Press u/ to bring up the Main Menu.
  Select uConfigure.
  Select uGraphics.
  Select your printer or plotter from the list.  Press [F1] for help
!in moving around the list and making your selection.  If your printer
!or plotter doesn't appear in the list, select one it emulates.
  Fill out the Graphics Setup Form and Setup Communications Form.
!Press [F1] for an explanation of each field.
  To save your printer setup permanently, press u/ (for Main Menu),
!uF (for File), uS (for Save), uO (for Options Only).

/
uThe Next Steps
sh

You have several options now, after reading this Startup Help.

  Go through the tutorial.
  Continue this introduction by selecting "Time Line Intro" (menu below).
  Quit this startup help (press [Enter]) and configure for your hardware.
  Quit, and enter your first schedule (use "Assist / New Schedule").
  Review these startup instructions  select "Index" from the menu below,
!then select "Startup Help" from the index list.

Please remember that the following learning aids are available.

  The [F1] (Help) key, available while using Time Line.
!(For key lists, select "Hints for Using Time Line" from the Help Index.)
  The Quick Reference Card, shipped with your product.
  The Discussion and Procedures sections of the Manual.
  Symantec Corporation training and consulting services.
  Other Time Line users in your organization.
+Quit,Index,Time Line Intro
=Quit,Index,TM.INTRO
$GANTTEXT
uGantt View7Press [Enter] for Function Key Template
558
sImportant Keys:& sTask Bar Symbols:# sStatus Column Codes:
 u[/]#Menus'  u" Future summary    u? Needs recalc [F9]
 u[Ins]!Insert task!  u== Started!"#  uC Critical path task
 u[CtlF2] Edit task#  u=" Done$"#  uR Resource conflict
 u[Del]!Delete task!  u" Future detail!  ur Delayed by leveling
 u[F6]"Change Layout   u Started!"#  up Partial depend predcsr
 u[F7]"Highlight#  u" Done$"#  us Partial depend succesr
 u[Spcbr] Set "P","S"!5  uL Dependency loop
 u[F3]"Set depndency   u" Fixd task delay 
 u[AltF8] Histogram#%or Neg. slack!
sMove:0  u Slack (float)! sColors:
 u[/]#1 task$  u.. Resource delay    w Highlight 1 [F7]
 u[PgDn/Up] 1 screen"  u"Milestone%  y Highlight 2 [Ctl/F7]
 u[Home]"To parent!5  { Highlight 3 [Alt/F7]
 u[Ctl/Hm]  To as-of dt   u" Baseline task!  s Predecessr [Sh/F4]
 u[Ctl/End] To task bar   u Started bsln"  u Successor  [Sh/F4]
 u[Tab]#sprdshtbars5
558
$HINTS
><TLHint
/
><GANTHint
/
><HISTHint
/
><PERTHint
/
><TREEHint
/
><.TRACK
$HISTO
><HISTTEXT
//
><.HKEYS
//
>VIEWHis
$HISTTEXT
uHistogram View3Press [Enter] for Function Key Template
5P
sImportant Keys:& sResource Name Display:
 u[/]#Menus'  WName%In Use&Avail0
 u[Ins]!Insert task!  Freds(1)"Task: 0.5s(2)  Unavail.s(4)
 u[CtlF2] Edit task#+Day : 1  s(3)  1 @ 100%s(5)
 u[Del]!Delete task!  B
 u[F6]"Change layout   s1: Resource name
 u[Sh/F7] Select filter   s2: Assignment to current task
 u[F8]"Histogrm form   s3: Assignment to all tasks, this time period 
 u[AltF8] Histogram of    s4: Resource unavailability, this time period!
'current task    s5: Resource availability, this time period
sMove:0P
 u[/]#1 task$ sHistogram Colors:& sGantt Colors:
 u[/]#1 date col   [  ][  [  s1: Scheduled# w Hilight 1 [F7]
 u[Ctl//] Severl cols  [_YAY_[_ s2: Overscheduled  y Hilight 2 [Ctl/F7]
 u[Ctl/Hm]  To as-of dt   s#  s3: Current task   { Hilight 3 [Alt/F7]
 u[Ctl/End] To task bar   s12345  s4: Avail. less! s Predecessr [Sh/F4]
5's5: Unavailable! u Successor  [Sh/F4]
5P
+Quit,Index,Gantt Symbols,Availability,Unavailable
=Quit,Index,TM.GANTT,RSRC6,RSRC5
$INSTR
uUsing the Help Index
sh

The Help Index is an alphabetized list of major Time Line functions
and services.

uYou can move around this list quickly:
>.PICKLIS
$LAPTOPS
uUsing Time Line on a Laptop
sh

  The lack of a numeric keypad on most laptops means that you will have
!to use the number key equivalents to the shifted arrow combinations:

!INSTEAD OF"TYPE(TO
  *!"".
![Sh/Up]&8$move a task up
![Sh/Down]$2$move a task down
![Sh/Right]#6$indent a task
![Sh/Left]$4$outdent a task
![Sh/Ins]%0$copy a task

  Configure/Video:  With a non-Compaq mono VGA laptop, configure for
!IBM "compatible", Monochrome, VGA.
$LAYOUTS
uLayouts
sh

Layouts control the appearance of information on the screen and, to some
extent, on reports.  The Gantt, PERT, and Work Tree views are each
controlled by a layout.  For more information, select an option below.
+Quit,Index,Gantt Layout,PERT and Work Tree Layout
=Quit,Index,SCHELay,20800
$LOOP
uDependency Loop
sh

A loop is a circular chain of dependencies:  (A  B  C  A)

When this condition occurs, Time Line is unable to compute the schedule.

  Task A%&0A loop would be caused by joining
  Task B-&(Task C (as a predecessor) to Task
P Task C5&  A (as the successor).

If Recalc is set to "Automatic" (Options Form), the loop is detected
immediately.  Press Undo [Sh/F10] to remove the loop.

If Recalc is set to "Manual", Time Line does not detect the loop until the
schedule is recalculated [F9].  Using Undo, you will have to recalc after
each Undo to find where the loop was introduced.  Alternately, use one
of the loop detection techniques described on the next screen.

/
To locate tasks in a loop:

  Display the Status column - tasks in a loop are marked "L".
  Filter for tasks "involved in a loop".
  Display Dependency List for last changed task - tasks in loop have "L".
  Change to PERT view - view isolates tasks in loop.

You must clear the loop before continuing to build or modify the schedule.
$MACROHNT
uHints for Using Macros
sh

The following techniques will help your macros operate more efficiently.

  Start the macro at an easily-remembered place  with your cursor on the
!task you want to change, for instance.
  End the macro in a way that prepares for a repeat of the macro  by
!moving down to the next task, for instance.
  On forms, reset any fields that might have changed between uses of the
!macro.  Better to be safe than sorry; reset a field if you're not sure.
  In multiple-choice fields, select by pressing the first letter.
! [Ctl/Left] always jumps to first choice; [Ctl/Right] to last.
  For spreadsheet editing, press [Sh/Tab] to make sure the macro starts
!in the Spreadsheet area.
  For report macros, create layouts (and filters) to be used ONLY for
!reports.  Select them as part of the macro.
  uAdvanced: Use a Journal Note as a log for long macros.  At various
+points, press [Alt/F2], edit a "Log" note, go to end, make
+entry.  Review when macro completes.
$MULTI
uMulti-project Scheduling
sh

The Outline feature facilitates multi-project scheduling.  You can con-
solidate several schedules with File/Combine, analyze their interactions
and reschedule where necessary, then save the individual jobs separately
using File/Save (Extract).  In addition to the outline, you will find the
following features useful.

  uPriority*to favor particular projects.
  uJournal Notes%to record conflicts with other schedules.
  uLayouts and Filters to highlight particular projects.
  uKeyword, WBS, OBS!to code project groupings.
  uResource Leveling!to resolve cross-project resource conflicts.

A full description of multi-project scheduling is contained in Chapter 18
of the Time Line Manual.
$NETVIEW
>TM.NETW
$NOTES
uNotes
sh

In scheduling, it is critical to communicate information about the project
to others.  To help with this, Time Line provides notes as a way of
annotating tasks, resources, reports, and many other components of the
schedule.  Notes may be permanently attached to:

  Tasks
  Resource/cost names
  Layout names
  Filter names
  The schedule as a whole (printed as part of the report heading)

In addition, free-floating Journal notes can be made from anywhere in the
program.  The names of Journal notes are maintained in an outlined list.
+Quit,Index,Task Notes,Journal Notes
=Quit,Index,TASKNot,SCHEJou
$OUTLINE
uOutline
sh

Time Line uses an outline to organize groups of tasks.  Each related task
group can have a summary task, that automatically represents a consoli-
dation of the group.  As you see in the example below, summary tasks hold
the summarized timing, cost, and resource assignments for all tasks
indented beneath them.

><.TLSAMPL

This outlining can be carried as many levels deep as necessary to fully
represent the complexity of the project.
+Quit,Index,Components
=Quit,Index,OUTLCOM
$OUTLCOM
uComponents of the Outline
sh

An outline of tasks contains the following components:  parent, child,
summary, detail.  A parent task summarizes its child tasks.  A child is
summarized by its parent.  A summary task summarizes at least one other
task.  A detail task does not summarize other tasks; it has no child tasks.
A family is a parent task, all its children, all their children, and so on.

UParent&Child
Families  W-Sep%Oct  Summary Detail Of*Of
&  W Task Name#4!18"2    % $ *- #
 %W AProduct A#)  #*)All Others"None 
 &W A  Design$#&**"None(Prd A
 !!W A  Manufacture$""#*)Setup,Machine Prd A
 !"W A"Setup(%**"None(Manuf
 !!W A"Machine'"**"None(Manuf
 %W A  Assemble+  **"None(Prd A
$PERTTEXT                   
uPERT and Work Tree Views)Press [Enter] for Function Key Template
558
sImportant Keys:& sSymbols:, sColors:
 u[/]#Menus'  uͻ/  wͻ Highlight 1 (F7)
 u[Ins]!Insert task!  u  "Detail task    wͼ
 u[F2]"Edit task#  uͼ/  yͻ Highlight 2 (Ctl-F7)
 u[Del]!Delete task!  uNameͻ,  yͼ
 u[F6]"Change layout   u# Summary task   {ͻ Highlight 3 (Alt-F7)
 u[F7]"Highlight#  u#,  {ͼ
 u[Spcbr] Set "P","S"!  u+"+-  sͻ Predecessr (S-F4)
 u[F3]"Set dependncy   uName  Summary task   sͼ
 u[+]#Open summary    u+"+"(closed)!  uͻ Successor  (S-F4)
 u[-]#Close summary   uͻ ͻ*  uͼ
sMove:0  u  ĺ   Dependency   Bͻ Current task
 u[Arrows]  Around scrn   uͼ ͼ*  Bͼ!(cursor)
 u[Tab]#Task to task5  A
 u[Home]"To parent!5 
 u[Ctl/End] Betw parents5 
558
$PleaNot
uLinking
sh

Time Line cannot find the linked schedule file you have specified on the
Task Link Form.

You have three options:
  uNot Available stops looking for the linked file; uses task data
/obtained when schedule last linked.
  uReady'tries establishing the link again; this option could
/be used when linked schedule is on diskette.
  uSkip(passes over this link; will try again after all other
/links have been checked.
$PleaRead
>PleaNot
$PleaSkip
>PleaNot
$Q&A
uCommon Questions and Answers
sh

uQ: Why don't the Shift/Arrow key combinations work on my computer?
A: On keyboards with two keypads, you must use the numeric keypad, not the
!separate arrow keys.  On laptops, you may need to use these numbers:
!8 [Sh/Up], 2 [Sh/Dn], 4 [Sh/Lft], and 6 [Sh/Rt].
uQ: When I press [F2] to edit a task or [Ins] to add one, I get the Task
!uForm at times, but not always.  Why is that?
A: When editing a task [F2], the Task Form appears when the cursor is in
!the task bars area.  When it's in the spreadsheet area, the current
!column is edited at the top of the screen.  (Change between these two
!areas with [Tab].)  To be assured of getting the Task Form, edit the
!task with [Ctrl/F2].
#When adding tasks [Ins], you get the Task Form whenever the cursor is
!in the task bars area, or in any column OTHER than Task Name.  With the
!cursor in the Task Name column, a blank Task Name field is presented at
!the top of the screen.  Other task data is then added in other columns.
uQ: How do I print a report on the printer?  It just goes to the screen.
A: Press [/], then [R], and [F].  Change the first field to Printer.
/
uQ: Why is a task being pushed out in time?  The start date I entered on
!uthe Task Form is still there, but the task is being scheduled later.
A: Other factors may be affecting the start date.  Is a predecessor
!pushing out the task's start date?  (Check with [F4].)  If so, you can
!force the task to start on the entered date by adding the Start Date
!Restriction column to the current layout, and changing it to "Must
!Start".  Is Resource Leveling on?  If so, a resource overload may be
!delaying the start of the task.  Try increasing the task's priority.
uQ: How do I change the display width of the task bars?  How do I change
!uthe Gantt date scale?
A: Press [F6], then [F2].  Change the layout name to save both old and new
!scales (or leave the name as-is to just change the current layout).
!In the Scale field, enter a larger time period to shorten the bars or a
!smaller time period to lengthen the bars.  Press [F10], [F10].
uQ: My summary bar doesn't show achievement (broken bar), even though some
!uof its detail tasks are done.  Why not?
A: You may need to change the way Time Line rolls up achievement to
!summary tasks.  On the Calculations Form (Schedule/Calculations), press
![F1] on the Weighting field, and learn about the options available to
!you, then select one that fits the way you're tracking progress.
/
uQ: When I print my report, a line labeled "Dependencies" appears under
!uthe report heading.  How can I get rid of it?
A: You have "showed dependencies" [Sh/F4] before printing the report.
!Return to the Gantt view, choose Schedule/Filters/Clear, then reprint
!the report.
uQ: Why won't Time Line let me enter a date in the Date Range fields of the
!uGantt Report Form?
A: Since the Gantt Report follows the on-screen layout, you may not be
!showing task bars on the current layout.  Press [F6], [F2], and examine
!the field labeled "Show Task Bars".
uQ: How can I print out my Journal Notes?
A: From within the note you wish to print, press [F8].  Enter the name
!"PRN" (or another DOS device name such as LPT2 or COM1 if your printer
!is attached to a port other than the 1st parallel port).  Press [F10]
!and answer "Proceed" to the "File Exists" message.  To insert a
!form-feed character, hold down the [Alt] key and enter "012" on the
!numeric keypad.
uQ: When I installed, I chose Compressed Video.  How do I change it back?
A: In the \TL5 directory, edit the TL.BAT file.  Remove the words "DISPLAY
!IS COMPRESSED".
/
uQ: Why does Time Line delete the tasks I've set to "Done"?
A: Check the current Select filter [Sh/F7].  If it's set to show tasks
!with Achievement less than 100%, choose Schedule/Filters/Clear.
!The "deleted" tasks will reappear.
uQ: I keep getting the message "This Option Not Installed".  Why?
A: Time Line gives this error message when the FILES statement in your
!computer's CONFIG.SYS file is either too low or doesn't exist.  Edit
!the CONFIG.SYS file (in the root directory); increase the FILES
!statement to FILES=30.  Then reboot [Ctrl/Alt/Del] the computer.
uQ: How can I copy a non-editable field and paste it into an Aux column?
!uCan I do this with the one-key macro?
A: Non-editable fields can be copied just like editable fields.  (Press
![Alt/C] after pressing [F2] on the appropriate column data.)  Time Line
!will display the message "...cannot edit this column..." but the data
!will be copied nonetheless, and can be pasted with [Alt/V].
#To automate this process with a one-key macro, create a layout with
!the two columns side-by-side.  With your cursor on the cell you want to
!copy, press [Alt/R].  Record the macro: [F2], [Alt/C], [Esc], [Right],
![F2], [Sh/F9], [Alt/V], [Down], [Left].  (The last two keystrokes
!prepare for the next playback.)  Press [Alt/R] again to stop recording.
/
uQ: Why do I keep getting the message "Date Out of Range" when trying to
!uadd a task?
A: Time Line cannot add a task beyond the range of the Master Calendar.
!To increase the range, change Precision (Calendar Settings Form) to a
!larger unit of time.  For example, if Precision is set for 15 Minutes,
!change it to Half-Hour.  (For tasks scheduled on the quarter-hour, this
!will round off their timing to the half-hour.)
$SLACK
uSlack
sh

Slack (or float) refers to the extra time in a schedule - the amount of
time a task could be delayed without affecting other tasks.  Time Line
calculates two types of slack, Free Slack and Total Slack.

Free Slack is the amount of time a task's end date could be delayed before
affecting another task's start date.  In the interconnected world of
critical path scheduling, a task with Free Slack enjoys a certain amount
of independence, at least as much as the amount of its Free Slack.

Total Slack, on the other hand, is the amount of time a task's end date
could be delayed before affecting a succeeding fixed task that is marked
"Force Critical", or the end of the schedule.

sNOTE: If a top-level family has no dependencies to other families, its
$slack is computed as if it were a schedule of its own.  In other
$words, Total Slack will be computed to the latest date in the family.
$SPRDVIEW
uSpreadsheet Editing
sh

You can edit most data showing in the Gantt view by pressing [F2] on the
item.  The information is displayed at the top of the screen.

  Move within the data             [Right], [Left Arrow]
  Move to beginning              [Home]
  Move to end                 [End]
  Move by word                 [Ctl/Left], [Ctl/Right]
  Insert data                 [Ins]
  Delete a character              [Del]
  Complete the edit              [Enter], [F10]
  Cancel the edit               [Esc]
  Complete the edit & move to next task    [Down Arrow]
  Complete the edit & move to previous task  [Up Arrow]
$SUMMARY
uSummary Tasks
sh

Summary tasks represent an aggregation of detail tasks indented beneath.

><.TLSAMPL

  Timing is summarized as the earliest and latest dates of any details.
  Any resources assigned to details are "invisibly" assigned to summaries.
!That is, summaries will represent detail task resource/cost assignments
!on reports.  When assigning resources to summaries, be sure they're not
!also assigned at the detail level.
  Percent achieved as entered on details is rolled up to summaries, using
!a weighted average as set on the Calculations Form.
+Quit,Index,Pct Achvd Weighed Average
=Quit,Index,CALF7
$SUPPORT
uTime Line Support Services
sh

Symantec offers a variety of Time Line Support products and services,
allowing you to select the support that best fits your needs.  Our
services include:

  No-charge phone and BBS support for registered users.
  Time Line workshops.
  Consulting services.
  Train-the-trainer support.
  Sales of training materials.
  Corporate subscription maintenance program.

For specific information about any of these services, you can continue
through this Help sequence, or call us at 415-898-1919 in the USA and
Canada.  In other countries, call your local Symantec office.
/
><SUPTECH
/
><SUPTRCON
/
><SUPCORP
/
><SUPINTNL
$SUPCORP
uCorporate Support Program
sh

Larger corporate clients have special needs.  The Corporate Support
Program (CSP) was developed with those needs in mind.  Companies with
20 or more registered users can subscribe to the CSP program to obtain
the following centralized benefits:

  Free version upgrades.
  Automatic file maintenance updates.
  Priority 800 number support.
  Support Center Manual.

Call the Support Services Department at 415-898-1919 for details about
each of the CSP plan options.

Available only in the USA and Canada.  (See "International Services".)
$SUPINTNL
uInternational Services
sh

If you are located outside the USA and Canada, please contact
your local Symantec office or distributor for product support.
For information about the Symantec office or distributor in your
area, please call 408-253-9600 (Pacific time zone, USA).
$SUPTECH
uTechnical Support Services--USA and Canada
sh

Before calling, please review the uQ&A subtopic (press [Q]), and prepare
for the call by reviewing uPreparing to Call (press [P]).

Available : to registered users
Hours#: 6AM to 5PM Pacific time, Monday through Friday
Phone#: 415-897-1445
Fax%: 415-898-1297
BBS%: 415-892-0408 (3-2400 baud, no parity, 8 data bits, 1 stop bit)

  You can reach our Technical Support staff by phone, fax, BBS (Bulletin
!Board Service), or through the Symantec forum on CompuServe.
  To become a registered user, complete the Registration Form that is
!included with the product.
  Information on special topics (Windows, memory management, DOS 5) can
!mailed or faxed to you.
  Available only in the USA and Canada.  (See "International Services".)
+Quit,Index,Q&A,Preparing to Call,Sending Materials
=Quit,Index,Q&A,CALLPREP,CALLSEND
$SUPTRCON
uTraining and Consulting Services
sh

uWorkshops and Seminars:  Symantec offers two- and three-day workshops on
Time Line, available at your site and at public locations across the U.S.
and Canada.

uTrainer Support:  We offer a train-the-trainer program and sell workshop
materials, including Leader's Guides and participant's workbooks, to
trainers interested in presenting Time Line workshops.

uConsulting Services:  Our consulting services are available at your
location, at our facility, and via phone, modem, or fax.

For details on any of these programs, or a list of upcoming workshop dates
and locations, call the Symantec Training Department at 415-898-1919.
Available only in the USA and Canada.  (See "International Services".)
$TLHint

uHints for Learning Time Line.Print out with [Print Screen]

Add a task           [Ins] (at minimum, enter name & duration)
Move around a form       [Enter] [Dn] [Up] [Tab]
Leave any form         [F10]
Move from task to task     [Dn] [Up] [PgDn] [PgUp]
Move task in the list      [Sh/Dn] [Sh/Up]
Make a task "family"      Indent [Sh/Rt] some tasks under another
Define a resource        [Sh/F8], then [Ins]
Assign a resource        Move to Resources on Task Form, then [F2]
Make a dependency        [Spacebar] on 1st task, then [F3] on 2nd
Change on-screen columns    [F6], pick a layout with [Enter]
Change layout definitions    [F6], then [F2] on layout name to change
Print a report         [/], then [R] for report menu
Save a schedule         [/], then [F] and [S]
Retrieve a schedule       [/], then [F] and [R] 
+Quit,Index
=Quit,Index
$TL.MONTH
>CALEDat
$TLSWAP
uTime Line Swap Files
sh

uTLSWAP:  If insufficient RAM Memory (especially EMS) is available to
Time Line, it uses disk space for its working file, named TLSWAP.$$$.  The
location of this file is the default directory (usually \TL5), although
this location can be changed with the SwapVol runtime parameter.  If a
second copy of the TLSWAP file is required (as is often the case on a
network), it is named TLSWAP.$$1.  TLSWAP files are automatically deleted
by Time Line upon exit from the program.

uExit to DOS Swap Volume: When plotting graphics, or when executing
"Exit to DOS / Proceed" or "Exit to DOS / Run a Program", Time Line
creates a temporary image of itself on disk before it releases its DOS
memory to the next program.  The location of the two files it creates
(named TLMEMORY.SWP and TLCODE.SWP) is the default directory, or the
directory specified by the SwapVol parameter.  If your Time Line session
ends abnormally (a power failure, for instance), these two files are left
on the disk for two days, then automatically deleted by Time Line.  Refer
to Appendix C for details.
$TL.WEEK
>CALEWor
$TM.GANTT
><GANTTEXT
/
><.FKEYS
/
>VIEWGan
$TM.INTRO
uPresenting Time Line Project Management Software
sh

Welcome.  If you're new to Time Line, this is a good place to start.  In
this introduction, we'll lay out some basic project management concepts
and show you how you can make them fly with Time Line.  (Don't worry.  We
won't go into a lot of depth here.  Just enough to get you started.)

Another reason for a quick introduction - Time Line is eager to help!
From anywhere in the program, you ask for assistance by pressing the
u[F1] key.  Menu selections, entry blanks in Time Line's forms, on
lists of options - [F1] helpfully describes each one.  And for browsing,
the Help Index is nearby - as close as u[Sh/F1].

u"6u#ҷ!"
u F1  ...the Help key.%uShift +  F1  ...the Help Index key.
u"6u#ʼ!"
+More,Quit,Index
=INTRMore,Quit,Index
$INTRMore
sh
OK, let's get started.

uTasks are the basic building blocks of a good project schedule.

  uSmooth surface
  uLay tar coat
  uPour asphalt

Tasks are grouped with summarizing tasks, called uparent tasks.

  uPave Driveway
#Smooth surface
#Lay tar coat
#Pour asphalt

In this manner, a list of things to do is compiled.
/
sh
Estimates of utiming are made.

31st2nd3rdĿ
  Pave Driveway
#Smooth surface  u& 3 days %
#Lay tar coat"u 1 day 
#Pour asphalt"u 1 day 

A sequence of events, or uprecedence, is established.

31st2nd3rd4th5thĿ
  Pave Driveway
#Smooth surface  % 3 days & u(1)
#Lay tar coat: 1 day  u(2)
#Pour asphaltB 1 day  u(3)

And the schedule begins to take shape!

/
sh
At this point, the parent task can usummarize the timing.

  Pave Driveway$u. 5 days /
#Smooth surface  & 3 days '
#Lay tar coat< 1 day 
#Pour asphaltD 1 day 

And if a change is made, the schedule can be uinstantly recalculated.

  Pave Driveway$* u4 days *
#Smooth surface  " u2 days "
#Lay tar coat3 1 day 
#Pour asphalt; 1 day 

So here's the power of project management - the ability to create a model
of the project, and see the effect of any change on the overall schedule.
/
sh
Who works on projects?  uPeople.#(The chart below, known as a
BuGantt Chart, can show all of this.)

  Pave Driveway,4 days  >
#Smooth surface  uAl$2 days  .
#Lay tar coat"uFlo#1 day1&
#Pour asphalt"uAl$1 day9&

Project management can vary the timing for tasks based on the number of
of people working on them.

  Pave Driveway,u3 days  6 _ _ _ _
#Smooth surface  Al,uFlo  u1 day!& - - - -
#Lay tar coat"Flo#1 day)&
#Pour asphalt"Al$1 day1&

/
sh
Having several ways of looking at the project helps focus on the problem
at hand:

  A uPERT Chart spotlights the sequence,!...while a uHistogram shows
  or dependencies, among tasks...*who's working when.

 uPave Driveway3%Surface!Al!$
 u %!%!% %Tar coat  Flo&
 u Smooth Lay tarPour! %Asphalt!Al*
 u surface!coat!!asphalt 4*
 u %!%!% %uAl's)_*
 u  2 days! 1 day ! 1 day  %uHistogram$$!
 u %!%!% 
 uA%uFlo's(_*
 uA%uHistogram*

Flexible planning and accurate tracking - all of a sudden you're on top of
your projects instead of being weighed down by them.

/
sh
Whether during the planning phase or the tracking phase, you always need
to stay in touch with the others involved - your team, management, and of
course vendors and subcontractors.  That's where reporting comes in.

*uFĿ
*uo|  Schedule:"Pave the Driveway&|o
*uo|  Responsible: Al's Fault Repair&|o
  Pave driveuo|F|o)
#Smooth uo|  Task Name$End#10/18!10/21  |o
#Lay taruo|  Pave Driveway  10/21!*!|o
#Pour asuo|"Surface$10/19!$'|o!&
*uo|"Tar coat#10/20'$|o
*uo|"Asphalt$10/21*!|o
*uo|F|o
*uo|  Time Line Gantt Report&Page 1  |o
*uF
/
sh
So what's the best way to get started?

! Take the Time Line Tutorial.
! Skim the Discussion sections of the Time Line Manual.
! Start up Time Line itself - dive right in, using the Help facility.
# [F1] on all menu selections.
# [F1] on as many form fields as you can find.
# [Shift/F1] and read all Index entries.
! Create your first schedule using Assist / New Schedule.
! Try things out - remember that [Shift/F10] (the Undo key) can
#back you out of many a tight and confusing place.

This completes the introduction.  Best wishes for timely scheduling.

P.S.  On the next screen, we've included a page of hints for you.
$We hope this helps in your first exploration of Time Line.
/
>TLHint
$TM.NETW
><PERTTEXT
/
><.PKEYS
/
><VIEWPer
/
>VIEWWor
$TRACKING
uTracking
sh

Careful planning and clear communication boost the chances for a project's
success.  Once the project is under way, however, it is just as important
to monitor its progress, identify potential problems, and recover from
unforeseen delays.  That's where tracking comes in.

The following facilities are available.
  Fields to track actual work accomplished and expenses incurred.
  An estimate of percent achieved that rolls up to summary levels.
  A "baseline" version of the schedule, freezing planned dates and costs
!for later comparison with actual progress.
  An Assisted Update feature and Needs Update filter to help in
!identifying tasks that should be reviewed.
  Larger versions of the Task and Assignment Forms, providing the extra
!detail needed for effective cost tracking.
  Calculated columns of information for display on Gantt view and in
!reports, that accurately analyze earned value.
$WEEKNUM
uWeek Numbers
sh

Dates may be identified by means of a week numbering system, wherein each
week within the calendar year is assigned a week number.  The method used
by Time Line in calculating week numbers is based on international
standard ISO 8601, using the following definitions and conventions:

  A "calendar week" is seven days long and starts on Monday.
  The first calendar week in any given year is the one which includes
!the first Thursday of that year (in the Gregorian calendar, this is
!the same calendar week which includes 4 January).
  Weeks are numbered sequentially, starting with the first calendar week
!and continuing up to the first calendar week of the following year.
!By convention, the first or last calendar week in a year may include
!days from two adjacent years, so that every calendar week has exactly
!seven days.  For example, 31 December 1991 is included in "Week 1" of
!1992, because the calendar week which contains 4 January 1992 begins
!on Monday, 30 December 1991.
/
  Time Line uses a week number date representation of the form "DDYYWW",
!where DD is an abbreviation for the day of the week, YY is the last
!two digits of the year, and WW is the calendar week number.  For
!example, the week number representation of Wednesday, 8 January 1992,
!is "WE9202".

In order to use a week number date format, the beginning of a Standard
Year must be defined as "January" (Calendar Settings Form).
$WINDOWS
uRunning Time Line Under Windows
sh

Time Line is able to run as a DOS program under Microsoft Windows (tm).
The following points address this type of installation:

  Do not use the Time Line TLVIDMEM addin (using video card memory to
!increase the memory available to Time Line) unless you use the Windows
!.PIF file supplied with Time Line.
  If available memory and/or processing speed is an issue, do not run
!Time Line under Windows.  Memory and processing speed are reduced under
!Windows.
$ASSI1-U
uASSIST:  UndoS[Sh/F10]
sh

The Undo feature reverses out the last change made to a task.  If
repeated, it backs up another step.  You can undo as many steps as are
specified in the Undo/Redo Limit field of the Options Form.

  Backs out changes to:
! Tasks (add, change, delete)
! Dependencies (add, change, delete)
! Resources (add, change, delete)
! Outline movement (indent, outdent, move up/down)
  Will NOT undo:
! Changes to the calendar, layouts, filters, or reports
! Changes to files on disk (retrieve, save)
! Sorts (use Last Manual Order instead)
! Changes made before the last File/Save.
+Quit,Index,Undo/Redo Limit
=Quit,Index,OPTN8
$ASSI2-R
uASSIST:  RedoR[Ctl/F10]
sh

After undoing several steps, you may need to retrace your steps.  Redo
just reverses the steps backed out with Undo.

  If you undo too far through a series of steps, use Redo to move back.
  The combination of Undo and Redo allow you to move back and forth
!through a series of changes.
  Undo and Redo help to see the "before and after" of a change to the
!schedule.  Make the change, then toggle back and forth from the change
!to the original with the Undo and Redo keys.
+Quit,Index,Undo/Redo Limit
=Quit,Index,OPTN8
$ASSIHel
uASSIST:  Help
sh

In Time Line, the Help System is context-sensitive.  That means that Help
is always aware of the area of the program you're in, and offers
information about that area when you press [F1].

%$'  [F1] is the Help key.  With your cursor on menu
%  F1  *names, form fields, lists, or views, press [F1]
%$*for specific information about that item.

 #ҷ!$!  [Sh/F1] displays an index to the Help System.
 Shift +   F1  $Scroll through the index with [PgDn] and [PgUp],
 #ʼ!$$or start typing the first letter(s) of an item.
9Press [Enter] to get Help for a particular item.
/
uASSIST:  Help
sh

Help screens (such as this one) have a list of choices at the bottom.

When one of the choices is "More", it means that additional information is
available on this topic.

The choice "Backtrack" allows you to move backwards to revisit screens you
have already seen.

Often there are other choices as well.  These bring you to screens with
information about related topics.
/
uASSIST:  Help
sh

%$&
% PgDn '  [PgDn] will move to the next screen.
%$*

%$&
% PgUp '  [PgUp] will backtrack to the previous screen."
%$*

%$&
% Esc  '  [Esc] will exit from Help."
%$*

For an overall description of basic Time Line principles, select
"Presenting Time Line", below.
+Quit,Index,Presenting Time Line
=Quit,Index,TM.INTRO
$ASSINew
uASSIST:  New Schedule
sh

Assist / New Schedule guides you through several important forms, helping
you to prepare for your first schedule by specifying such items as the
shop calendar, the available resources, and your preferences in working
with the product.

  On-screen messages guide you through the process.
  After reviewing several forms, you will be given final instructions
!for entering your first tasks:
! Press [Ins] to add new tasks.
! Press [F2] to change existing ones.
! Press [/] to access the menus.
! Press [F1] to get help about menus, forms, and lists.
  You don't HAVE to use this feature when starting a new schedule.
!In fact, you may only use it the first time through.
$ASSIQui
>FILEQui
$ASSITut
uASSIST:  Tutorial
sh

The Time Line Tutorial is available as a function of the program itself.
Assist/Tutorial takes you directly to the tutorial, saving your place in
Time Line.

  To be safe, save the schedule (File/Save) before going to the tutorial.
  When you leave the tutorial, you will be returned to your schedule as
!you left it.
$ASSIUpd
uASSIST:  Update
sh

Typically, you'll want to review and update the schedule while work is
being done.  This might involve a small or large amount of effort,
depending on the amount of detail you need to track.  Assisted Update
helps make this process more efficient.

  Given the current As-of Date, Assisted Update checks for tasks whose
!status should have changed (Future to Started, Started to Done).
  For each, it displays a message asking if status should be changed.
  Gives opportunity to edit Task Form to enter new dates and/or durations.
  Stops on ALL started tasks if large Task Form selected on Options Form.
!Gives opportunity to update Percent Achieved and estimate to complete.
  Works similarly to Needs Update filter on Filter Form.
+Quit,Index,Needs Update Filter,Updating Hints
=Quit,Index,FLTR14,.TRACK
$ASSIWbs
uASSIST:  WBS Generation/Checking
sh

Work Breakdown Structure (WBS) codes indicate each task's position in
the outline (hierarchy).  The WBS codes are especially important when
exporting and reimporting tasks.  The WBS Manager offers an automated way
of entering these codes quickly.

  Use the WBS Manager Form to specify the pattern, or "map", for the
!codes.  This form offers flexibility in structuring the codes.
  Assist/WBS can number (renumber) all tasks, or just the current family.
  Other options available:
! Verify current codes.
! Verify and renumber errors.
! Number unnumbered tasks.
! Erase current codes.
! Transfer codes from other fields.
$CALEDat
uCALENDAR:  Dates
sh

With Hour precision (Calendar Settings Form), Time Line maintains a
calendar from January 1, 1983 through December 31, 2017.  The Dates
Calendar allows entry of work and nonwork dates during this period.
As shipped, Time Line shows all federal holidays.

  Change a date between Work and Non Work by pressing the [Spacebar].
  For macros, [Ins] sets a date to Non Work; [Del] restores it to Work.
  Move among the dates of a month with the [Arrow] keys.
  Move from month to month with [Tab]/[Sh/Tab] or [PgDn]/[PgUp].
  The Dates Calendar can be changed at any time during the scheduling
!process.  Time Line will schedule tasks around added nonwork dates.
  For a specific date to be scheduled for work, its day of the week must
!have workhours available on the Workhours Calendar.
/4
  Days that are marked Non Work on the Master Calendar cannot be changed
!to work days on the Resource Calendar.
  Press [F5] to go to a specific date (enter "today" to return to start).
+Quit,Index,Workhours Calendar
=Quit,Index,TL.WEEK
$CALEQui
>FILEQui
$CALESet
uCALENDAR:  Settings
sh

When scheduling work, Time Line must know certain facts about your work
calendar: the number of hours in your day, the number of days in your
week, the first day of your week, and the first month of your year.  You
enter these site standards into the Calendar Settings Form.

  The form also allows the setting of scheduling precision (with a
!variety of settings from minute to hour).
  After changing Dates or Workhours Calendars, check Settings to make
!sure the standards still match your scheduling.
$CALEWor
uCALENDAR:  Workhours
sh

The Workhours Calendar allows entry of work and nonwork periods for each
day of the week.  Time Line uses the Workhours and Dates Calendars to
determine when to schedule work.

  For work to be scheduled on a specific date, the day of the week must
!have work periods (Workhours Calendar), and the date must be a work
!date (Dates Calendar).
  Work periods of half-hour and quarter-hour are available, if Precision
!(Calendar Settings Form) is set to half or quarter hour, respectively.
  Change from a nonwork hour to a work hour (and vice versa) by pressing
!the [Spacebar].
  Move among the hours with the [Arrow] keys.  [Home] moves to the
!beginning of the line, [End] to the end of the line.
/5
  The Workhours Calendar can be changed at any time during the scheduling
!process.  Time Line schedules around any added nonwork hours, and
!includes new work hours in its scheduling.
  Review the Calendar Settings Form after changing the Workhours Calendar.
+Quit,Index,Dates Calendar
=Quit,Index,TL.MONTH
$CONFDat
uCONFIGURE:  Date Formats
sh

Dates (and times) can be displayed in different ways.  The option chosen
here affects date display on screen, in forms, data columns, and reports.

  This is a global option.  When this option is changed (and your options
!are saved), it affects any schedule loaded into memory.
  When you change date formats, review your layouts.  You may want to
!change the width of date columns, given the new format.
  Only formats 1, 2, 3 and 4 can be used with Fiscal Years.
+Quit,Index,Fiscal Years,Week Numbers
=Quit,Index,12477,WEEKNUM
$CONFDis
uCONFIGURE:  Disk File
sh

Time Line reports can be "printed" to a disk file.  This option allows
you to specify the format to be used in creating the file.

  For disk file output, select Disk File on the Report Form.
  For sideways printing, configure the disk file for sideways or rotated
!format.  Disk file strips will be "glued", ready for rotated printing.
+Quit,Index,Report Form
=Quit,Index,PRNT1
$CONFGra
uCONFIGURE:  Graphics
sh

To properly output graphics, Time Line must know about the device you are
using.

  This menu brings up a scrolling list of devices from which to pick.
  After selecting your device, complete the Graphics Setup Form.
  Then use the Setup Communications Form to specify the output port
!(communications interface).
  Save your selections permanently by choosing File/Save (Options Only).
$CONFMou
uCONFIGURE:  Mouse
sh

This allows you to modify two mouse settings:

  the speed with which you are able to "double-click" the mouse,
  the maximum speed with which you are able to scroll on lists with
!the mouse.
$CONFPri
uCONFIGURE:  Printer
sh

To properly output printed reports, Time Line must know about your
printer.  Use this menu to specify, or change, your printer.

  If the printer's manufacturer or model is not in the list, select one
!that your printer emulates, or select "DOS ASCII Printer".
  LaserJet Y Font prints all high-order ASCII characters (solid task
!bars, milestones, and delay markers).
  Save your selection permanently by choosing File/Save (Options Only).
$CONFQui
>FILEQui
$CONFSou
uCONFIGURE:  Sound
sh

Time Line sounds a tone at certain messages to call your attention.  This
menu item allows you to silence these tones.

  With the sound off, Time Line flashes a light instead of beeping.
  This option is saved globally (affects all schedules until changed
!within any one of them again).
$CONFVid
uCONFIGURE:  Video
sh

Use this menu to specify, or customize, your monitor and screen colors.

  Instructions are provided as part of the menu screens.
  Seven basic color palettes are provided.  Experiment to find your
!preference.
  Colors may be fine-tuned with the Customize option.
!NOTE: Customized colors are lost if one of the seven palettes is
're-selected.
  Save your selection permanently by choosing File/Save (Options Only).
/3
To switch between normal and compressed video modes, you need to change
the TL.BAT file with an ascii editor.  The command for compressed mode
is "DISPLAY IS COMPRESSED".
$CROSQui
>FILEQui
$CROSRes
>REPOCro
$CROSTas
>REPOCro
$CURSNor
>VIDECur
$CURSOve
>VIDECur
$CURSRes
>VIDECur
$CURSSec
uVIDEO:  Customize
sh

This video attribute not currently used.
$DEPEFor
uDEPENDENCIES:  FormN[Sh/F3]
sh

Use the Dependency Form to specify a partial dependency.  A partial
dependency modifies the standard finish-to-start connection to allow
start-to-start and finish-to-finish relationships, and overlaps
(leads) and gaps (lags) between tasks.

  Another task (a predecessor or successor) must have already been marked
!"P" or "S" (with [Spacebar]) before calling up the Dependency Form.
  Use to join tasks previously unjoined, to change standard dependency to
!partial, or to modify an existing partial dependency.
  Another way to create or modify a partial dependency:
! Create standard dependency [F3].
! Bring up dependency list [F4] and move cursor to dependent task.
! Edit dependency [F2].
! Enter timing relationship on Dependency Form.
+Quit,Index,Dependency Instructions
=Quit,Index,DEPENS
$DEPEJoi
uDEPENDENCIES:  JoinQ[F3]
sh

The DEPENDENCIES menu can be used to create a standard (finish-to-start)
dependency.  However, since this is such a common function, we recommend
using the following shortcut.

  Mark one task as the predecessor in the relationship ([Spacebar] once)
!or the successor ([Spacebar] twice).
  Move to the other task in the relationship and press [F3].

  To designate multiple predecessors, mark the successor "S", then move
!to each predecessor and press [F3].
  To designate multiple successors, mark the predecessor "P", then move
!to each successor and press [F3].
  To create a partial dependency (start-to-start, overlap, gap), execute
!the same steps, but press [Sh/F3] instead of [F3].  Complete the form.
+Quit,Index,Dependency Instructions
=Quit,Index,DEPENS
$DEPELis
uDEPENDENCIES:  ListQ[F4]
sh

Reviewing a task's dependencies is best accomplished with the Dependency
List.  Since a compressed outline is displayed, off-screen and hidden
dependencies (within closed outline levels) can be seen.

  Predecessors are marked "P", successors "S", and partial dependencies
!are noted in the second column.
  Controlling dependencies (affect start date) are marked "".
  Controlling dependencies on critical path are marked "#".
  Pressing [P] shows only predecessors, [S] shows successors, [B] both.
  Pressing [Enter] on a dependent task lists that task's dependencies.
  Press [F10] to leave list and jump to current task on Gantt view.
  Press [Esc] to leave list and return to the original task.
+Quit,Index,Dependency Instructions
=Quit,Index,DEPENS
$DEPEPer
uDEPENDENCIES:  PERTM[Ctl/F4]
sh

In the PERT view, dependencies are clearly shown as lines between boxes.

  Most task features, such as adding and editing, are available on both
!Gantt and PERT views.
  Select chart style (outline or traditional) and box placement (standard
!or presentation) on Options Form.
+Quit,Index,Chart Style,Box Placement,Dependency Instructions
=Quit,Index,OPTN11,OPTN12,DEPENS
$DEPEQui
><FILEQui
$DEPESho
uDEPENDENCIES:  ShowN[Sh/F4]
sh

If dependent tasks tend to be near one another in your schedule, you may
prefer to review dependencies using this feature.

  All visible dependent tasks of current task are highlighted.
  On a color monitor, predecessors are displayed in one color, successors
!in another (colors depend on palette selection: Configure/Video).
  To see ALL dependencies (not just visible), use Dependency List [F4].
+Quit,Index,Dependency Instructions
=Quit,Index,DEPENS
$DEPEUnj
uDEPENDENCIES:  UnjoinK[Ctl/F3]
sh

This feature removes a dependency between two tasks.

  Another task (the predecessor or successor of the current task) must
!have already been marked "P" or "S" before removing a dependency.
  If you haven't done that, move to the other task and press [Spacebar]
!once (marks it "P") or twice (marks it "S").
  Time Line asks for a confirmation before the dependency is removed.
  Another way to remove dependencies:
! Bring up Dependency List [F4] on predecessor or successor.
! Move cursor to other task in dependency.
! Press [Del].  Time Line asks for a confirmation.
+Quit,Index,Dependency Instructions
=Quit,Index,DEPENS
$DIREAsc
uDIRECTION:  Ascending
sh

  uAscending  sorts text from A to Z; numbers, costs, and durations from
,smallest to largest; and dates from earliest to latest.
  uDescending sorts text from Z to A; numbers, costs, and durations from
,largest to smallest; and dates from latest to earliest.
$DIREDes
>DIREAsc
$ERASAny
uERASE:  Any TL or DOS Files
sh

  uAny TL Files brings up a list of Time Line files in the current
.directory.  Included are all schedules (including previous
.versions) saved by the current version of Time Line.

  uAny DOS Files builds a list of all DOS files in the current directory.

  When you select items from these lists, they will be PERMANENTLY erased
!from disk (after a confirming prompt).
  To change directories, press [+/-] on directory names, or press [F2].
$ERASCur
uERASE:  Current TL Files
sh

  Brings up a list of all current Time Line schedules.
  When you select an item from this list, it will be PERMANENTLY erased
!from disk (after a confirming prompt).

uTo move around the list:
>.PICKLIS
$ERASQui
>FILEQui
$ERASTL
uERASE:  TL Ver. 2, 3, or 4 Files
sh

  The "TL Ver. 2, 3, and 4" options list all Time Line schedules in the
!current directory created by these previous versions of Time Line.
  When you select an item from this list, it will be PERMANENTLY erased
!from disk (after a confirming prompt).

uTo move around the list:
>.PICKLIS
$EXPOCro
uEXPORT:  Cross Tabs
sh

  Export schedule data in cross tab format:
! Task vs Time
! Resource vs Time
! Task vs Resource
  This option brings up the Export Cross Tabs Form.  Enter your export
!specifications onto the form.
  A subsequent form appears for entry of data to be cross tabulated.
$EXPOTab
uEXPORT:  Tables
sh

  Export schedule data in table format:
! Tasks
! Resources
! Assignments
! Dependencies
! Availability Profile
! Rate Profile
! Resource Calendars
! Varying Assignments
  This option brings up the Export Tables Form.  Enter your export
!specifications onto the form.
$EXPOQui
>FILEQui
$FILECom
uFILE:  Combine
sh

File/Combine is used to merge information from two schedules.

  A list of schedules in the current directory (as specified on the
!File Form) appears.  Select a schedule to combine.
  Combine the entire schedule by selecting Tasks/Resources/Costs.
  The Master Calendar option is used before adding tasks to start with a
!master calendar from another schedule.
  The other options - Resources/Costs, Filters, Layouts, Journal Notes,
!and Column Names - merge items in those lists with the items in the
!current lists.
  Graph Palettes merges the graphics color definitions from another file.
/5
  If Tasks/Resources/Costs is selected, the tasks will be placed at the
!current cursor position.
  Optionally, a summary task can be added to group the combined schedule.
  To reverse the process, use File/Save/Extract.
+Quit,Index,File/Save/Extract
=Quit,Index,EXTRACT
$FILEEra
uFILE:  Erase
sh

  PERMANENTLY delete schedules and other DOS files from disk.
  Displays a list of:
! Time Line schedules (current or earlier versions).
! all files in the current directory.
  This feature works like the DOS DEL and ERASE commands.
  If you want to clear the current schedule from memory, use
!Schedule/Erase instead of this.
+Quit,Index,Schedule/Erase
=Quit,Index,SCHEEra
$FILEFor
uFILE:  FormU[Ctl/F6]
sh

  Form for changing information about the DOS schedule file.
  This form can also be displayed by pressing [Ctl/F6].
  The form contains these fields:
! The DOS filename and directory for the schedule.
! A way of archiving previously saved versions of the schedule.
$FILEImp
uFILE:  Import
sh

  Converts data from another program's format (Lotus 1-2-3, Symphony,
!Quattro, Excel, dBASE III and IV, ASCII text, and outlines).
  Four types of data can be imported:  tasks, resources, assignments, and
!dependencies.
  To import a full schedule that has been previously exported:
! In a blank schedule, set up the master calendar (or use File/Combine).
! Import all four types of data (ensure Tasks file includes WBS code).
  To merge data with the current schedule:
! Import the type of data to be merged (be sure both current schedule
#and imported data contain WBS codes).
  uOn Target data (another Symantec scheduling product) can be imported.
$FILEPre
uFILE:  Previous
sh

  Loads a previous version of a schedule from disk.
  If the Previous field (File Form) is set to a number greater than 0,
!previous version(s) of the schedule are maintained each time you save
!the schedule.
  The most recent previous version has a DOS file extension of ".5T1".
  Thus, if Previous (File Form) is set to 5, the oldest version has an
!extension of ".5T5".
  A Directory List of all versions appears.  Select file from list.
  wCAUTION: If a previous version is saved with File/Save, it will
*become the current version.
  DO NOT use as a backup of the schedule.  Backups should be made to a
!device other than your hard disk.
  To permanently archive a previous version (the schedule as of the end
!of Phase 1, for example) make a copy of it using a new name.
$FILEQui
uMENU:  Quit
sh

  Leave the menu system, return to the current view.
  [Esc] also leaves the menu system.
$FILERet
uFILE:  Retrieve
sh

  Loads a schedule from disk into memory.
  A list of schedules in the current directory (as specified on the
!File Form) appears.
  To change directories, change the File Form before retrieving,
!press [F2] on the list of files to select a new directory, or press
![+] and [-] on directory names to open and close the directory outline.
  Select a schedule by moving to it and pressing [Enter].
  If another schedule is already in memory, a confirmation must be given
!before replacing it with the retrieved schedule.
$FILESav
uFILE:  Save
sh

  Saves the current schedule to disk (saves it permanently).
  If schedule is named (File Form) and an old version exists on disk,
!a message will offer these options:
! Replace old version with current schedule.
! Make a copy of schedule, using new name.
! Extract a portion of the current schedule.
! Save global options only, don't save the schedule.
  If no schedule with current name exists on disk, all options above are
!given with exception of "replace".
  If schedule has not been named, you'll be allowed to name the schedule
!or save options only.
  Previous version is NOT overwritten if Previous field (File Form) is
!set to 1 or more.
$FILEXpo
uFILE:  Export
sh

  Converts schedule data to another program's format.
  Currently supported:  Lotus 1-2-3, Symphony, Quattro, dBASE III and IV,
!Excel, and text (CSV format).
  Several types of data can be exported:
! uAll Task Information    all entered, many calculated task fields.
! uCurrent Layout       task data from current Gantt layout.
! uResources          selected resource/cost columns.
! uAssignments         all current resource assignments to tasks.
! uDependencies        all current task dependencies.
! uTask vs. Time Cross Tab   Task vs. Time Cross Tab Report format.
! uResource vs. Time Cross Tab Resource vs. Time Cross Tab Report format.
! uTask vs. Resource Cross Tab Task vs. Resource Cross Tab Report format.
  If data is to be later imported, answer Yes to "Verify unique WBS codes
!for reimport?"  Time Line will verify WBS codes before exporting.
$FILT1
>VIDECur
$FILT2
>VIDECur
$FILT3
>VIDECur
$FILTCle
uFILTER:  Clear
sh

  Deactivates all highlight and select filters.
  To clear an individual filter (clear the select filter without changing
!highlight filters, for instance) bring up its list and select "-Clear-"
!at the top of the list.
  Also clears highlights placed on the screen with Show Dependencies.
$FILTHig
uFILTER:  Highlight
sh

  Enhances a subset of tasks, all having a common element.
  Use to call attention to some tasks for ease of use on-screen, or for
!more meaningful reporting.
  Three highlight filters are available - each a different color on color
!monitors.  All print in bold on reports.
  Any highlight filters can be used together - even with select filter.
  When this option is selected, a list appears with names of previously
!defined highlight filters. (Press [F1] at this point for instructions.)
  Changes to names on the Highlight Filter lists affect the Select Filter
!list as well.
!select filter lists.
  When using multiple highlight filters, add Filter (Highlight) columns
!to Gantt with Layout Form.
+Quit,Index,Select Filter
=Quit,Index,FILTSel
$FILTPre
>VIDECur
$FILTQui
>FILEQui
$FILTSel
uFILTER:  Select
sh
 
  Displays a subset of tasks, all having a common element.
  Use to condense the task list for ease of use on-screen, or for more
!selective reporting.
  When this option is selected, a list appears with names of previously
!defined select filters.  (Press [F1] at this point for instructions.)
  Changes to names on the Select Filter list affect Highlight Filter
!lists as well.
+Quit,Index,Highlight Filter
=Quit,Index,FILTHig
$FILTSuc
>VIDECur
$FORMBac
>VIDECur
$FORMDat
>VIDECur
$FORMHid
>VIDECur
$FORMPro
>VIDECur
$GANTDat
>VIDECur
$GANTHis
>VIDECur
$GANTQui
>FILEQui
$GRAPGan
uGRAPHICS:  Gantt Chart
sh

The graphics Gantt Chart shows a bar chart view of the schedule, printable
on plotter, laser, or dot matrix printer.

  First, a form appears for setting up the chart.
  The form contains these fields:
! Gantt Layout name to select text columns.
! Palette name for color choices.
! Title and notes.
! Lines, spacing, scale.
! Task bar labeling.
  When the chart form is accepted, another form appears, showing:
! Sizing.
! Reduction/enlargement.
! Preview on screen.
+Quit,Index,PERT Chart
=Quit,Index,GRAPPer
$GRAPQui
>FILEQui
$GRAPPer
uGRAPHICS:  PERT Chart
sh

The graphics PERT Chart shows tasks as boxes, with dependency lines drawn
between the boxes.

  First, a form appears for setting up the chart.
  The form contains these fields:
! PERT Layout name to select text fields.
! Palette name for color choices.
! Title and notes.
! Style and format for task boxes and dependency lines.
! Selection of periodic chart format or one without time phasing.
  When the chart form is accepted, another form appears, showing:
! Sizing.
! Reduction/enlargement.
! Preview on screen.
+Quit,Index,Gantt Chart
=Quit,Index,GRAPGan
$HELPInd
uHELP:  Index
sh

  Displays an index of important Help topics.
  Display Help for an index item by moving to it with the arrow keys
!and pressing [Enter].
  Jump to a particular item by typing first letter(s) of its name.
  Pick another index item by selecting Index on the Help menu.
$HELPPre
uHELP:  Presenting Time Line
sh

  Presents a guided tour of Time Line.
  The major areas of the program are displayed.
  Important concepts are explained.
  "Don't miss" features are described.
$HELPQui
>FILEQui
$IMPOOn 
uIMPORT:  On Target!
sh

Time Line imports planning data from On Target, a Symantec Windows
product.

  Tasks and their start/end dates are imported.
  The following items are not imported:
! Holidays in the standard calendar
! User modifications to the standard calendar
! Layout information
! Filter information
! Tasks: colors, fonts, position in PERT chart
! Resources: colors, fonts, sorted position, total cost
  If timing is measured in quarters in On Target, each is translated to
!three months when imported.
  After importing, be sure to recalc [F9] to update the imported schedule.

$IMPOOut
uIMPORT:  Outlines
sh

  Imports schedule from text file on disk or from direct keystroke entry.
  Schedules can be imported from an ASCII file produced by a word
!processor or outline program such as GrandView, ThinkTank, or Ready.
  In a text (ASCII) file, indentations indicate outline levels.
  Time Line scans the lines as they're brought in, searching for key
!words such as "start" and "link".  It interprets these words to find
!task, resource, and dependency information.
  Only new schedules can be created with Outline Import.  Merging one
!schedule into another is not possible with this facility.
$IMPOQui
>FILEQui
$IMPOTab
uIMPORT:  Tables
sh

  Imports schedule data in table format.
  "Table" refers to row/column format - spreadsheets and databases.
  This option brings up the Import Form.  Enter your import
!specifications onto the form.
$IMPOTim           
uIMPORT:  Time Line Ver. 4 / Ver. 3 / Ver. 2
sh

These options convert previous version Time Line schedules to the current
version's format.

  Only schedules saved using the selected version are displayed in the
!Directory list.
  Only schedules stored in the current directory (File Form) are shown.
  To change to a different directory, press [-] on the directory name.
  If a schedule is linked to other schedules, import and save the other
!schedules before importing the schedule containing the cross project
!links.
  If the imported schedule starts its year in a month OTHER than January
!(fiscal year), you are warned that the Starting Month (Calendar
!Settings Form) is to be changed to January.
$INSECho
uINSERT:  Choices
sh

  Allows insertion of a menu.  (On playback, the menu is displayed at
!this point.)
  A form appears to record each menu option and the name of the macro it
!is to execute.
$INSEDia
uINSERT:  Dialog
sh

  Allows display of a message box to prompt for input or to provide
!instructions.  (On playback, a box appears at this point.)
  A form appears to record the message.
$INSEInp
uINSERT:  Input Pause
sh

  Allows variable input each time the macro is run.
  Macro stops at this point, displays a message "Input: F10 = Resume
!Macro", and allows any number of keystrokes.  When [F10] is pressed,
!the macro continues from this point.
  Similar to Pause, except Pause resumes with [Ctrl/Home].
+Quit,Index,Pause
=Quit,Index,INSEPau
$INSELin
uINSERT:  Link
sh

  Allows "chaining" of macros.  The named macro is retrieved from
!disk and played from this point of the calling macro.
  The linked macro must have been recorded first.
  Return is not automatic.  (It is a one-way link.)  Automatic return
!can be accomplished by inserting another macro.
$INSEMac
uINSERT:  Macro
sh

  Allows "nesting" of macros.  The named macro is retrieved from
!disk and played as part of the calling macro.  When it completes, the
!calling macro resumes from this point.
  You can also insert a macro by pressing [Alt/F6] and selecting a macro
!name from the list.
  The inserted macro must have been recorded first.
  wCAUTION: Do not change the name of the inserted macro after including
*it in another macro.
$INSEPau
uINSERT:  Pause
sh

  Allows variable input each time the macro is run.
  Macro stops at this point, displays a message "Input: Ctrl-Home =
!Resume Macro", and allows any number of keystrokes.  When [Ctl/Home] is
!pressed, the macro continues from this point.
  Similar to Input Pause, except Input Pause resumes with [F10].
+Quit,Index,Input Pause
=Quit,Index,INSEInp
$INSEQui
>FILEQui
$INSESec
uINSERT:  Secondary Macro
sh

  At the point of insertion, another macro is recorded, to be replayed
!as an inserted macro later in the recording.
  Secondary macros are most often used to insert the same information
!several times.  At the first insertion, the macro stops to record the
!information, then automatically inserts it again in other places.
$ MACCon
uMACROS:  Configure
sh

  Displays the Macro Configuration Form.
  The form contains several fields for changing the way macros works.
! The "HotKeys" for start/stop recording, inserting during recording,
#and calling menus and the Macro List.
! A toggle between step mode and continuous playback.
! A setting for the playback speed from fast to slow.
$ MACEra
uMACROS:  Erase
sh

wCAUTION: This selection erases all macros currently recorded in memory.
'Be sure you have saved your macros (Macros/Save) before doing
'this.

  This selection does not affect schedule data in any way.
$ MACHal
uMACROS:  HaltT[Alt/-]
sh

  Stops macro recording.
  Also accomplished by pressing [Alt/-].
$ MACIns
uMACROS:  InsertQ[Alt/F3]
sh

  Displays a menu of items to insert during the recording of a macro.
  Options include:
! A link to (no return), or call to (with return) another macro.
! A secondary macro.
! Two different kinds of pauses for variable-length input.
! A menu or message box.
$ MACLoa
uMACROS:  Load
sh

  Retrieves a file of macros from disk.
  After loading, the macros can be displayed by pressing [Alt/F6].
$ MACMac
uMACROS:  Macros
sh

  Displays the Macro List.
  To playback a macro, select it from the list.
  Also accomplished by pressing [Alt/F6].
$ MACQui
>FILEQui
$ MACRec
uMACROS:  RecordR[Alt/=]
sh

  Starts recording a macro.
  Displays the Primary Macro Form for entering macro name and hotkey.
  Also accomplished by pressing [Alt/=].
+Quit,Index,Macro Hints
=Quit,Index,MACROHNT
$ MACSav
uMACROS:  Save
sh

  Permanently saves all macros currently in memory to disk.
  Displays the Macro File Form for entering the filename and directory.
$MAINAss
uMAIN MENU:  Assist
sh

The Assist features are provided to introduce certain topics and help
with repetitive tasks.

  Display an on-screen introduction to Time Line.
  Access the Help System Index.
  Take the Time Line tutorial.
  Have Time Line lead you through creating a new schedule.
  Focus in on tasks requiring a progress update.
  Number, renumber, or verify WBS codes and the outline structure.
  Undo (and redo) the last several changes made to the schedule.
$MAINCon
uMAIN MENU:  Configure
sh

Configuration options include several one-time setup features.

  Select your computer's display type (color, monochrome, Hercules, etc.)
  Select your printer manufacturer/model, and communications interface.
  Select your graphics output device (plotter, graphic printer, etc.)
  Turn off (and on) the audible sounds played with certain messages.
  Select the format for reports sent to disk (sideways, MultiMate, etc.)
  Select the display format for dates and times on screen and in reports.
  Select performance characteristics for an attached mouse.
$MAINFil
uMAIN MENU:  File
sh

File management features provide access to your permanent files on disk.

  Change the current disk and/or directory (File/Form).
  Retrieve and save schedules.
  Merge another schedule into the current schedule.
  Save a portion of the current schedule (File/Save, Extract option).
  Retrieve archived versions of schedules.
  Import and export schedules from/to other products.
  Erase Time Line schedules or other files from disk.
$MAINGra
uMAIN MENU:  Graphics
sh

Graphics allows the printing/plotting of two project presentation styles.

  uGantt Chart similar to on-screen Gantt, allows customization of
-task bar labels, graph format, symbols, and scale.
  uPERT Chart  similar to on-screen PERT, allows customization of
-task boxes, dependency lines, and time-scaling.

  Set up for your plotter and/or graphic printer with Configure/Graphics.
+Quit,Index,Gantt Chart,PERT Chart
=Quit,Index,GRAPGan,GRAPPer
$MAINQui
uMAIN MENU:  Quit Program
sh

Use "Quit Program" to leave Time Line.

  Before exiting, Time Line asks for a confirmation.
  If the current schedule has not been saved, Time Line asks if you
!want to quit without saving (in other words, a second confirmation).
$MAINRep
uMAIN MENU:  Reports
sh

  uTables   A submenu of tabular reports.
,uTask(Calendar'Rate
,uResource$Availability#Varying Assignment
,uAssignment
  uGantt   Printed version of on-screen Gantt view.
  uDetail   Includes options for full dependencies & notes.
  uStatus   Daily, weekly, monthly summaries; group by task, resource.
  uCross Tab Matrix of task/time, resource/time, or task/resource -
,intersections (cells) can show any of over 15 items of info.
  uHistogram Printed bar chart showing resource workloads.
  uPERT    Printed version of on-screen PERT view.
  uWork Tree Printed version of on-screen Work Tree view.
  uForm    Change margins, report destination, other report options.
$MAINSch
uMAIN MENU:  Schedule
sh

The Schedule menu leads to most of the functions you will use in Time Line.

  Add, change, or delete tasks, resources, and dependencies.
  Modify the master calendar.
  Change the layout (selection of columns) of the on-screen Gantt view.
  Sort, select, and highlight (filter) groups of tasks.
  Access the project journal (notepad).
  Set the schedule baseline.
  Select from among several options in working with the schedule.
  Change the way Time Line calculates the schedule.
  Erase the current schedule from memory (be sure to save first).
$MAINUti
uMAIN MENU:  Utilities
sh

The Utilities menu provides access to several miscellaneous features.

  Record and playback keystrokes with Macros.
  Temporarily exit to the DOS prompt, perform some DOS operations or
!execute small programs, then return to the same place in Time Line.
  Display a screen of session data (helps when calling Tech Support).
  Change the computer's date and time.
  Copy configuration options from the previous version of Time Line.
$MAINVie
uMAIN MENU:  Views
sh

Even though the schedule is stored internally in one way only, you can
visualize your schedule in four different ways:

  uGantt View   tasks in rows; columns of data that can be customized;
0bar chart showing task duration under a calendar.
  uHistogram View synchronized with the Gantt view; bar chart showing
0up to five resources' workloads.
  uPERT View   tasks in boxes; summary tasks are boxes surrounding
0their details; dependency lines drawn between tasks.
  uWork Tree View outline structure represented as org chart; also
0known as a WBS diagram.
$MENUBac
>VIDECur
$MENUCho
>VIDECur
$MENUFir
>VIDECur
$MENUHel
>VIDECur
$MENUPre
>VIDECur
$MESSCap
>VIDECur
$MESSInd
>VIDECur
$MESSNor
>VIDECur
$MESSSha
>VIDECur
$MESSWar
>VIDECur
$PERTBac
>VIDECur
$PERTBri
>VIDECur
$PERTDon
>VIDECur
$PERTSta
>VIDECur
$REPOCro
uREPORTS:  Cross Tab
sh

  Reports periodic information for tasks and resources, or resource
!information for tasks.
  Data is arranged in spreadsheet format:
! Tasks as rows, resources as columns.
! Tasks as rows, time periods as columns.
! Resources as rows, time periods as columns.
  In the cells, any of over 15 different data items can be shown.
  Where appropriate, row and columns totals are printed.
  Report data can be restricted to select filtered tasks/resources.
  Can be exported to spreadsheets and databases in any of the same three
!formats.
$REPODet
uREPORTS:  Detail
sh

  Prints a page of information for each task.
  Presented in full-page format.
  A selection of task data is available.
  Display summary or detailed resource/cost assignments.
  Print all or a number of task note lines.
  Include all predecessors and/or successors for each task.
  Restrict tasks to be printed with select filter or by closing outline.
$REPOFor
uREPORTS:  Form
sh

  Form for changing the printing of all reports.
  The form contains these fields:
! Output destination and format.
! Margin settings.
! Customization of the report heading.
$REPOGan
uREPORTS:  Gantt
sh

  Prints the on-screen Gantt view.
  Report follows current Gantt layout (columns, scale, etc.)
  If summaries are closed, they'll print as closed summaries on report.
  If select filter active, only visible tasks will print.
  If highlight filter active, all highlights will print as bold.
$REPOHis
uREPORTS:  Histogram
sh

  A vertical bar chart, showing resource/cost assignment data.
  Similar to on-screen histograms if you choose to "duplicate on-screen
!resource histograms".
  Otherwise, any of over 15 data items can be graphed.
$REPOPer
uREPORTS:  PERT
sh

  Prints out the on-screen PERT view.
  Report follows current PERT layout (data fields, widths, etc.)
  Closed summaries print as closed boxes with "+" at corners.
  If select filter active, only visible tasks will print.
  If highlight filter active, all highlights will print as bold.
$REPOQui
>FILEQui
$REPOSta
uREPORTS:  Status
sh

  Prints daily, weekly, or monthly summaries of current activities.
  Report can grouped by task or resource.  As an example, you can show
!all tasks assigned to Joe for each of the next three weeks.
  A combination of reports may be produced.  For instance, you can choose
!to print five daily status reports & two weekly reports in the same run.
  For each status time period, a selection of task columns can be shown.
  If reports are grouped by resource, additional resource assignment
!information can be displayed.
$REPOTab
uREPORTS MENU:  Tables
sh

  uTasks       shows all columns in current Gantt layout.
  uResource      shows a selection of resource/cost columns.
  uAssignment     shows resources assigned to tasks, or tasks assigned
4to resources.
  uCalendar      shows unavailable time for each resource with an
4individual resource calendar.
  uAvailability    shows the number and pct of each resource available
4and when their availabilities change.
  uRate        shows the cost rate changes for each resource/cost.
  uVarying Assignment shows the assignments of resources to tasks and
4the changes in assignment amount/duration.
$REPOWor
uREPORTS:  Work Tree
sh

  Prints out the on-screen Work Tree view.
  Report follows current Work Tree layout (data fields, widths, etc.)
  Open summaries show child tasks as inverted tree below (org chart).
  If select filter active, only visible tasks will print.
  If highlight filter active, all highlights will print as bold.
$RESOForm
uRESOURCES:  Form=[Sh/F8], then [Ins] or [F2]
sh

  Form for adding/changing resource information.
  The Resource/Cost Form appears whenever you add [Ins] or edit [F2] a
!resource on the Resource/Cost List.
  The form contains these fields:
! The resource name, full name, keyword, and notes.
! Type - resource or three different cost types.
! Calendar - the period(s) of time the resource is unavailable.
! Availabilities - can be changed over time.
! Cost rates - can be changed over time - and unit of measure.
! Default assignment amount and percentage.
$RESOHis
>ViewHis
$RESOLis
uRESOURCES:  ListQ[Sh/F8]
sh

  Displays current Resource/Cost List, the pathway to the Resource/Cost
!Form.
  Also appears when [F2] is pressed during resource/cost assignments to
!tasks.
  Resources/costs on list can be added, changed, and deleted.
!sNOTE:  Before a resource or cost can be deleted, it must be removed
(from all tasks (including baseline assignments).
  Add resources/costs to tasks by entering in Resource/Cost section of
!Task Form, or by pressing [F2] then [Ins] on Resource column on Gantt.
+Quit,Index,Resource/Cost Form
=Quit,Index,RESOForm
$RESOQui
><FILEQui
$SCHEBas
uSCHEDULE:  Baseline
sh

The baseline is used to freeze the current schedule for later
comparison.  Changes made to the schedule do not affect baseline values.

  Baseline records task timing, resource assignments, and expenses.  It
!is usually set just before actual work begins.
  Baselines record the dates and expenses of tasks, and the cost rates
!of resources.  Optionally, they can also record the exact assignments 
!of resources to tasks.
  Display on Gantt with baseline columns (Layout Form).
  Display baseline task bars with "Show Baseline (Yes)" (Layout Form).
+Quit,Index,Show Baseline,Percent Achieved
=Quit,Index,DSPL6,TASK113
//
  Resetting baseline is permitted - select Schedule/Baseline again:
! uReset entire!makes a completely new baseline for all tasks.
! uStarted/future does not affect baselines of Done tasks.
! uTasks without  makes new baseline only for recently added tasks.
! uCursor task"makes new baseline only for current (cursor) task.
! uResources$makes new baseline for all resources, no tasks.
! uErase(removes the current baseline for all tasks.
  When resetting a baseline, you can selectively reset the costs, or 
!the dates, or both.
  When an option other than Reset Entire is chosen, only the baselines of
!the affected tasks are changed.  Summary task baselines are not
!automatically updated.  If you need accurate summary task baselines for
!your analysis, you must reset these summaries' baselines manually.
$SCHECal
uSCHEDULE:  Calculations
sh

Certain characteristics of the way Time Line recalculates the schedule
can be changed here on the Calculations Form.

  Changes made to the Calculations Form are saved with the schedule.
  Calculation can be set to occur automatically, or only when Recalc [F9]
!is pressed.
  Future tasks (except those with a Start Date Restriction set to Must
!Start) can be forced to be scheduled in the future.
  Negative slack can be calculated, or not.
  Resource calendars can be taken into effect, or not.
  The unworked portions of tasks can be split from the completed
!portions, and scheduled in the future.
  Resource leveling can be turned on and off.
  Highest priority can be given to the number 999.9 or the number 0.
  The method of rolling up achievement to summary tasks can be selected.
+Quit,Index,Options Form
=Quit,Index,SCHEOpt
$SCHEDep
uSCHEDULE:  Dependencies
sh

One of the most important concepts in critical path scheduling is the
dependency.  It allows you to specify the precedence of activities to be
accomplished.  Using an accurate description of this precedence network,
Time Line is able to juggle the placement of tasks to arrive at the most
efficient schedule.  With the features in this section of the program,
you can:

  Create and delete dependencies.
  Fine-tune relationships by creating partial dependencies.
  Review established dependencies on the Gantt view, in a condensed list,
!or in the PERT view.
+Quit,Index,Dependency Instructions
=Quit,Index,DEPENS
$SCHEEra
uSCHEDULE:  Erase
sh

  Erases the schedule currently showing on screen.
  Does NOT affect the file on disk.  (File/Erase deletes disk files.)
  The current calendar stays in memory.
  Changes made to standard layouts and filters are eliminated.
  Only one confirmation is offered.  If schedule not saved, changes will
!be lost.
  If you want to permanently erase a schedule file from disk, use
!File/Erase instead of this.
+Quit,Index,File/Erase
=Quit,Index,FILEEra
$SCHEFil
uSCHEDULE:  Filter
sh

If there were no way of focusing on related groups of tasks, you might
feel overwhelmed by the size of your project.  Filters provide that focus.
By defining a filter to group tasks with a common attribute, you can
highlight those tasks in bold or a different color, or temporarily hide
all other tasks from the screen (and reports).

  A list appears, allowing you to select filters by name.
  Use a select filter to display a subset of tasks, hiding the others
!from view temporarily.
  Use a highlight filter to spotlight certain tasks in color or bold.
  Tasks are filtered on the basis of criteria entered on the Filter Form.
  Filtering carries through to all reports except PERT and Work Tree.
+Quit,Index,Highlight Filter,Select Filter
=Quit,Index,FILTHig,FILTSel
$SCHEJou
uSCHEDULE:  JournalN[Alt/F2]
sh

  Keeps notes on the schedule as a whole.
  Press [Alt/F2] to bring up the list of Journal notes.  This can be done
!from almost any place in Time Line.
  Use the Journal to collect general notes such as phone numbers, meeting
!minutes, and follow ups.
  The Journal uses the notepad facility.  A note of almost any length can
!be entered.
  The first line of each Journal note appears as the note title in the
!Journal List.  These titles can be indented and outdented like an
!outline.
$SCHELay
uSCHEDULE:  LayoutsR[F6]
sh

The Layout facility allows flexibility in the on-screen display.  Columns
can be added and rearranged, the task bar scale can be changed, and other
information, such as each task's baseline, can be shown.

  A list appears, allowing you to select layouts by name.
  Use layouts to arrange the on-screen columns (pick from over 100).
  Layouts also affects the task bars - scale, progress symbols, slack and
!delay symbols, and whether baseline is shown.
  If more columns are selected than can be shown on-screen, you can
!scroll to off-screen columns.  All columns are printed in reports.
$SCHEMas
uSCHEDULE:  Master Calendar
sh

The Master Calendar options affect the underlying timeframe (shop schedule)
within which Time Line schedules work.

  On a monthly calendar, specify the workdays and holidays.  (Unavailable
!time for each resource is specified on the Resource/Cost Form.)
  On a weekly calendar, specify the normal workdays and offdays.  (If the
!Precision field (Calendar Settings Form) allows, workdays can start and
!end on the half and quarter hour.)
  On a form, specify:
! Standard workday.
! Standard workweek.
! Beginning day of week.
! Beginning month of year.
! Smallest unit of time with which you wish to schedule tasks.
$SCHEOpt
uSCHEDULE:  OptionsO[Sh/F6]
sh

Time Line is designed to be flexible.  Many of the ways it works can be
changed on the Options Form.

  Changes made to the Options Form are saved with the schedule.
  The Options Form Schedule Name, Notes, Responsible, and As-of Date
!fields can be printed on reports.
  The As-of Date can be updated daily, weekly, or manually.
  Times can be displayed with dates, or not.
  The defaults for newly entered fixed tasks can be modified.
  Use of large or small Task and Assignment Forms can be controlled.
  The actions of Undo/Redo and the PERT view format can be customized.
+Quit,Index,Calculations Form
=Quit,Index,SCHECal
$SCHEQui
>FILEQui
$SCHERes
uSCHEDULE:  Resources
sh

People accomplish projects.  The resources area of Time Line allows
definition and assignment of people and other scheduled resources such as
equipment.  Allocations may then be monitored and scheduling conflicts
resolved - the goal being the smooth flow of work to people.  Cost items,
such as materials, contractor and vendor payments, are similarly estimated
and tracked.

  Resources are added, changed, and deleted on the Resource/Cost List.
  They are assigned to tasks on the Task Form or with a Resource column.
  Charts of allocation (histograms) may be shown for up to five people
!at a time, and can be synchronized with the current task assignments.
  Overscheduling problems can be manually corrected or automatically
!reduced with Resource Leveling.
+Quit,Index,Resource/Cost List,Histograms
=Quit,Index,3000,VIEWHis
$SCHESor
uSCHEDULE:  Sort
sh

  This function sequences the task list (within the outline structure).
  Sort using any of the Gantt Layout columns, ascending or descending.
  For multi-level sorts, nine sort levels are available.
  Sorting only occurs within outline levels:

!Before sorting by task name&After sorting
!9&9
!Before event5After event
#Roll out carpet2Evaluate
#Put up chairs4Tear down
!Event<Before event
!After event8Put up chairs
#Tear down8Roll out carpet
#Evaluate7Event
$SCHETas
uSCHEDULE:  Tasks
sh

Schedules are composed of tasks.  The relationships among tasks and the
estimates of their timing provide the basis for accurate scheduling.
Some task components, such as duration and start date, directly affect
the schedule.  Others, such as notes and WBS, are informational only and
are used to organize and report on the schedule.

  Tasks are added, edited, and deleted on the Gantt, PERT, and Work Tree
!views.
  Task information may be changed at any time during the planning process.
  Careful tracking of task progress allows for updated forecasts and a
!post-project comparison of planned vs. actual results.
$SORTGo
uSORT:  Go
sh

  Starts the sort.
  You must have entered at least a Primary key before doing this.  (Time
!Line uses Task Name as a Primary key if none is entered.)
  Use Last Manual Order to return to original sequence after sorting.
$SORTLas
uSORT:  Last Manual Order
sh

  When you enter or move tasks in the Gantt view, you are establishing a
!manual sequence of tasks.  Select this option to return to that
!manually arranged sequence after any number of sorts.
  If (after sorting) you attempt to move a task up or down in the list,
!Time Line asks if you wish to establish a new manual order.  If
!you answer Yes, your original sequence is lost.
$SORTOth
uSORT:  Other Keys
sh

  Selects key to break ties after Primary/Secondary sorts.
  Other keys are only used for sorting when duplicates still exist after
!sorting by Primary and Secondary keys.
  The available columns are the same as are available on the Layout Form,
!and can be used to sort in ascending or descending order.
$SORTPri
uSORT:  Primary Key
sh

  Selects the first task data column on which to sort (any duplicates in
!this column are sorted using the Secondary Key).
  The available columns are the same as are available on the Layout Form,
!and can be used to sort in ascending or descending order.
  If this key is not specified, Task Name is used by default.
$SORTQui
>FILEQui
$SORTSec
uSORT:  Secondary Key
sh

  This data column (key) is used to sequence the duplicates found in the
!Primary sort.  In other words, if two or more tasks have the same
!information in the Primary key field, this key is used to sort those
!duplicates.
  If this sort ustill produces duplicates, columns specified in Other
!Keys must be used to sort the remaining duplicates.
  The available columns are the same as are available on the Layout Form,
!and can be used to sort in ascending or descending order.
$SOUNNo
uSOUND:  No
sh

  Turns OFF sound.
  In effect for all schedules until changed at this menu.
$SOUNYes
uSOUND:  Yes
sh

  Turns ON sound.
  In effect for all schedules until changed at this menu.
$TABLAss
uREPORTS:  Assignment
sh

  Reports on each task's resource assignments, or each resource's tasks.
  Report can be grouped by task or resource.  For example, you can get a
!list of all tasks assigned to Joe, or a list of all resources working
!on the prototype design.
  Task, resource, and assignment columns are available.
  Task columns print at left when report grouped by task; resource
!columns print at left when report grouped by resource.
$TABLAva
uREPORTS:  Availability
sh

  Reports on each resource's available number and percentage.
  If a resource's availability varies over time (as defined on Resource
!Form), several entries for the resource will appear on this report.
  Columns on report are:
! Resource Name#name of resource (all are included in report)
! Start Date&date of first day of availability period
! End Date(date of last day of availability period
! Leveling Limit"for this period, max number for leveling
! Leveling Percent  for this period, max percent for leveling
+Quit Help,Availability,Calendars,Unavailable
=Quit,RSRC6,CALENDAR,RSRC5
$TABLCal
uREPORTS:  Calendar
sh

  Reports on each resource's unavailable time as specified on the
!Resource Calendar (Resource/Cost Form).
  If no unavailable time has been specified, the resource does not appear
!in the report.
  Columns on report are:
! Calendar Name  name of resource (must have unavailable time specified)
! Start Date#date of first day of each unavailable period
! End Date%date of last day of each unavailable period
+Quit Help,Calendars,Unavailable,Availability
=Quit,CALENDAR,RSRC5,RSRC6
$TABLQui
>FILEQui
$TABLRat
uREPORTS:  Rate
sh

  Reports on cost rates for each resource and cost type.
  If rates vary over time (as defined on Resource Form), several entries
!for the resource will appear on this report.
  Columns on report are:
! Resource Name  name of resource (all are included in report)
! Start Date#date of first day of rate period
! End Date%date of last day of rate period
! Rate)for this period, the resource's cost rate for the time
2period specified in the next column
! Per*for this period, the time period for the cost rate
2specified in the previous column
$TABLRes
uREPORTS:  Resource
sh

  Prints columnar information for each resource/cost.
  Report columns are chosen from a list of all items entered on the
!Resource/Cost Form.
  Can be exported to spreadsheets and databases in the same format.
$TABLTas
uREPORTS:  Task
sh

  Prints current Gantt layout columns, without task bars.
  Report follows current Gantt layout on Layout Form.
  If summaries are closed, they'll print as closed summaries on report.
  If select filter active, only visible tasks will print.
  If highlight filter active, all highlights will print as bold.
  Report can be exported with Current Gantt Layout Info on Export Form.
$TABLVar
uREPORTS:  Varying Assignment
sh

  Reports on assignment of resources to tasks.
  If appropriate, resource assignments may show the date range of each
!assignment, and number assigned in each date range.
  Columns on report are:
! Task Name!name of task (all are printed unless select filtered)
! Task WBS"task's WBS code
! Rsrc Name!name of assigned resource (all assigned to current task
/are printed)
! Start Date  date (and time) of first day of assignment period
! End Date"date (and time) of last day of assignment period
! Work Rate!rate of assignment, this period
$TASKAdd
uTASKS:  AddX[Ins]
sh

  Adds a new task to the schedule.
  Pressing the [Ins] key also adds a task to the schedule.
  Brings up a blank Task Form (either large or small, depending on
!setting on Options Form).
  We suggest adding tasks by placing cursor on predecessor.  Then, after
!the task is added, you have only to press [F3] to make the dependency.
  To copy an existing task (or summary family), place cursor on task and
!press [Sh/Ins] or select Schedule/Task/Copy.
  To edit a task, press [F2] on a column, or [Ctrl/F2] for Task Form.

NOTE: When cursor is in Task Name column, [Ins] adds task by entering name
$at top of screen.  (Other task data is entered in adjacent columns.)
$Change between spreadsheet and task bars areas with [Tab].
$TASKCop
uTASKS:  CopyT[Sh/Ins]
sh

  Copies an existing task or summary family.
  Pressing [Shift] and the [Ins] key works as a shortcut to copy tasks.
  Inserts a new task below the current task, using information from the
!current Task Form as defaults for the copied task.
  All task information EXCEPT the WBS field is copied (including task
!name and resource assignments).  Change any fields on copied Task Form.
  Dependencies are NOT copied, except dependencies among family members
!when a summary task is copied.
$TASKDel
uTASKS:  DeleteU[Del]
sh

  Deletes the current task, or the entire task family if current task is
!a summary.
  Pressing the [Del] key also deletes the current task.
  Time Line asks for a confirmation before deleting task.
  If summary task, displays 2nd confirmation before child tasks deleted.
  If baseline set, displays 3rd confirmation before deleting baseline.
  After deleting task, asks if deleted task's dependencies should be
!"bridged".  If "Y", Time Line makes dependencies among tasks
!previously dependent upon the deleted task.

  Delete a task accidentally?  Use Undo [Sh/F10] to get it back!
$TASKEdi
uTASKS:  EditL[Ctl/F2] or [F2]
sh

  Changes the current task's details.
  Pressing the [F2] key from the task bars area, or [Ctl/F2] from either
!the spreadsheet or task bars area, edits the current task on the form.
!Note: [F2] in the spreadsheet area edits the current column.
  Brings up the default Task Form with current task information.
  Task information can also be edited directly on the Gantt view.
! Move to the Spreadsheet area of the Gantt view [Sh/Tab].
! Move to the task and column you wish to change (add the column to the
#Gantt view, if necessary, with the Layout Form).
! Press [F2] to edit the information in the Status line (top of screen).
  To enter a new task, press [Ins] or select Schedule/Task/Add.

NOTE: Change between spreadsheet and task bars areas with [Tab].
$TASKFor
uTASKS:  FormK[Ins] or [Ctl/F2]
sh

  Form for adding/changing task information.
  The Task Form appears whenever you add [Ins] or edit [Ctl/F2] a task.
!Note: If cursor is in Task Name column, [Ins] adds task and edits name
'at top of screen  does not present Task Form.
  If your cursor is in the Task Bars area, you can press [F2] to edit.
  The form contains these fields:
! The task name and notes.
! Coding - keyword, WBS, OBS.
! Timing - type, duration method, duration, effort, start/end dates.
! Tracking - percent achieved, status.
! Resources, priority.
! Link to other file (Cross Project Links).
  Use Task Form field (Options Form) to change between large and small
!Task Forms.
$TASKInd
uTASKS:  IndentP[Sh/Right]
sh

  Moves current task 1 level IN in the outline structure.
  Indents current task under first sibling (task at same level) above.
  If current task is a summary, child tasks are indented as well.
  To move a task from one family to another: outdent it, move it to a
!position immediately below (a sibling to) the other parent, then indent.

  wCAUTION: If you indent by mistake, use Undo [Sh/F10] to move back.

  sNOTE: [Sh/Right] only works with numeric keypads arrow keys.
'On keyboards without numeric keypads, indent with number "6".
$TASKNot
uTASKS:  NotesT[Sh/F2]
sh

  Brings up the task notepad.  Enter notes and press [F10].
  Task notes are also accessible by pressing [F2] on a Gantt view Notes
!column (add Notes column to Gantt with Layout Form).
  First line of notes appears in Note field of Task Form.
$TASKOut
uTASKS:  OutdentP[Sh/Left]
sh

  Moves current task 1 level OUT in the outline structure.
  Shifts current task to the left, out of its current family.
  If current task is a summary, child tasks are outdented as well.
  To move a task from one family to another: outdent it, move it to a
!position immediately below (a sibling to) the other parent, then indent.

  wCAUTION: If you outdent by mistake, use Undo [Sh/F10] to move back.

  sNOTE: [Sh/Left] only works with numeric keypads arrow keys.
'On keyboards without numeric keypads, outdent with number "4".
$TASKQui
>FILEQui
$TASKSea
uTASKS:  SearchV[F5]
sh

  Finds a particular task by name.
  Brings up QuickPick List.
!(All task names - including those off-screen, within closed summaries,
"or unselected - are displayed in an outline format.)
  When a task name is selected, the cursor jumps to that name on the
!Gantt view.

uTo move around the list:
>.PICKLIS

  To find a task by WBS code, press [Sh/F5] instead.
$TEXTBri
>VIDECur
$TEXTEnh
>VIDECur
$TEXTNor
>VIDECur
$TEXTRev
>VIDECur
$UTILDOS
uUTILITIES:  DOS Date/Time
sh

  Resets the computer's date and time.
  This may never be necessary, especially if your computer's time is
!automatically kept by an on-board clock.
  DOS date/time affects the As-of Date if Current time, Start/day,
!or Start/Week is selected on the Options Form.
$UTILExi
uUTILITIES:  Exit to DOS
sh

  Temporarily jumps out to DOS - holds your place in Time Line.
  Use this to perform routine DOS functions - create directory,
!copy file, delete files - without completely exiting Time Line.
  wCAUTION: Do not load memory-resident programs such as the DOS PRINT
*command or SideKick after exiting to DOS.  Such "TSR" programs
*must already be installed before starting Time Line.
  Return to your Time Line work by typing "EXIT" at the DOS prompt.
  Time Line stays exactly as you left it.
  We suggest saving the schedule before exiting, in case you forget to
!return.
$UTILMac
uUTILITIES:  MacrosN[Alt/F1]
sh

  Record a sequence of keystrokes, then save it by name for later recall.
  For example, you might record all the keystokes to produce a set of
!reports, then reprint them weekly by using the WklyRpts macro.
  Simple macros are also helpful.  You might record a macro to add "SFO"
!to the Keyword field of the current task, then replay it to mark all
!the San Francisco tasks.
  Macros can be invoked with an Alt key shortcut.  [Alt/G] might assign
!George to tasks.

  Start macro recording          [Alt/=]
  Stop macro recording           [Alt/-]
  Insert into macro            [Alt/F3]
  Display list of macros          [Alt/F6]
+Quit,Index,Macro Hints
=Quit,Index,MACROHNT
$UTILQui
>FILEQui
$UTILSta
uUTILITIES:  Statistics
sh

  Displays a screen of information that may be helpful to Tech Support
!when calling with problems.
  Screen includes:
! Schedule filename, data directory, and program directory.
! The number of tasks and resources currently in the schedule.
! User name and serial number.
! DOS version and MS Windows information.
! Information about the computer's use of memory.
+Quit,Index,MS Windows
=Quit,Index,WINDOWS
$UTILTL 
uUTILITIES:  TL 4.0 Config
sh

  Copies global configuration settings from Time Line version 4.0.
  This helpful utility saves the reentry of hardware configurations, and
!allows standard layouts and filter created in Ver. 4 to be used in
!Ver. 5.
$VIDECur
uVIDEO:  Customize
sh

  Customizes video (monitor) color palettes.
  Allows color selection for specific Time Line display areas, such as
!the color of forms and the menu area.
  Use the customization menus to locate the item you wish to change.
!Each menu item leads to a color palette.  Select the foreground/
!background combination with the arrow keys.  Press [Enter] to select.
$VIDEFil
>VIDECur
$VIDEFor
>VIDECur
$VIDEGan
>VIDECur
$VIDEMen
>VIDECur
$VIDEMes
>VIDECur
$VIDENet
>VIDECur
$VIDEPer
>VIDECur
$VIDEQui
uVIDEO:  Quit
sh

  Exits video customization.
  Select this option when you have finished your video setup.
  To permanently save video options, select File/Save (options only).
$VIDETex
>VIDECur
$VIEWGan
uVIEWS:  GanttS[Ctl/F8]
sh

The Gantt view is the primary view in Time Line.

 u* Spreadsheet Area +  " Task Bars Area Ŀ
 WMSep1Oct
 W Task Name'Task Type  Duration!Cost  4!11"18"25"2  
 W A  Product A%Summary"22 days!$8000  4
 W A#Design%Fixed$10 days!$1500  (
 W A!+ Manufacture  ASAP&8 days!$4000*&
 W A#Assemble#ASAP&4 days!$25002"
 u %$      
(u' Layout Columns '

  (EGA/VGA) Display 43/50 lines: Start TL with uTL DISPLAY IS COMPRESSED.
/
>GANTHint
$GANTHint

uGantt View Hints;Print out with [Print Screen]

Move cursor to Spreadsheet area             [Sh/Tab]
Toggle cursor between Spreadsheet and Task Bars area   [Tab]
Edit current layout column in Spreadsheet area      [F2]
Edit the current task using the Task Form        [Ctl/F2]
Edit the current task's notes              [Sh/F2]
Rearrange layout columns (change widths, reorder)    [F6]
Open and close summary tasks               [+] / [-]
Select and highlight certain tasks (filter)       [Sh/F7] & [F7]
Move tasks up and down at current level         [Sh/Up] & [Sh/Dn]
Indent and outdent tasks                 [Sh/Rt] & [Sh/Lt]
Overlay the Gantt view with the Histogram view      [F8]
View resource assignment histograms of cursor task    [Alt/F8]
Print a report of the on-screen data           [/] [R] [G]
Draw a chart of the current Gantt data          [/] [G] [G]
$VIEWHis
uVIEWS:  HistogramG[F8] or [Alt/F8]
sh

Histograms show periods of scheduled (and overscheduled) work.  The
assignment to the current task and unavailable periods are also shown.

 W?SepB
 W Task Name'Resource$4'11&18&25%
 W A  Design(Jim, Ann$03
 W A  Manufacture#Ann7BA/#
 W)In Use$Avail"E
 W AJim%Task: 0#Unavail. [-  [4
 W A(Day : 0#1 @ 100% ["_"_"_ B[  _"_"_"_"
 W A_=Y-__Y[_3
 W AAnn%Task: 1,[E
 W A(Day : 2#1 @ 100% ["_"_"]B][ _"_"_"_"
 W A_=Y,A2[_#
+Quit,Index,Availability,Resource Calendars
=Quit,Index,RSRC6,RSRC5
/
>HISTHint
$HISTHint

uHistogram View Hints7Print out with [Print Screen]

Add another resource's histogram  [F8], add name
Change to another resource     [F8], change name; or Double-Click
Histograms for cursor task      [Alt/F8], or Dbl-Clk on task bar
Return to Gantt view        [Ctl/F8] or [/] [V] [G]
Change time scale (dateline at top) [F6] [F2], change Scale
Show tasks for histogram resource  Select filter [Sh/F7] for resource name
Find the overscheduled periods   [Rt][Lft] to overscheduled period
In the overscheduled periods,    [Dn][Up] - current task's contribution
  which tasks are contributing?%is highlighted
Print report of on-screen data   [/] [R] [H], "Yes"
$VIEWPer
uVIEWS:  PERTT[Ctl/F4]
sh

The PERT view displays the outline & dependency structure of the schedule.

"}"Product AK"
"}"T"
"}"+Manufacture,+"
"}"+8+"
"}"(  ( ~(} ("
"}"Design"Ķ Setup#~Production}ĺAssemble  "
"}"(  ( ~(} ("
"}"+,*+"
"}"+8+"
"}"T"
/
>PERTHint
$PERTHint

uPERT View Hints<Print out with [Print Screen]

Move around the PERT view             [Arrow] keys or [Tab]
Move from screen to screen             [Ctl/Rt] [Ctl/Lt]
Jump from start to end summary (traditional style) [Ctl/End]
Change to alternate layout             [F8]
Change layout used as standard or alternate    [F6], select new name
Change data in task boxes             [F6] [F2]
Qselect columns, widths
Show data at top of screen only          [F6] [F2]
Qadd columns, "0" width
Change style and box placement           [Sh/F6]
Print a report of the on-screen data        [/] [R] [P]

  All Gantt view commands ([Ins], [Del], [F2], [F3]) are also available.
$VIEWQui
>FILEQui
$VIEWWor
uVIEWS:  Work Tree
sh

The Work Tree view displays the outline structure in org chart format.

*}0)0
*}0Product A  0
*}0)0
*}(++(
*}") ~)} )"
*}"Design# ~Manufacture} Assemble!"
*}") ~)} )"
*}6+(
*}0) )"
*}0Setup$ Production "
*}0) )"
/
>TREEHint
$TREEHint

uWork Tree View Hints7Print out with [Print Screen]

Move around the Work Tree view           [Arrow] keys or [Tab]
Move from screen to screen             [Ctl/Rt] [Ctl/Lt]
Change to alternate layout             [F8]
Change layout used as standard or alternate    [F6], select new name
Change data in task boxes             [F6] [F2]
Qselect columns, widths
Show data at top of screen only          [F6] [F2]
Qadd columns, "0" width
Print a report of the on-screen data        [/] [R] [T]

  All Gantt view commands ([Ins], [Del], [F2], [F3]) are also available.
$WBSBot
uWBS:  Both Verify and Renumber
sh

  Using the specifications from the WBS Form, reviews the outline and
!verifies any existing WBS codes.
  If problems found, renumbers tasks in error.
  Numbers tasks without WBS codes, as well.
  Records error conditions in "WBS Errors" task column.
$WBSEra
uWBS:  Erase
sh

  Erases WBS codes.  Can erase codes from:
! All tasks.
! Current task only.
! Current task and its child tasks.
! Current tasks' child tasks only.
$WBSFor
uWBS:  Form
sh

  Form for specifying the pattern (map) for the WBS code.
  The form contains these fields:
! A prefix to precede all other coding in the WBS code.
#For each segment in the WBS:
! The character sequence to use for that segment.
! Its maximum and minimum widths.
! Specifications for separating segments of the code.
$WBSNum
uWBS:  Number Blank Tasks
sh

  Using the specifications from the WBS Form, numbers any tasks without
!WBS codes.
  Records error conditions in "WBS Errors" task column.
$WBSQui
>FILEQui
$WBSRen
uWBS:  Renumber
sh

  Using the specifications from the WBS Form, renumbers all or a
!selection of tasks.  Can renumber:
! All tasks.
! Current task only.
! Current task and its child tasks.
! Current tasks' child tasks only.
  Records error conditions in "WBS Errors" task column.
$WBSTra
uWBS:  Transfer
sh

  Transfers codes from other fields to the WBS field.
  Can transfer from:
! Task Name.
! Keyword.
! OBS.
! Notes.
! Aux 1, 2, or 3.
  Transfer can be made to:
! All tasks.
! Current task only.
! Current task and its child tasks.
! Current tasks' child tasks only.
  Codes can be moved from other field to WBS, or data interchanged
!between the fields.
$WBSVer
uWBS:  Verify
sh

  Using the specifications from the WBS Form, reviews the outline and
!verifies any existing WBS codes.
  Records error conditions in "WBS Errors" task column.
$CALF0
uRecalculationJCalculations Form
sh
  Recalc schedule automatically, or only when [F9] pressed?
  For large schedules, Manual is recommended - recalc only after a series
!of changes.
  To note on reports whether the schedule has been recalced, include
!"*(CODE(\42))*Recalc*" in report heading (Report Form).
  Schedule must be recalced before a baseline is set.
  To stabilize task start dates while updating, set Force Future Tasks to
!"No" during data entry.  (Select "Updating Hints" below for more info.)
+Quit,Index,Updating Hints
=Quit,Index,.TRACK
$CALF1
uForce Future TasksECalculations Form
sh
  uNo  schedules Future tasks after their latest predecessor, even if
%that is earlier than the As-of Date (in other words, in the past).
%Use during updating to avoid changing task dates of tasks not yet
%updated (see "Updating Hints" below).
  uYes  reschedules all Future tasks to start at the As-of Date or
%later (except those with a Start Date Restriction set to Must Start).
%Started or Done tasks are not affected.  Use to have Time Line show
%all unstarted tasks in the future.
+Quit,Index,Updating Hints
=Quit,Index,.TRACK
$CALF2
uCalculate Negative Slack?Calculations Form
sh
  If a successor must start earlier than the task's end date, should Time
!Line show the task's slack as being a negative amount?
  uNo  does not calculate negative slack.  Even in the above situation,
%the task would show no less than "0" slack.
  uYes calculates negative slack.  Tasks can show negative slack amounts,
%and late start/end dates can be earlier than start/end dates.
  Negative slack means "super-critical."
/9
  If a Gantt layout is chosen that shows slack, it will also show
!negative slack.  Any task with negative slack will display as:

#$&

!to indicate the distance between the (required) late start, and the
!(projected) early start.  This symbol () is also used to show fixed
!tasks that are projected to start late.
$CALF3
uHonor Resource Calendars?Calculations Form
sh
  uNo  ignores the unavailable periods marked on all Resource Calendars.
  uYes delays tasks until resources are available, or splits tasks
%around the unavailable periods (exact behavior chosen on Task Form.)
  Unavailable time is set on the Resource/Cost Form by pressing [F2] on
!the Resource Calendar field.
+Quit,Index,Delay/Split
=Quit,Index,TASK19
$CALF4
uSplit Spent/To Go Effort?Calculations Form
sh
To use this feature effectively, you must also choose "Yes" for
Force Future Tasks.

  uNo  does not split the scheduling of tasks to separate Spent and To Go
%effort.  (Compatible with Time Line versions 4 and prior.)
  uYes splits the scheduling of tasks.  Effort that has been spent is
%scheduled prior to the As-of Date.  The future portion of the task
%is scheduled separately, based on remaining effort.
+Quit,Index,Force Future
=QUIT,INDEX,CALF1
/8
  For example, consider an effort-driven task that has 10 days of
!required work.  Four of these 10 days have already been worked (spent)
!at the beginning of the month, and it is now the 15th.
! uNo  here would schedule the entire task at the beginning of the
'month and (misleadingly) show the unfinished work in the past.
! uYes would schedule the unfinished (to go) portion of the task
'starting today (better choice if progress is regularly recorded).
/6
  Histograms can show the split scheduling.  In fact, histograms can show
!the complete scheduling of every resource on a task, taking into
!account separation of spent and to-go effort, splitting around
!unavailable time, and contouring of effort-split tasks.  Press the
!Histogram Hot Key [Alt/F8] on a task for this type of histogram.
$CALF5
uLevelingOCalculations Form
sh
  uNo      turn off leveling.  Schedule calculated with CPM only.
  uYes     delays start dates until resources are available.
  uWithin Slack delays start dates (like "Yes"), but not if required
.start dates or the schedule end date are delayed.
  Time Line schedules higher priority tasks first, when possible.
+Quit,Index,Priority,Highest Priority
=Quit,Index,TASK122,CALF6
/8
  Rescheduled tasks show "r" in the Status column; dots to left of task
!bar show when task COULD have started, were the resources available.
  When many resources are overscheduled, "Within Slack" tends to allow
!many conflicts at the end of dependency chains.
  Appears on reports if "*(CODE(\42))*CALC*" included in Report Heading on Rpt Form.
+Quit,Index,Priority,Start Date,Report Keywords
=Quit,Index,TASK122,TCOL113,HDGCODES
$CALF6
uHighest PriorityGCalculations Form
sh
  Determines whether high numbers or low numbers have higher priority.
  If "0" is selected, a task with priority 5 would take precedence over
!a task with priority 10.  However, if "999.9" is selected, just the
!reverse would be true.
  Priority is only used during Resource Leveling.  If two (or more) tasks
!sharing resources COULD be scheduled during the same period, the
!task(s) with higher priority are scheduled first.
  Priority is assigned on the large Task Form.
+Quit,Index,Resource Leveling,Priority
=Quit,Index,CALF5,TASK122
$CALF7
uWeightingNCalculations Form
sh
When the Percent Achieved field of detailed tasks is rolled up to compute
the Percent Achieved of summary tasks, a weighted average is used.

  Bsln Cost!  (Earned Value Method) Baseline Dollar Value
  Bsln Effort   Like Bsln Cost, but uses the budgeted effort instead of
1cost.  Use when large capital expenses distort tracking.
  Effort      Current task effort.  Less accurate, but does not 
1require a baseline.
  Duration     Even less accurate. Use when no resources, no baseline.
  None       Unweighted average.
+Quit,Index,Percent Achieved
=Quit,Index,TASK113
/5
If a choice is made that requires a baseline, but there is no baseline,
the program acts as though "None" were chosen.

If you see zero amounts rolled up for some tasks, and not others, check 
that all your tasks have baselines set.
$CALN0
uStandard WorkdayBCalendar Settings Form
sh
  The number of hours in a normal workday.
  Time Line uses this number to convert tasks scheduled in days to an
!equivalent number of hours.
  To schedule more work per day, increase this field (answer Keep
!Durations when you leave form) and add workhours to Workhours Form.
$CALN1
uStandard WorkweekACalendar Settings Form
sh
  The number of days (whole days only) in a normal workweek.
  Time Line uses this number to convert tasks scheduled in weeks to an
!equivalent number of days (and indirectly, hours).
  To schedule more work per week, increase this field (answer Keep
!Durations when you leave the form) & add workhours to Workhours Form.
!You may also need to add extra work days on the Dates Form.
$CALN2
uStandard Week Begins>Calendar Settings Form
sh
  The first day of the normal workweek.
  For a normal Monday-Friday workweek, this would be Monday.
  With some Gantt layout scale settings (1 day per character, for
!example), this first day of week governs the dates that are used in
!the dateline above the task bars.
  This determines the As-of Date if "Start of Week" used on Options Form.
$CALN3
uStandard Year Begins (Fiscal Year Begins))Calendar Settings Form
sh
  The month for the start of your year (affects reports printed by year).
  Enter the full month name, or a three-letter abbreviation, such as
!Jan or Oct.  Delete remaining letters with [Del] or [Sh/F9].
  Any month except January indicates a Fiscal Year (all dates will
!contain "FY" to indicate fiscal years).  If Fiscal Year chosen, date
!format (change with Configure / Date Formats) must be 1, 2, or 3.
$CALN4
uPrecisionICalendar Settings Form
sh
  The smallest unit of time to be scheduled.
  Only affects scheduling done in less than one-hour increments.
  If you don't need greater precision, use Hour.  This affords the
!longest overall schedule (approximately 25 years).
  Scheduling to the minute restricts the schedule to approx. six months.
  NOTE: Small precision may change dates in the past to "Non Work".
$CALN5
uFormat End DatesBCalendar Settings Form
sh
  Determines whether a task that concludes at the end of the workday is
!scheduled to end on that workday or at the beginning of the next
!workday (to Time Line, these two times are the same).
  Usually, "End of the day" is the preferred setting.
  Does not affect the scheduling of other tasks.
$COLN0
uColumn NameKCustom Column Form
sh
  The name of the column as it appears in this Column list.
  No commas are allowed in the name.
  "Original Name" (below) shows what the column name was before it had
!ever been changed.
  Title fields (below) control the titles at the top of the columns on
!the Gantt and Tabular reports.
+Quit,Index,Titles
=Quit,Index,COLN4
$COLN1
uDescriptionKCustom Column Form
sh
  Type a description of the field (two lines will be merged into one).
  The combination of these two lines is displayed at the top of the
!screen when the cursor is resting on the column name in the list.
$COLN2
>COLN1
$COLN4
uColumn TitleJCustom Column Form
sh
  Two lines for column headings.
  This column heading is used on screen, reports, and graphs.
  Full Titles are used when the column width is sufficient to hold the
!full text of the Full Title.
  Short Titles are used whenever the column width is too narrow to hold
!the Full Title.
$COLN5
>COLN4
$COLN6
>COLN4
$COLN7
>COLN4
$COLN8
uDefault WidthICustom Column Form
sh
  Width of column when first selected from list.
  You might have to do some experimenting with this field to determine
!the usual width with which you wish to display this column.
$COLN9
uMin DigitsLCustom Column Form
sh
  The fewest number of decimal digits to display for this numeric field.
  If fewer decimals are required to properly display this number, zeros
!will be used to fill.
$COLN10
uMax DigitsLCustom Column Form
sh
  The greatest number of decimal digits to display for this numeric field.
  If more decimals are required to properly display this number, the
!the number will be rounded to match the number entered here.
$COLN11
uExport Column NameDCustom Column Form
sh
  Enter a name here to be used for the field when exporting to other
!products (must be ALL CAPS).
  dBASE does not allow punctuation (spaces, hyphens, etc.) in its field
!names, so do not use it here if you are working with dBASE.
  For spreadsheet products, this name will be range name for the column.
  For database products, this name will be the field name.
  The name entered here will be used by the Import function, so do not
!change this name if you have exported data that you expect to re-import.
$COMMF1
uMethodISetup Communications Form
sh
  uParallel!select if device connected to parallel port.
  uSerial#select if device connected to serial port.
  uDOS Device directs output through DOS communications port (common on
,local area networks but usually not used for local output).
  uNo Output  sends output to a "null" device; useful for testing macros
,and other procedures when no printing/plotting is desired.
$COMMF2
uParallel PortBSetup Communications Form
sh
  Used when the computer has more than one parallel port.
  If your computer has only one parallel port, select "1".
$COMMF3
uSerial PortDSetup Communications Form
sh
  Select the serial port to which your device is connected.
  For help, see the device owner's manual.
$COMMF4
uBaud RateFSetup Communications Form
sh
  Must match your device setup.  Check owner's manual.
  Use highest baud rate accepted by your device for greatest production.
$COMMF5
uData BitsFSetup Communications Form
sh
  Must match your device setup.  Check owner's manual.
  Default is 8.  Some devices require 7.
$COMMF6
uStop BitsFSetup Communications Form
sh
  Must match your device setup.  Check owner's manual.
  Default is 1.  Some devices require 2.
$COMMF7
uParityISetup Communications Form
sh
  Must match your device setup.  Check owner's manual.
  If Start Bits 8, no parity checking is allowed.
$COMMF8
uTime OutGSetup Communications Form
sh
  Use to have Time Line notify you of lengthy interruptions in device
!communication.
  A common Time Out setting is 30.
  Use a number greater than 30 for larger or higher-resolution graphs.
$COMMF9
>COMMF8
$COMMF10
uProtocolGSetup Communications Form
sh
  Must match your device setup.  Check owner's manual.
  Also called "handshaking" in some device manuals.
  Select Auto to have Time Line select an appropriate protocol.
$COMMF11
uDOS DeviceESetup Communications Form
sh
  DOS devices are used, for the most part, to set up for a network
!printer or to redirect output.  If you are working on a local area
!network, consult your network administrator for guidance.
$DATE0
uDOS DateWDate Form
sh
  Changes current date and time.
  wCAUTION: Changes DOS date/time as well.
  To change position of vertical line on Gantt, change uAs-of Date
!on Options Form.
+Quit,Index,Entering Dates,As-of Date
=Quit,Index,.DTFRMTS,OPTN3
$DATE1
uDate[Date Form
sh
  Enter a date here, to move to or to reset the DOS date/time.
  Use any date format (for list of available formats, see "Date Formats"
!below).
+Quit,Index,Date Formats
=Quit,Index,.DTFRMTS
$DOS0
uProgram FileODOS Exit Form
sh
  Enter name of program to run.  When program is finished, Time Line is
!automatically restarted at the same place you left it.
  Name can consist of full pathname.
  Examples: CHKDSK, F:\EMAIL\MAIL.
$DOS1
uParametersQDOS Exit Form
sh
  Command line keywords to be passed to program designated in Program
!File field.
  If you normally run the program by typing its name and one or more
!words following, type those extra words into this field.
$DSPL0
uLayout NameRLayout Form
sh
  Names this combination of settings.
  Appears in Layout List.
  Layout List is sorted alphabetically, so put important words first.
  Cannot have two names exactly alike (one can be capitalized & one not,
!though).
$DSPL1
uNotesXLayout Form
sh
  Use to describe the layout and its use.
  This is for your information only.
  [F2] opens a larger notepad.
  First line of larger note appears in this field.
$DSPL2
uScaleXLayout Form
sh
  Controls compression of dateline and task bars on Gantt view.
  If higher value (longer period of time) entered here:
! The task bars are shortened.
! More time is displayed on each screen.
  For best display, try to stay with "1" (min, hr, day, wk, or mth).
$DSPL3
>DSPL2
$DSPL4
uSlack DisplayPLayout Form
sh
  Use to display slack (thin lines to right of bars) on Gantt view & rpt.
  uTotal shows Total Slack (time a task can be delayed without affecting
'a subsequent fixed task or the schedule end date) on Gantt view.
  uFree  shows Free Slack (...without affecting ANY other task) on Gantt.
  uNone  displays no slack lines.
  If Total or Free selected, resource delay markers ("..." to left of
!tasks delayed by resource conflicts) will be displayed as well.
$DSPL5
uShow Task BarsOLayout Form
sh
  Use to show (or hide) task bars on Gantt view.
  If "No", Progress fields (below) are not applicable.
  Also controls display of task bars on Gantt Report.
  To print a Gantt Report without task bars, use Task Table Rpt instead.
+Quit,Index,Tasks Report
=Quit,Index,REPOTas
$DSPL6
uShow BaselinePLayout Form
sh
  Show a baseline task bar for each task, or not.
  Baseline must be set first (use Schedule/Baseline).
  Use for on-screen comparison of current progress to original plan.
  Shows a second (baseline) line of information for most task columns,
!as well.
  Baseline data can also be shown with specific baseline task columns.
+Quit,Index,Schedule/Baseline
=Quit,Index,SCHEBas
$DSPL7
uProgress DataPLayout Form
sh
  Select data [F2] to show progress on task bars.
  Determines what is represented by pct complete symbols ().
  Progress is rolled up to summary tasks using the Weighting selection
!on the Calculations Form.
/7
  uPercent Achieved    Percent Achieved (Task Form).
  uProportional % Achievd Mathematically enhanced Pct Achvd.
  uBaseline Prop % Achievd Use when showing progress on baseline task bars.
  uElapsed Time Percent  Always shows Pct Achvd to As-of Date line.
  uSpent Effort Percent  Alternate to Pct Achvd = hrs spent / tot effort.
  uSpace          Suppress progress display.
+Quit,Index,Show Baseline,Percent Achieved
=Quit,Index,DSPL6,TASK113
$DSPL8
uShow On (Actual/Baseline)DLayout Form
sh
  Choose to show progress () on actual or baseline task bars.
  The data used to show progress is selected in the previous field.
  If Baseline selected, recommend using "Baseline Proportional Percent
!Achieved" or one of the "% of bsln" data to show progress.
$DSPL9
uColumnWLayout Form
sh
  Select a column name (press [F2]) to display in a Gantt layout column.
  With the list of column names on screen, a definition of the current
!(cursor) column name appears on the top line of the screen.
  Change the name of a column or column heading by pressing [F2] on the
!name of the column in the Column list.
  On Layout Form, sequence of column names determines left-to-right order
!of columns on screen.  Change sequence with [Sh/Up] and [Sh/Down].
$DSPL10
uWidthXLayout Form
sh
  The displayed width of the column data.
  Enter "0" to temporarily hide column; "1" or more replaces it on screen.
  This also controls column width for Gantt and Tasks Reports.
$DSPL11
>DSPL9
$DSPL12
>DSPL10
$DSPL13
>DSPL9
$DSPL14
>DSPL10
$DSPL15
>DSPL9
$DSPL16
>DSPL10
$DSPL17
>DSPL9
$DSPL18
>DSPL10
$DSPL19
>DSPL9
$DSPL20
>DSPL10
$DSPL21
>DSPL9
$DSPL22
>DSPL10
$DSPL23
>DSPL9
$DSPL24
>DSPL10
$DSPL25
>DSPL9
$DSPL26
>DSPL10
$DSPL27
>DSPL9
$DSPL28
>DSPL10
$DSPL29
>DSPL9
$DSPL30
>DSPL10
$DSPL31
>DSPL9
$DSPL32
>DSPL10
$DSPL33
>DSPL9
$DSPL34
>DSPL10
$DSPL35
>DSPL9
$DSPL36
>DSPL10
$DSPL37
>DSPL9
$DSPL38
>DSPL10
$DSPL39
>DSPL9
$DSPL40
>DSPL10
$FLTR0
uFilter NameRFilter Form
sh
  Names this combination of settings.
  A filter name automatically appears in all four (select and three
!highlight) filter lists, and thus can be used to highlight or select.
  Names are sorted alphabetically in lists, so put important words first.
  Cannot have two names exactly alike (one can be capitalized and the
!other not, though).
$FLTR1
uNotesXFilter Form
sh
  A note describing the filter and its use.
  This is for your information only.
  [F2] opens a larger notepad.
  First line of larger note appears in this field.
$FLTR2
uActionWFilter Form
sh
  Controls the overall effect of the filter, no matter what criteria are
!chosen below.
  uFilter    is the normal selection, includes tasks that meet
.criteria entered in following fields.
  uDon't Filter includes all tasks EXCEPT those that meet the criteria.
.It is usually used to hide certain tasks in reports.  For
.example, it could be used to hide tasks coded with
."personal" in the Keyword field.
$FLTR3
uEvery/AnyTFilter Form
sh
  To be filtered, must a task meet all criteria on the form, or just one?
  uAny  selects tasks that meet AT LEAST ONE of the conditions entered
'in the following fields.
  uEvery selects only those tasks that meet ALL of the conditions.
  As an example, a schedule may have some tasks on the critical path and
!some assigned to Bob.  "Any" would filter tasks that are either on the
!critical path or assigned to Bob.  "Every" would filter tasks that are
!BOTH on the critical path and assigned to Bob.
$FLTR4
uCritical PathPFilter Form
sh
  uNo     performs no filtering.
  uYes    filters tasks on the critical path.
  uWithin 20% filters tasks whose Total Slack is within 20% of making the
,task critical (includes tasks already on critical path).

  Use the "Within 20%" option to monitor both critical path and tasks
!that are close to being critical.
$FLTR5
uAchievementRFilter Form
sh
  uLess    filters tasks whose Pct Achvd is less than next field.
  uOver/Equal filters tasks whose % Achvd is at least that of next field.

  Use to filter tasks with no progress (less than 1%), incomplete tasks
!(less than 100%), and completed tasks (over/equal to 100%).
  For example, enter "Over/equal" and "100%" to filter completed tasks.
$FLTR6
uAchievementRFilter Form
sh
  Use with previous field to filter by percent achieved.
  Enter a whole number representing percent achieved.
$FLTR7
uDates (On/After)MFilter Form
sh
  A task will be filtered if ANY PORTION of the task occurs on or after
!the date.
  If no date is entered in the next field, all tasks occurring on or
!after the date will be filtered.
  To make this filter more dynamic, use date codes such as "TODAY" and
!"ASOF" instead of specific dates - the dates to be filtered will change.
+Quit,Index,Entering Dates
=Quit,Index,.DTFRMTS
$FLTR8
uDates (Before)OFilter Form
sh
  Task will be filtered if ANY PORTION of it occurs before the date.
  If no date is entered in the previous field, all tasks occurring before
!the date will be filtered.
  To make this filter more dynamic, use date codes such as "TODAY" and
!"ASOF" instead of specific dates - the dates to be filtered will change.
+Quit,Index,Entering Dates
=Quit,Index,.DTFRMTS
$FLTR9
uMilestonesSFilter Form
sh
  Filter tasks with duration of "0".
  Milestones appear in the Gantt view as "".
$FLTR10
uPartial DependenciesIFilter Form
sh
  Filter tasks involved in one or more partial dependencies.
  Partially dependent tasks have a dependency to another task OTHER THAN
!a Finish-to-Start dependency - Start-to-Start, Finish-to-Finish, Lead
!(overlap), or Lag (gap).
  Tasks with partial dependencies are also noted with "p" or "s" in the
!Status column, and are marked as such on the Dependency List.
$FLTR11
uResource ConflictLFilter Form
sh
  Filter tasks with overscheduled resources.
  Resource conflicts occur when a resource is scheduled to work more
!than the maximum as defined on the Resource/Cost Form.
  Resource conflicts are also noted with "R" or "r" (depending on
!whether resources have been leveled) in the Status column.
  When leveled, delayed tasks' bars will show dots () indicating
!the duration of the delay.
$FLTR12
uLoopYFilter Form
sh
  Filter tasks involved in dependency loop.
  A dependency loop occurs when a chain of dependencies circles back on
!itself (A to B, B to C, C to A).
  Loops are also noted with "L" in the Status column.
  Use to help isolate loop when Time Line states that one exists.
$FLTR13
uPredicted LateOFilter Form
sh
  Filter tasks whose end date is later than baseline.
  A baseline must have been set.
  To further highlight late conditions, display Bsln End Date and End
!Date columns (Layout Form) or "Show Baseline" with End Date column.
$FLTR14
uNeeds UpdateQFilter Form
sh
  Filter tasks whose Start Status should have changed by now.
  Compares each task's Start Status (Future, Started, Done) to the
!current As-of Date.  If the Start Status is inconsistent with the As-of
!(future task that should have started by now, or started task that
!should be done) the task is filtered.
  Helps when updating tasks - allows you to focus on tasks most likely
!to need updating.
  Works similarly to Assisted Update (Assist/Update menu choice).
+Quit,Index,Assisted Update,Updating Hints
=Quit,Index,ASSIUpd,.TRACK
$FLTR15
uTask NameTFilter Form
sh
  Filters tasks whose name matches the name entered here.
  To filter tasks on a PORTION of the task name, use "..":
! uEDIT..!filters sEdit 1st & sEditing!but not s1st Edit.
! u..EDIT!filters s1st Edit & sNo Credit but not s1st Editing.
! u..EDIT.. filters sEdit 1st & s1st Edit  and#s1st Editing.
$FLTR16
uKeywordVFilter Form
sh
  Filters tasks whose keyword matches the keyword entered here.
  To filter tasks on a PORTION of the keyword, use "..":
! uAB..!filters sAB1 & sAbsolutely but not s1AB.
! u..AB!filters s1AB & sTab&but not sFabulous.
! u..AB.. filters sAB1 & s1AB&and#sFabulous.
$FLTR17
uWBSZFilter Form
sh
  Filters tasks whose WBS code matches the WBS code entered here.
  To filter tasks on a PORTION of the WBS, use "..":
! uB11..!filters sB11-123 & sB114.10 but not sAB11.
! u..B11!filters sAB11"& sA14.B11 but not sAB11.00.
! u..B11.. filters sB114.10 & sA14.B11 and#sAB11.00.
$FLTR18
uOBSZFilter Form
sh
  Filters tasks whose OBS code matches the OBS code entered here.
  To filter tasks on a PORTION of the OBS, use "..":
! uMKT..!filters sMKT-04 & sMKTNG  but not s01-Mkt.
! u..MKT!filters s01-Mkt & s2MKT!but not s01-Mktng.
! u..MKT.. filters sMKT-04 & s01-Mkt and#s01-Mktng.
$FLTR19
uData Field / ConditionGFilter Form
sh
  The two Data Field / Condition pairs allow filtering on any field that
!can be displayed on the Gantt view.
  Press [F2] on Data Field to display Layout Column names.  Select one.
  In the Condition field, enter a formula to use in filtering the data.
!For available symbols, select "Conditions" below.
  The math operators available in the Condition fields only operate on
!unumeric fields.  You CAN'T, for instance, filter on task names
!beginning with A or B by specifying a condition of "< C".
  The tilde character(~) may be entered as the first character of a
!condition.  Using a tilde matches exactly those tasks that would
!uNOT have been matched by the condition alone.  For example:
!selecting keyword as the Data Field and entering "Phase1" as the
!condition will select all tasks marked as being in Phase1.  If the 
!condition is changed to "~Phase1", all tasks except those in Phase1 
!are selected.
+Quit,Index,Conditions
=Quit,Index,FLTRCOND
$FLTRCOND
uCondition SymbolsLFilter Form
sh
  To filter on a text field, use ".." and "?":
!u.. at end%= sstarting with (Type uA.. filters ASAP & ALAP.)
!u.. at beginning = sending with!(Linked File u..ABC filters tasks
Flinked to ABC.)
!u.. begin/end"= scontains$(Notes u..Smith.. filters tasks with
F"Smith" somewhere in notes.)
!u?  matches any char in position!(Type uA?AP filters ASAP & ALAP.)
  To filter on a numeric field, use the following:
!="equal to value.
!<>!not equal to value.
!<"less than value.
!>"greater than value.
!<=!less than or equal to value.
!>=!greater than or equal to value.
  To filter on a range of values, use both Data Fields  low end in one,
!upper end in the other.  (Duration in Hours ">8" and "<=40" filters tasks
!of from 9 to 40 hours in duration.)
$FLTR20
>FLTR19
$FLTR21
>FLTR19
$FLTR22
>FLTR19
$FLTR23
uResource KeywordMFilter Form
sh
  Filter tasks assigned to particular group of resources.
  This filter works with the resource/cost keyword.  To be filtered,
!a task must be assigned to a resource with the designated pattern as
!part of the resource keyword.  The pattern entered on the Filter Form
!can occur ANYWHERE in the resource/cost keyword.
  For instance, if "ENG" is entered, then tasks assigned to resources
!with "ENG01", "01-ENG", and "MECH ENGIN" as keywords would be filtered.
$FLTR24
uResourcesTFilter Form
sh
  Filter tasks assigned to particular resources.
  Press [F2] for the Resource/Cost List.  Select an item to filter.
  Optionally, type in a Resource/Cost name.
  If more than one name entered, action depends on "Every,Any" field
!(above).
! uEvery requires that ALL resources specified be assigned.
! uAny!requires that ONLY ONE of the resources specified be assigned.
$FLTR25
>FLTR24
$FLTR26
>FLTR24
$FLTR27
>FLTR24
$GSET1
uPaper SizeKGraphics/Setup Form
sh
  Select paper size to be used for graphs.
  Press [F2] for list of available paper sizes.
  To change paper size while producing graphs, select this menu option
!(Configure/Graphics) again.
$GSET2
uOrientationJGraphics/Setup Form
sh
  uPortrait  prints with short edge of paper across top.  This is the
+better selection if your schedules tend to have many tasks
+over a short period of time (a compressed time scale).
  uLandscape prints with long edge of paper across top.  This is the
+better selection if your schedules tend to have few tasks
+over a long period of time (a lengthened time scale).
$GSET3
uContinuous FeedFGraphics/Setup Form
sh
  Available only when configured for Dot Matrix printers.
  If "Yes", prints each strip of the graph without a break in the paper.
  Allows for easier paste-up when printing large graphs.
$GSET4
uUnit of MeasureFGraphics/Setup Form
sh
  This setting determines whether graph size estimates are displayed in
!inches or centimeters.
$GSET5
uOutput to (Device, File)=Graphics/Setup Form
sh
  uDevice directs plotted output to the configured output device.
  uFile!directs plotted output to a DOS file for later use.  Select
(if transferring to another program or sending via modem.
  sNOTE: Time Line adds a three-digit number to the filename to identify
'pages of the graph, so limit the name to five characters.
$GSET6
uPen Speed / Resolution?Graphics/Setup Form
sh
  Select drawing speed or dots per inch (resolution).  This field
!changes, depending on whether you've configured for plotter or printer.  
  Plotters vary resolution by changing pen speed.  Use Medium for normal
!work.  Use Slow for higher quality, and for transparency film.
  Printers give better graphic quality by printing more dots per inch.
!For laser printers, "High" gives 300 dpi, "medium" 150, "low" 75.
$GSET7
uPen Carousel Capacity@Graphics/Setup Form
sh
  The number of pens in the plotter's carousel.
  The number entered in this field governs whether Time Line will pause
!for pen changes during plotting.  If you enter "6" here, for instance,
!and specify 8 pen colors in the palette (Gantt or PERT Chart Form),
!Time Line will ask you to change pens before drawing with pens 7 and 8.
$GSET8
uHP Autofeed Capability?Graphics/Setup Form
sh
  uNo  stops plotting and prompts for a new page when necessary.
  uYes automatically feeds the next page on multi-page graphs.
$HIST0
uHistogram NameLHistogram Form
sh
  Press [F2] for the Resource List.  Select a resource.
  Optionally, type in a resource name.  (Costs are not allowed.)
  If one resource is selected, the histogram is six lines high; if more
!than one is selected, each histogram is four lines high.
  To print the histogram(s), use Histogram Report (choose to "Duplicate
!On-Screen Histograms").
  [Alt/F8] while on Gantt chart will show histograms of cursor task.
$HIST1
>HIST0
$HIST2
>HIST0
$HIST3
>HIST0
$HIST4
>HIST0
$IMP0
uTaskYImport Form
sh
  Choose "Yes" to import task information.
  Imported file must contain WBS codes.
  This can be used to merge updated information.  For tasks with matching
!WBS codes, the imported information overwrites the current schedule's.
!Tasks with no match are added to the schedule.
  To create schedule, import Task, Resource, Assignment, & Dependency fls.
!Must have exported with "All", or included WBS col with "Gantt Layout".
$IMP1
uTask FilenamePImport Form
sh
>IMPCOMM
$IMPCOMM
  Name of file containing imported information.
  Default name can be overwritten.  (The new name becomes the default.)
  If no file with entered name exists, an error message is displayed and
!logged in the Journal.
  Filename directory determined by Import Directory field below.
$IMP3
uResourceUImport Form
sh
  Choose "Yes" to import resource definitions.
  If Resource name found in Resource/Cost List, data in current schedule
!is overwritten by imported data.
$IMP4
uResource FilenameLImport Form
sh
>IMPCOMM
$IMP6
uAssignmentSImport Form
sh
  Choose "Yes" to import resource assignment information.
  Imported assignments must include WBS code of task.
  If WBS code cannot be found, an error is logged in the Journal.
$IMP7
uAssignment FilenameJImport Form
sh
>IMPCOMM
$IMP9
uDependencySImport Form
sh
  Choose "Yes" to import dependency information.
  Imported dependencies must include WBS code of both predecessor and
!successor.
  If WBS code(s) cannot be found, an error is logged in the Journal.
$IMP10
uDependency FilenameJImport Form
sh
>IMPCOMM
$IMP12
uImport FormatPImport Form
sh
  Press [F2] from this field for list of available formats.
  Selection affects default extension attached to files.
  For Quattro, file must have been saved in ".WK1" format.
  Excel 3 allows saving in Excel 2 format.  However, this action does unot
!create a file that is readable by Time Line.  To import an Excel 3
!spreadsheet, save it in Lotus 1-2-3 Rel. 2.1 format, then import the
!file into Time Line with the Lotus 1-2-3 import option.
  For CSV format, extension can be changed in File Extension field.
$IMP13
uFile ExtensionOImport Form
sh
  Default extension to be attached to import filename(s).
  Can only be changed if either "Time Line CSV (Text)" format chosen.
  Entry here affects all imported filenames.
$IMP14
uImport DirectoryMImport Form
sh
  Drive/directory location of imported file(s).
  Press [F2] from this field for Directory List.
  Example:!C:\123R3\DATA
$JOIN0
uPredecessor (Start, End)ADependency Form
sh
  Is dependency to be joined to start or end of the predecessor?

)55Predecessor
)4
"uStart  &-&  uEnd(Successor
$JOIN2
uTime (Add/Subtract)FDependency Form
sh
  Should time be added (lag) or subtracted (lead)?

&P!36Predecessor
.u  Subtract    uAdd  
,/)
,<
-&5&!Successor
$JOIN3
uTime (Add/Subtract)FDependency Form
sh
  How much time should be added (lag) or subtracted (lead)?

&P!3$Predecessor
.  Subtract  
,/$(subtract u5 Days)
,
-&.Successor
$JOIN4
>JOIN3
$JOIN5
uSuccessor (Start, End)CDependency Form
sh
  Is the dependency to be joined to the start or end of the successor?


  Linked to&*8Predecessor
  uStart6
>&/Successor


  Linked to&*8Predecessor
  uEnd8
5&8Successor

$LINK0
uDirectory / FilenameFTask Link Form
sh
  Enter the directory and filename of the linked file.
  Press [F2] on either field for a Directory List.
$LINK1
>LINK0
$LINK2
uTypeVTask Link Form
sh
  uSchedule Link summarizes an entire other schedule.  Task duration is
/length of summarized schedule if represented as task, or
/latest date in summarized schedule if shown as milestone.
  uTask Link#summarizes ("clones") a task from another schedule.
/Can show length of task, or just end date.  Resource
/Profile Links can show resource assignments (set "Copy
/Resources" to Yes.  Can link to summary or detail task.
$LINK3
uWBS NumberPTask Link Form
sh
  For Task Link, enter WBS code stored in WBS field of the linked task.
  Press [F2] for list of WBS codes in linked file (entered above).
  WBS must have already been entered in linked task; otherwise, error is
!displayed.
$LINK4
uRepresent AsNTask Link Form
sh
  uTask%creates task from start to end of summarized schedule
,(Schedule Link) or length of summarized task (Task Link).
  uEnd Date!creates milestone showing latest date in summarized schedule
!uMilestone  (Schedule Link) or end date of summarized task (Task Link).
  Task is created as fixed date task, using dates from linked schedule.
  If master calendars differ, start date and duration are used to
!determine end date of task, using current schedule's master calendar.
$LINK5
uCopy ResourcesLTask Link Form
sh
  With Schedule Link, summarizes (averages) resource usage over entire
!schedule.
  With Task Link, Resource Profile Links represent detailed resource
!assignments to linked task.  (Can be used to point out resource
!conflicts across schedules.)
$MACFF0
uMacro FileOMacro File Form
sh
  Specify filename for macros (8 characters or less).
  Extension of M$0 is supplied automatically.
$MACFF1
uPathUMacro File Form
sh
  Specify pathname for macro file.
$MACMC0
uStart RecordingFMacro Configuration
sh
  [Alt/=] is default.  Change to avoid conflicts with other programs.
$MACMC1
uStop RecordingGMacro Configuration
sh
  [Alt/-] is default.  Change to avoid conflicts with other programs.
$MACMC2
uMenusPMacro Configuration
sh
  [Alt/F1] is default.  Change to avoid conflicts with other programs.
$MACMC3
uMacro ListKMacro Configuration
sh
  [Alt/F6] is default.  Change to avoid conflicts with other programs.
$MACMC4
uInsertOMacro Configuration
sh
  [Alt/F3] is default.  Change to avoid conflicts with other programs.
$MACMC5
uStep Mode?KMacro Configuration
sh
  Step Mode single-steps through the macro, allowing careful checking of
!its function.
  At each step, any key continues to the next step.
$MACMC6
uPlayback SpeedGMacro Configuration
sh
  Varies the speed with which macros are played back.
  Slow, medium slow, and medium allow visual checking of new macros.
  Fast speed inserts no delays.  The macro operates as fast as your
!computer can work.
$MACMM0
uTitleTMacro Menu Form
sh
  Appears at the bottom of the menu box on playback.
$MACMM1
uMessageRMacro Menu Form
sh
  The entry in these two fields appears as a message at the top of the
!menu box on playback.
  The first message line wraps to the second at the end of the line.
$MACMM2
>MACMM1
$MACMM3
uPrefixSMacro Menu Form
sh
  Appears to the left of the menu choices, to introduce them.
  A colon is automatically provided, following the prefix.  No need to
!enter it as part of the prefix.
$MACMM4
uChoiceSMacro Menu Form
sh
  The entries here become the menu options on playback.
  At least two choices must be entered.
$MACMM5
uMacroTMacro Menu Form
sh
  Each macro name is paired with a choice.  On playback, selecting a
!choice plays the macro identified to its right on this form.
  The macro name entered may already exist or not.
$MACMM6
>MACMM4
$MACMM7
>MACMM5
$MACMM8
>MACMM4
$MACMM9
>MACMM5
$MACMM10
>MACMM4
$MACMM11
>MACMM5
$MACMM12
>MACMM4
$MACMM13
>MACMM5
$MACMM14
>MACMM4
$MACMM15
>MACMM5
$MACMS0
uTitleQMacro Message Form
sh
  Appears at bottom of message box on playback.
$MACMS1
uMessageOMacro Message Form
sh
  Type message to be displayed in these fields.
  Each line automatically wraps to the next field (255 chars total).
  No spaces are added between lines, allowing words to be split.
$MACMS2
>MACMS1
$MACMS3
>MACMS1
$MACMS4
>MACMS1
$MACMS5
>MACMS1
$MACPM0
uMacro NameLPrimary Macro Form
sh
  Enter a 40-character name (appears in Macro List).
  Spaces not allowed.  Use hyphens instead for readability.
  Exact duplicates of names are not allowed.
  To change the name or hotkey of a macro, you must copy it from the list
!with [Sh/Ins], give it a new name or HotKey, then delete the original.
$MACPM1
uMacro HotKeyJPrimary Macro Form
sh
  Enter a hotkey by pressing [Alt] in combination with any letter or
!number key except R and P.  These alt-keys are reserved for
!single-key macro recording and playback, respectively.
  If the entered hotkey has already been used, Time Line asks for a
!confirmation before reusing the hotkey.
  The hotkey appears as a reminder in the description box below the
!Macro List.
$MACPM2
uDescriptionKPrimary Macro Form
sh
  Enter a 60-character description here.
  The description appears as a reminder in the description box below the
!Macro List.
$MACSE0
uMacro NameJSecondary Macro Form
sh
  Enter a name of the secondary macro.  It will appear in the Macro List.
  Duplicates not allowed.
$MACSE1
uMacro HotKeyHSecondary Macro Form
sh
  Enter a hotkey for the secondary macro.
  The hotkey is the easiest way to recall the secondary macro when you're
!ready to use it later in the primary macro recording.
$MACSE2
uDescriptionISecondary Macro Form
sh
  Enter a description.  This will appear below the Macro List.
$MOUS0
uDouble-Click SpeedDMouse Control Form
sh
  When the mouse is clicked twice, within a short time interval, at the 
!same location, this is called a "double click".  Choose how long the 
!interval may be.

!On the Gantt chart, and on many forms and lists, a double click is a
!shortcut, with the same effect as selecting the item and then pressing 
![F2] to edit it.
$MOUS1
uRepeat RateKMouse Control Form
sh
  Limits the maximum speed of scrolling on lists and views.
$NETL0
>DSPL0
$NETL1
>DSPL1
$NETL2
uBox OutlineMPERT Layout Form
sh
  Display task information within boxes, or not.

  uNo  does not display boxes (the layout is compressed).
  uYes displays boxes.
$NETL3
uColumn NameMPERT Layout Form
sh
  Press [F2] for list of fields.  Select an item to display in task box.
  With the list of column names on screen, a definition of the current
!(cursor) column name appears on the top line of the screen.
  On Layout Form, position of column names determines displayed position
!of data in task boxes.  Change sequence with [Sh/Up] and [Sh/Down].
  Columns with "0" width display at top, but not in task boxes.
$NETL4
uWidthSPERT Layout Form
sh
  Width of data item when displayed in task box.
  If width of "0" (or blank) entered, data will appear at top of screen
!for cursor task, but will not appear in boxes.
  Width of task boxes determined by largest combination of field widths.
  If a short left-side item is entered (with no right-side item), it
!uses the entire width of the box in which to display its data.
$NETL5
>NETL3
$NETL6
>NETL4
$NETL7
>NETL3
$NETL8
>NETL4
$NETL9
>NETL3
$NETL10
>NETL4
$NETL11
>NETL3
$NETL12
>NETL4
$NETL13
>NETL3
$NETL14
>NETL4
$NXPR0
>CALC1
$OPTN0
uSchedule NameOOptions Form
sh
  Descriptive name to appear on reports.
  Appears on all reports if "*(CODE(\42))*ScheduleName*" included in Report Heading
!(Report Form).
  Saved with the schedule.
+Quit,Index,Heading Keywords
=Quit,Index,HDGCODES
$OPTN1
uNotesWOptions Form
sh
  A note describing the schedule.
  [F2] opens a larger notepad.
  Appears on all reports if a number greater than 0 is entered in Print
!Options Form Notes on Report Form.
  Saved with the schedule.
+Quit,Index,Print Notes
=Quit,Index,PRNT8
$OPTN2
uResponsibleQOptions Form
sh
  The person responsible for the schedule.
  Appears on all reports if "*(CODE(\42))*Responsible*" included in Report Heading
!(Report Form).
  Saved with the schedule.
+Quit,Index,Heading Keywords
=Quit,Index,HDGCODES
$OPTN3
uAs-of DateROptions Form
sh
  Shows as vertical line on Gantt - schedules nondependent ASAP tasks.
  uCurrent time sets As-of Date to current DOS (computer) date.
  uStart/day  sets As-of Date to 1st work hour of the day.
  uStart/week  sets As-of Date to 1st hour of first workday of the week.
  uManual    allows entry of As-of Date in next field.
  Appears on reports if "*(CODE(\42))*Asof*" included in Report Heading (Rpt Form).
+Quit,Index,Heading Keywords
=Quit,Index,HDGCODES
$OPTN4
uAs-of DateROptions Form
sh
  Enter the As-of Date here.
  Only available when "Manual" selected (previous field).
  As-of Date stays the same until specifically changed on this form.
  Appears on reports if "*(CODE(\42))*Asof*" included in Report Heading (Rpt Form).
+Quit,Index,Entering Dates,Updating Hints,Heading Keywords
=Quit,Index,.DTFRMTS,.TRACK,HDGCODES
$OPTN5
uTask FormSOptions Form
sh
  Selects the large or small Task Form.
  Controls the size of Task Form that appears when:
! [F2] pressed in Task Bar area of Gantt view.
! [Ctl/F2] pressed anywhere on Gantt view.
  Items on large Task Form also available as Gantt columns (Layout Form).
  If large Task Form selected, Assisted Update stops on all started tasks.
  Large/small Assignment Forms are selected with Cost Tracking field.
+Quit,Index,Cost Tracking
=Quit,Index,OPTN7
$OPTN6
uCost TrackingOOptions Form
sh
  Invokes cost tracking options.
  With Cost Tracking set to "Yes":
! Large assignment forms are displayed when assigning resources/costs.
! When a task is marked Done, Time Line asks for confirmation before
#reconciling assigned effort to actual effort.
!Note: Large and small task forms are selected with Task Form field.
+Quit,Index,Task Form,Percent Achieved
=Quit,Index,OPTN6,TASK113
/4
 If Cost Tracking is set to "No", updating the percent achieved will 
  automatically update each assigned resource so that the amount recorded
  as uspent relative to the total amount budgeted is proportional to
  the percent achieved.
$OPTN7
uDate DisplayPOptions Form
sh
  Determines whether time of day is displayed when dates are shown.
  Affects date display in all parts of Time Line - Gantt view, Task Form,
!and all reports.
  If "Date Only" selected, times are still internally maintained, and can
!even be entered in date fields.  They won't display or print, though.
  Date format is changed with Configure/Date Formats.
+Quit,Index,Configure Date Format
=Quit,Index,CONFDat
$OPTN8
uUndo/Redo LimitMOptions Form
sh
  The limit on the number of steps Time Line can undo.
  Only changes to tasks, resources, and dependencies can be undone.
  Steps cannot be undone after any File functions (Save, Retrieve, etc.)
  Maximum is 999, although a practical recommendation is 10-15.
  A higher number here uses more memory, reduces the number of tasks.
  Undo actions with [Sh/F10] or Assist/1-Undo.
  Redo (replay) actions with [Ctl/F10] or Assist/2-Redo.
+Quit,Index,Undo,Redo
=Quit,Index,SCHE1-U,SCHE2-R
$OPTN9
uStart Date RestrictionFOptions Form
sh
  uNo Sooner Than restricts fixed tasks from starting sooner than their
0start date (can start later, however, if predecessors
0force).
  uMust Start   forces fixed tasks to start on their entered start
0dates, no matter the action of their predecessors.
  This field sets the default for new fixed tasks.  The action can be
!overridden for a particular task by changing the Start Date Restriction
!column.
/4
Because uMust Start overrides other project constraints, it will
schedule tasks at dates even if they are not realistic.  We recommend
using uNo Sooner Than whenever possible, because that will allow 
Time Line to warn you if slippage is imminent. 
+Quit,Index,Start Date Restriction Column
=Quit,Index,TCOL113
$OPTN10
uForce CriticalNOptions Form
sh
  uNo  uses the critical path calculation to determine whether fixed tasks
%are to be considered "critical".
  uYes forces all fixed tasks to "critical", no matter their relationship
%to other tasks when the critical path is calculated.
  This field sets the default for new fixed tasks.  The action can be
!overridden for a particular task by changing the Force Critical column.
+Quit,Index,Force Critical Column
=Quit,Index,TCOL112
$OPTN11
uStyleWOptions Form
sh
 uOutline   depicts a summary task as a large box
-surrounding the task boxes of its family.

-Summary/
-  &  &  
-  Detail 1ĺDetail 2  
-  &  &  
-8

  uTraditional depicts a summary task as two small partial boxes
-at either end of its family.
V
-START  &  &  #END
-Summary ĺDetail 1ĺDetail 2Summary 
-&  &  &  &
$OPTN12
uBox PlacementOOptions Form
sh
  Fine-tunes the position of the task boxes on the PERT View.
  uDraft produces a normal box arrangement (shorter time).
  uFinal compresses the box placement (longer time).
  Try experimenting with this field.  Try both options to see which
!produces the best PERT arrangement in an acceptable time.
$PATH10
>PRJT1
$PATH11
>PRJT0
$PATH20
>PRJT0
$PATH21
uFilename ExtensionHFile Save Form
sh
  Three-character rightmost portion of filename.
  Often used to group files by name, such as ".TXT" for ASCII text files.
$PATH22
>PRJT1
$PRJT0
uDOS FilenameSFile Form
sh
  Name to be used in storing schedule on disk.
  Follows normal DOS naming conventions (no embedded spaces, 8 chars max).
  On File Access Form, wildcards ("*" and "?") are allowed.
$PRJT1
uDirectoryVFile Form
sh
  Hard disk location for schedule files.
  Enter directory and (optionally) drive letter.  (The current drive is
!assumed if no drive letter is entered.)
  Trailing backslash can be entered, but it's not necessary.
  uExamples:  D:\TL5\DATA\#=  \TL5\DATA directory on Drive D.
,\TL5\DATA\PROJ1  =  \TL5\DATA\PROJ1 on current drive.
$PRJT2
uPreviousWFile Form
sh
  This allows you to retain a number of previously saved versions of the
!current schedule.
  A previous version can be retrieved by selecting File/Previous.
  Previous versions are saved in the current schedule's directory.
  Each time the schedule is saved, the oldest version is deleted.
  Please don't consider this as your only backup.  It is important that
!you save hard disk data to an external medium (such as floppy disks).
!This prevents data loss if you lose access to your hard disk.
$PRNT0
uSend Output ToOReport Form
sh
  uPrinter  prints to printer, using normal or compressed characters.
  uDisk File places reports in a text file on disk, for processing by
+another program such as Sideways or a word processor.
  uScreen  "prints" reports to the screen, for preview.
  These settings stay in effect for all schedules until changed.
$PRNT1
uFormatWReport Form
sh
  Formats add special characters to reports - used by your printer.
  Usually, "Normal" and "Compressed" are used with Printer, "Disk File"
!is used with Disk File, and "None" is used with Screen.
  However, you can create a disk file with Normal or Compressed format,
!or with None to transmit the file via modem.
$PRNT2
uDisk File FilenameKReport Form
sh
  The full pathname of the disk file - may include drive and directory.
  Default is current drive, current directory.
  Example:  C:\WP51\DATA\RPT1.TXT
  Recommend placing disk file in data directory of target product.
$PRNT3
uTop Line MarginNReport Form
sh
  First line of page on which to print.
  The default of 6 gives a one inch top margin on most printers.
$PRNT4
uBottom Line MarginKReport Form
sh
  Last line of page on which to print.
  The default of 60 gives a one inch bottom margin on most printers.
$PRNT5
uLeft Side MarginMReport Form
sh
  First column (left side) in which to print.
  Measurement is affected by Normal/Compressed choice in Format field,
!and by the width of printed characters on your printer.
  With Normal format, 6 provides about a one-inch margin at left.
$PRNT6
uRight Side MarginLReport Form
sh
  Last column (right side) in which to print.
  Measurement is affected by Normal/Compressed choice in Format field,
!and by the width of printed characters on your printer.
  With Normal format, 78 provides about a one-inch margin at right.
  For all printers, the maximum for Right Side Margin is 230.
$PRNT7
uReport HeadingOReport Form
sh
  Press [F2] for the notepad.  (Report Heading can be edited.)
  For a list of codes available in the heading, choose "Keywords" below.
+Quit,Index,Keywords
=Quit,Index,HDGCODES
$HDGCODES
uKeyword8Description
s<!G
Asof;As-of Date (Options Form)
Calculation (Calc)-"Resource Leveled" if leveling on
A(Options Form), or "CPM" if not
Date (Today)3Current DOS date
DateAndTime (DT)/Current DOS date and time
ProjectDir (PjDir, Directory)"Current Directory (File Form)
Recalc9"Yes" if schedule has been recalculated;
A"No" if it needs recalc [F9]
Responsible (Resp)-Responsible person (Options Form)
ScheduleFile (SchFile, Schedule) DOS Filename (File Form)
ScheduleName (SchName))Schedule Name (Options Form)
Serial9Serial number of installed Time Line pgm
UserName (User)0Name of person operating Time Line

  Surround keywords with asterisks, and place in heading, title, and note
!areas.  They are replaced with current information when report is run.
  "(L)" aft keywrd justifies left within asterisks; "(R)" justifies right.
  Upper/lower case is ignored in keywords & abbreviations.
/

uKeywords - Entered3Keywords - Printed
sA"A

Schedule Name : *(CODE(\42))*Schedulename (L) *"Schedule Name : Production Schedule
Responsible!: *(CODE(\42))*responsible (R)  *"Responsible!:*John Doe
Recalculated? : *(CODE(\42))*Recalc*(CODE(\42))* - *(CODE(\42))*Calc*$Recalculated? : Yes - CPM

sA"A

*(CODE(\42))*DATE (L)"*(CODE(\42))*  ABC Company+Mar 12, 1990"ABC Company
)*(CODE(\42))*Schname (L)(*/Production Schedule

sA"A

 Project Mgr/As-of$Project Mgr/As-of
 -. -.$-. -.
 *(CODE(\42))*resp(l)%*(CODE(\42))* *(CODE(\42))*asof(r)%*$John Doe+Mar 12, 1990
$PRNT8
uPrint Options Form NotesEReport Form
sh
  Notes for the report heading can be placed in the Options Form notes.
  Enter the number of note lines to print.
  Remember that this is part of page heading, so keep number of lines low.
$PRNT9
uPrint Names of Currently Active Filters6Report Form
sh
  Select "Yes" here to print active filter names as part of the heading.
  Names used for each type of filter are listed separately.
$RSRC0
uResource (or Cost) Name?Resource/Cost Form
sh
  Identifies resource or cost in Resource/Cost List - 10 chars max.
  Recommend using abbreviated names (or initials) to save space.
  Names are alphabetized in Resource/Cost List.
  Appears in Resource and Cost columns (Gantt view).
  Use this to filter tasks assigned to a particular resource.
$RSRC1
uFull NameMResource/Cost Form
sh
  A longer, more descriptive name that also appears in Resource/Cost List.
  If abbreviation or initials used for short name, enter full name here.
  Used for description only - no filtering.
$RSRC2
uKeywordOResource/Cost Form
sh
  A coding field used for grouping resources (department, skills, etc.)
  Use this to filter tasks assigned to a particular resource group.
$RSRC3
uNotesQResource/Cost Form
sh
  A descriptive note - might contain personal information about a
!resource, or historical data about a cost.
  [F2] opens a larger notepad.
$RSRC4
uResource (or Cost) Type?Resource/Cost Form
sh
  Determines whether you are defining a resource or cost, and what type.
  Select "Resource" for people (or equipment that is time shared and
!can affect the schedule if over allocated).
  For information on cost types, select from menu below.
  You cannot make changes to this field, such as changing a variable cost
!to a unit cost, after assigning the resource or cost to tasks.
+Quit,Index,Fixed Cost,Unit Cost,Variable Cost
=Quit,Index,COSTF,COSTU,COSTV
$RSRC5
uResource CalendarEResource/Cost Form
sh
  Press [F2] to access this resource's calendar.
  Mark appropriate dates as unavailable, and the resource will not be
!assigned to work on those days.  This action can be overridden by
!setting Honor Resource Calendars to "No" (Calculations Form).
  Tasks can be delayed until resource is available, or split around them.
  Print with Reports/Tables/Calendars.
+Quit,Index,Honor Res. Calendars,Delay/Split
++Availability
=Quit,Index,CALF3,TASK19,RSRC6
$RSRC6
uAvail. ProfileHResource/Cost Form
sh
  Press [F2] to access the list of availabilities for a resource.
  Is only used by levelling.  Not used by CPM.
  Increase (decrease) number and/or percentage available as of any date.
  Vacations or unavailability: Do not enter an availability of zero here.
!Instead, mark day(s) as Unavail. on the Resource Calendar (prev field).
  Print with Reports/Tables/Availabilities.
+Quit,Index,Unavailable & Vacations,Delay/Split
=Quit,Index,RSRC5,TASK19
/6
  This number and percentage determines when a resource is overscheduled.
  Tasks with overscheduled resources have an "R" in the Status column.
  If Resource Leveling is turned on (Calculations Form), tasks assigned
!to these overscheduled resources may be delayed.
  If resource is an individual, enter "1".  If a group, enter number.
/9
  This profile shows changes in how many of a resource are available,
!provided that the calendar indicates that they are available.
  Use to show people becoming more productive, or changing from full
!to part time, or visa versa.
  Split tasks that are duration-driven do not split around insufficient
!availability on this profile.  Split tasks that are effort-driven will, 
!if levelling is used.
  Split tasks that are effort-driven "contour" to use periods of greater
!availability.
$RSRC7
uRate ProfileJResource/Cost Form
sh
  Press [F2] to access the Rates List for a resource (is also available
!for unit and variable costs).
  Increase (decrease) hourly or unit cost of resource/cost as of any date.
  If more than one rate entered, the cost of a task may depend on the 
!date at which it is scheduled.
  Print with Reports/Tables/Rates.
$RSRC8
uLevel this Resource?BResource/Cost Form
sh
  uNo  exempts resource from Resource Leveling (activated on Calculations
%Form).  Helpful when scheduling managers and administrative
%personnel, whose workloads are less closely monitored.
  uYes includes resource in Resource Leveling.
+Quit,Index,Resource Leveling
=Quit,Index,CALF5
$RSRC9
uDefault AssignmentDResource/Cost Form
sh
  This number and percentage is used when originally assigning resources
!to tasks.
  If resources assigned from the Resource/Cost List, this number/percent
!appears on the Resource Assignment Form (and can be overwritten).
  If resource names are typed in by hand, this number/percent is
!automatically used for the assignment (the form won't appear).
+Quit,Index,Calculator,Availability
=Quit,Index,CALC,RSRC6
$RSRC10
>RSRC9
$RSRC11
uOvertime Rate Multiplier>Resource/Cost Form
sh
+Quit,Index
=Quit,Index
$RS.MONTH
uResource Calendar
sh
  Change a date between Unavail. and available by pressing [Spacebar].
  For macros, [Ins] sets a date to Unavail.; [Del] makes it available.
  Move among the dates of a month with the [Arrow] keys.
  Move from month to month with [Tab] and [Sh/Tab], or [PgDn] and [PgUp].
  Go to a specific date by pressing [F5].
  Resource Calendars can be changed at any time.
  Days that are marked Non Work on the Master Calendar cannot be changed
!to work days on the Resource Calendar.
  Tasks are delayed until after unavailable periods, or are split around
!them.  (Action depends on Unavail. field of Task Form.)
  Resource Calendars can be ignored by setting the Honor Resource
!Calendars field (Calculations Form) to "No".
  Use Resource Calendars instead of lowering a resource's Availability to
!zero.  If task is set to "Unavail: Split", it will then be interrupted
!by the unavailable time.
  Print using Reports/Tables/Calendars.
+Quit,Index,Delay/Split,Honor Res. Calendars,Availability
=Quit,Index,TASK19,CALF3,RSRC6
$RTRP0
uReport onKResource Report Form
sh
  uResources     includes only resources in report.
  uCosts & Resources includes both resources and costs in report.

  To include only selected resources or costs, use a select filter.
+Quit,Index,Select Filter
=Quit,Index,FLTR24
$RTRP1
uColumn DataIResource Report Form
sh
  Select a column of data to include in report (press [F2] for list).
  Be sure to include Resource Name or Resource Full Name to identify the
!rows in the report.
  Sequence of Data Columns determines order of columns on report.
$RTRP2
uWidthOResource Report Form
sh
  Enter the width of the column to print on the report.
  If width entered as "0" (or left blank), column will not print.
$RTRP3
>RTRP1
$RTRP4
>RTRP2
$RTRP5
>RTRP1
$RTRP6
>RTRP2
$RTRP7
>RTRP1
$RTRP8
>RTRP2
$RTRP9
>RTRP1
$RTRP10
>RTRP2
$RTRP11
>RTRP1
$RTRP12
>RTRP2
$RTRP13
>RTRP1
$RTRP14
>RTRP2
$RTRP15
>RTRP1
$RTRP16
>RTRP2
$RTRP17
>RTRP1
$RTRP18
>RTRP2
$RTRP19
>RTRP1
$RTRP20
>RTRP2
$RTRP21
>RTRP1
$RTRP22
>RTRP2
$RTRP23
>RTRP1
$RTRP24
>RTRP2
$SSAV1
uTasksRFile Extract Form
sh
  uEntire Outline extracts all currently selected tasks.  If a select
0filter is active (its name appears at top of form), only
0the selected tasks are extracted.
  uCursor Family  extracts only the current (cursor) task and its family.
0If a select filter is active, only selected tasks in the
0current family are extracted.
$SSAV2
uResources & CostsFFile Extract Form
sh
  uEntire List    copies the current schedule's Resource/Cost List to
4the extracted file without modification.
  uAssigned Ones Only creates a subset Resource List in the extracted
4file that only includes those resources assigned to
4extracted tasks.
$SUMM10
uName[Task Form
sh
  The task name (30 characters - letters, numbers, special symbols).
  Duplicate names are allowed, and the name can be changed at any time.
  Can be abbreviated on Gantt with Task Name, Abbreviated column.
  Filter (highlight or select) with Task Name field on the Filter Form.
  For a unique task identifier, use WBS field, not this one.
+Quit,Index,Filter,WBS
=Quit,Index,FLTR15,SUMM120
$SUMM11
uKeywordXTask Form
sh
  Optional coding field (10 chars - letters, numbers, special symbols).
  Use to group tasks (such as "!" for all important tasks).
  Display on Gantt with Keyword column (Layout Form).
  Filter (highlight or select) groups with Keyword field on Filter Form.
+Quit,Index,Filter
=Quit,Index,FLTR16
$SUMM12
uNote[Task Form
sh
  Task comments.
  [F2] opens a larger notepad.
  Top line of note (from notepad) appears in this one-line field.
  Display on Gantt view with Notes column (Layout Form).
  Print complete task notes (all lines from notepad) with Detail Report,
!or press [F2] then [F6].
+Quit,Index,Detail Report
=Quit,Index,TLDR11
$SUMM16
uDuration Time UnitsDSummary Task Form
sh
  This task is a summary task; its duration is calculated from the
!earliest start date of its children to the latest end date.
  This time units field CAN be changed, however, to express the
!calculated duration in your preferred units.
$SUMM18
uEffort Time UnitsFSummary Task Form
sh
  This task is a summary task; its effort is calculated as the sum of its
!children's efforts.
  This time units field CAN be changed, however, to express the
!calculated effort in your preferred units.
$SUMM120
uWork Breakdown StructureGTask Form
sh
  The Work Breakdown Structure code, or WBS, is a numbering system that
!allows you to represent the task's position in the outline as a code.
  Enter WBS codes quickly with Assist/WBS.
  Filter (highlight or select) with WBS field on the Filter Form.
  Extract portion of WBS to file using File/Save with Extract option.
  WBS must be entered to export and reimport from another program.
+Quit,Index,WBS Manager,Filter,Extract
=Quit,Index,ASSIWbs,FLTR17,EXTRACT
$SUMM121
uOrganizational Breakdown Structure=Task Form
sh
  The Organizational Breakdown Structure code, or OBS, can be used to
!group tasks according to the part of the organization working on them.
  Since the OBS can be used for filtering, selective reports are possible.
  If you want to produce a report listing all task assignments for each
!resource, use the Assignments Report (by Resource).
+Quit,Index,Filter,Assignments Report
=Quit,Index,FLTR18,TABLAss
$SUMM125
uResources/CostsHSummary Task Form
sh
  Since resource assignments to detail tasks are automatically rolled up
!to summary tasks, explicit summary task assignments are NOT RECOMMENDED.
  Costs are more commonly added at the summary level than resources.
  Do NOT assign a resource to both a summary and one of its details.
  Rather than assigning at the summary level, enter the responsible
!resource in OBS or Aux field, then add that column to Resource layouts.
$SUMM127
>SUMM125
$SUMM129
>SUMM125
$SUMM131
>SUMM125
$SUMM133
>SUMM125
$SUMM135
>SUMM125
$SUMM137
>SUMM125
$SUMM139
>SUMM125
$SUMM141
>SUMM125
$SUMM143
>SUMM125
$SUMM145
>SUMM125
$SUMM147
>SUMM125
$SUMM149
>SUMM125
$SUMM151
>SUMM125
$SUMM153
>SUMM125
$SUMM155
>SUMM125
$SUMM157
>SUMM125
$SUMM159
>SUMM125
$SUMM161
>SUMM125
$SUMM163
>SUMM125
$SUMM165
>SUMM125
$SUMM167
>SUMM125
$SUMM169
>SUMM125
$SUMM171
>SUMM125
$SUMM20
>SUMM10
$SUMM21
>SUMM11
$SUMM22
>SUMM12
$SUMM26
>SUMM16
$SUMM28
>SUMM18
$SUMM225
>SUMM125
$SUMM227
>SUMM125
$SUMM229
>SUMM125
$SUMM231
>SUMM125
$SUMM233
>SUMM125
$SUMM235
>SUMM125
$SUMM237
>SUMM125
$SUMM239
>SUMM125
$SUMM241
>SUMM125
$SUMM243
>SUMM125
$SUMM245
>SUMM125
$SUMM247
>SUMM125
$SUMM249
>SUMM125
$SUMM251
>SUMM125
$SUMM253
>SUMM125
$SUMM255
>SUMM125
$SUMM257
>SUMM125
$SUMM259
>SUMM125
$SUMM261
>SUMM125
$SUMM263
>SUMM125
$SUMM265
>SUMM125
$SUMM267
>SUMM125
$SUMM269
>SUMM125
$SUMM271
>SUMM125
$TASK10
>SUMM10
$TASK11
>SUMM11
$TASK12
>SUMM12
$TASK13
uTask TypeVTask Form
sh
  uASAP  schedules task after latest of its predecessors.
  uALAP  schedules task before earliest of its successors.
  uFixed allows entry of start/end dates, puts task at/after/before
'specific date/time.
+Quit,Index,Details,Predecessor,Successor
=Quit,Index,TASK13,PRED,SUCC
$TASK13
uTask Type (continued)JTask Form
sh

  ASAP is the most often used task type.  An ASAP task is scheduled after
!all of its predecessors have completed and (if Resource Leveling is on)
!when resources are available.
  ALAP is used to schedule tasks that should happen just before some
!other (usually fixed) event, or as late in the schedule as possible.
  Fixed is used to enter a starting or ending date (for a project phase,
!for instance), and to lock in deadlines and schedule meetings.

uFixed tasks have a preferred start date entered in the Start Date field.

The exact effect of the entered Start Date can be controlled by the
Start Date Restriction field, which is not available on the Task Form, but
is available as a spreadsheet column.  Fixed Date tasks can be restricted
to start No Sooner, No Later, or Must Start on a certain date.

The default value of this, for newly-created Fixed tasks, is set on the
Options Form.
+Quit,Index,Start Date Restriction
=Quit,Index,TCOL113
$PRED
uPredecessor
sh
sDefinition: A task that must be accomplished before another can begin.

*Task A  %-uPredecessor
*Task B'%&Successor

  To indicate a predecessor of the current task:
! mark the current task as a successor (press [Spacebar] twice)
! move to the task you wish to be a predecessor
! press [F3] to make the dependency
+Quit,Index,Dependency Instructions
=Quit,Index,DEPENS
$SUCC
uSuccessor
sh
sDefinition: A task that can begin after the current task finishes.

*Task A  %-Predecessor
*Task B'%&uSuccessor

  To indicate a successor of the current task:
! mark the current task as a predecessor (press [Spacebar] once)
! move to the task you wish to be a successor
! press [F3] to make the dependency
+Quit,Index,Dependency Instructions
=Quit,Index,DEPENS
$TASK14
uDriven ByVTask Form
sh
  uDuration allows direct entry of task duration in Duration field (below).
  uEffort!derives length of task from resources assigned.  As more
*resources are assigned, task duration decreases.
+Quit,Index,Details
=Quit,Index,TASK14
$TASK14
uDriven ByVTask Form
sh
  uDuration allows direct entry of task duration in Duration field (below).
*Resource assignments (if any) determine total task effort.
  uEffort!derives length of task from resource assignments.  As more
*resources are assigned, task duration decreases.  Resources
*are interchangeable - all work together until task is finished.
*Duration = Total Effort / Resources Assigned.
/7
  Display on Gantt with Duration Method column on the Layout Form.
  View resource assignments on Histograms using [Alt/F8] or [F8].
  Effort-driven tasks must have resource assignments.  If no resource
!assignments are made, task is made Duration-driven.
  The effect of the Unavailable (Delay/Split) field differs depending on
!this Driven By field.
/6
  An Effort-Driven task can use Time Line's ucontouring feature.  If
!the Unavail. (Delay/Split) field says "Split", then each resource
!can work varying amounts on the task at different times, perhaps as a
!background task, interrupted by vacations, and interrupted or reduced
!by higher-priority tasks.
+Quit,Index,Delay/Split,Contouring
=Quit,Index,TASK19,CONTOUR
$TASK15
uDurationWTask Form
sh
  For Duration-driven tasks ("Driven By" field), enter an estimate of the
!task timing.  Duration can be expressed in any period of time.
  For Effort-driven tasks, duration is calculated from amount entered in
!Effort field plus number of resources assigned.  Time period (days,
!weeks, etc.) can be changed to any unit, however.
+Quit,Index,Details,Driven By field
=Quit,Index,TASK15,TASK14
$TASK15
uDuration (continued)KTask Form
sh

  Duration can also be entered with [F2] on a Gantt Duration column.
  When tracking progress, change duration to reflect revised estimate to
!complete.
  Math can be used in this field - " + 5" adds 5 to duration, " * 1.2"
!increases it by 20% (helpful when creating macros).
  [Ctl/Left] moves cursor to Minutes; [Ctl/Right] moves it to Months.
  Display on Gantt with any of Duration columns (Layout Form).

When a task is Effort-driven, it's duration may depend on the date at
which it is scheduled, because of the effect of vacations and contouring
around other tasks.  For this reason, the duration that is shown on this
form is an estimate, which may change during recalc.
+Quit,Index,Calculator,Delay/Split
=Quit,Index,CALC,TASK19
$TASK16
uDuration time unitsLTask Form
sh
  Interacts with previous field to give duration.
  For Effort-driven tasks, can be changed to show task duration in the
!selected time units.
  [Ctl/Left] ALWAYS moves cursor to Minutes; [Ctl/Right] ALWAYS moves
!cursor to Months (helpful when recording macros).
$TASK17
uEffortYTask Form
sh
  For Effort-driven tasks ("Driven By" field), enter an estimate of the
!total task effort.  After effort is entered and resources are assigned,
!duration is calculated.
  For Duration-driven tasks, effort is calculated from entered duration
!and resource assignments.  Time period (days, weeks, etc.) can be
!changed to any unit, however.
  Effort can also be entered with [F2] on a Gantt Effort column.
+Quit,Index,Details,Driven By field
=Quit,Index,TASK17,TASK14
$TASK17
uEffort (continued)MTask Form
sh

  When tracking progress, change effort to reflect revised estimate to
!complete.
  Math can be used in this field - " + 5" adds 5 to effort, " * 1.2"
!increases it by 20%.
  Display on Gantt with any of Effort columns on Layout Form.

When a task is duration-driven, it may split around vacations.  For this
reason, the actual effort of the task may depend on the date at which it is
scheduled, and may be changed by recalc.  For these tasks, the effort field
on the task for is an estimate, not necessarily a final value.
+Quit,Index,Calculator,Delay/Split
=Quit,Index,CALC,TASK19
$TASK18
uEffort time unitsNTask Form
sh
  Interacts with previous field to give effort.
  For Duration-driven tasks, can be changed to show task effort in the
!selected time units.
  [Ctl/Left] ALWAYS moves cursor to Minutes; [Ctl/Right] ALWAYS moves
!cursor to Months (helpful when recording macros).
$TASK19
uUnavailable: Delay/SplitGTask Form
sh
  uDelay indicates that the task, or its future portion, is to be
'delayed until it can be scheduled without interruptions.
  uSplit allows the task to be interrupted.  Exact effect depends on type,
'as described below:
/7
!If task is driven by:
! uDuration: vacations will cause gaps, but duration remains constant.
! uEffort: each resource will work at the available rate up to a
#maximum of the percent entered on the resource's Assignment Form,
#interrupted by vacations and ureduced by higher-priority tasks.
#This is known as sResource Contouring.
/6
  If a task is split, the task bar on the Gantt chart will remain solid
!(because the various resources assigned may split at different dates).
!However, the exact effect of any splitting is easily seen on the
!histograms.  Pressing the Histogram Hotkey [Alt/F8] shows histograms
!of the resources of the cursor task, highlighting its resource profile.
+Quit,Index,Driven By field,Contouring
=Quit,Index,TASK14,CONTOUR
$TASK110
uStatusYTask Form
sh
  uFuture  indicates task is not yet started (no percent achieved, and
)probably no actual work recorded).
  uStarted indicates task under way (Start Date field open for revision).
  uDone"indicates task completed (Start/End Date fields open).

  Display on Gantt with Start Status column (Layout Form).
+Quit,Index,Details
=Quit,Index,TASK110
$TASK110
uStatus (continued)MTask Form
sh

  For tracking, Percent Achieved (large Task Form) is automatically set
!to 100% when task is marked "Done".
  If Cost Tracking is set to "No" (Options Form), all work (spent) is
!automatically considered accomplished when task is marked "Done".
  "Needs Update" filter finds all tasks whose status should have changed.
!(Given current As-of Date, what should status be?)
  Assisted Update is interactive.  On all tasks needing update, asks if
!status should be changed - allows quick update of selected tasks.
+Quit,Index,Percent Achieved,Cost Tracking
=Quit,Index,TASK113,OPTN6
$TASK111
uStartZTask Form
sh
  Only accessible for Fixed tasks, or when task marked Started or Done.
  For Fixed tasks, exact meaning depends on Start Date Restriction field.
  Enter start date and duration - Time Line calculates end date.
  Erase [Sh/F9] start date, enter duration & end date - Time Line
!calculates start date.
+Quit,Index,Entering Dates,Start Date Restriction
=Quit,Index,.DTFRMTS,TCOL113
$TASK112
uEnd\Task Form
sh
  Only accessible for fixed tasks, or when task marked Done.
  Enter start date and duration - Time Line calculates end date.
  Erase [Sh/F9] start date, enter duration & end date - Time Line
!calculates start date.
+Quit,Index,Entering Dates
=Quit,Index,.DTFRMTS
$TASK113
uPercent AchievedOTask Form
sh
  Percentage of real progress toward completing task.
  Compare with actuals, entered on Assignment Form.  Percent achieved
!measures the portion of the task that has been accomplished.  Actuals
!is a record of work and/or cost expended.  The comparison of these two
!against original plan (baseline) yields several measures of progress.
  Can only be entered on detail tasks.
  Rolls up to summary tasks.  Most accurate if you have assigned resources
!(at their proper cost rate) and set a baseline before starting to track
!percent achieved - in other words, before the project starts.
+More,Quit,Index,Achievement Rollup
=TASK113,Quit,Index,CALF7
$TASK113
uPercent Achieved (continued)CTask Form
sh
 If Cost Tracking is turned off, updating the percent achieved will 
  automatically update each assigned resource so that the amount 
  recorded as uspent relative to the total amount budgeted is 
  proportional to the percent achieved.

The lower left corner of the Task Form - Achievements and Expenditures -
shows several useful figures for gauging task progress.
 uBasln  shows the total baseline effort and dollars (acts as a way of
'freezing the original plan as a budget).
 uAchvd  (on detail tasks) allows entry of percent achieved; (summary
'tasks) shows roll-up achievement.  Also displays time and dollars
'represented by the achievement.
 uSpent  consolidates - in percentage, time, and dollars - the total of
'actuals entered on the Resource/Cost Assignment Forms.

Just by glancing at this corner, you can compare your achievement with
your expenses, and monitor your budget as set in the baseline.
+Quit,Index,Achievement Rollup,Cost Tracking
++Baseline
=Quit,Index,CALF7,OPTN6,SCHEBas
//
uPercent Achieved (continued)CTask Form
sh
Index to the lower left corner, Achievements and Expenditures:

"Basln: u1  100 % u2 3 weeks$u3 $120
"Achvd: u4 [33 ]% u5 1 week%u6  $40
"Spent: u7"7 % u8 0.2 weeks"u9!$8

u1: 100%.,Achieving the full baseline is worth 100%
u2: Baseline Effort...The baseline was expected to take this much effort.s*
u3: Baseline Value."The baseline was expected to cost this much money.s*
u4: Percent Achieved..Entered by you or rolled-up from child tasks.
u5: Effort Achieved...Percent Achieved times Baseline Effort.s*
u6: Earned Value.$Percent Achieved times Baseline Value.s*
u7: Percent Spent.#Spent Value divided by Baseline Value.s*
u8: Effort Spent.$Entered on Assignment Forms or computed.
u9: Value Spent.%Entered on Assignment Forms or computed.
7(See Cost Tracking reference below.)

s*These fields require that a baseline has been set.
+Quit,Index,Achievement Rollup,Cost Tracking,Baseline
=Quit,Index,CALF7,OPTN6,SCHEBas
$TASK120
>SUMM120
$TASK121
>SUMM121
$TASK122
uPriorityWTask Form
sh
  3 digits, 1 decimal (suggest using "500" as medium priority for large
!projects).
  With Resource Leveling turned on (Calculations Form), determines which
!task receives resources (and is scheduled first) when they become
!available.  
  Either high or low numbers can be considered highest priority.  Change
!on Options Form.
+Quit,Index,Resource Leveling,Highest Priority
=Quit,Index,CALF5,CALF6
$TASK123
uLink to FileSTask Form
sh
  Use to link tasks and/or summarize schedules across files (Cross
!Project Links).
  Link to either Time Line or On Target schedules.
  Press [F2] to access Task Link Form for link details.
  When a link is established, Time Line changes the Task Type to Fixed.
!Task Links remain fixed.  Schedule Links can be changed to ASAP or ALAP.
+Quit,Index,Details,Schedule/Task Link
=Quit,Index,TASK123,LINK2
$TASK123
uLink to File (continued)GTask Form
sh

  A link can be represented as an end date milestone or as a task "clone"
!(start/end dates and task bar).
  Links can summarize all resource assignments.
  With Resource Profile Links, a Task Link may be used to represent
!discrete, accurate resource assignments from one schedule in another.
  Delete link by pressing [Del] on Link to File field.
+Quit,Index,Schedule/Task Link
=Quit,Index,LINK2
$TASK125
uResource/Cost AssignmentGTask Form
sh
  Assign a resource or cost here.
  Assignment is made at default percentage (Resource/Cost Form) unless
!changed for this task on Assignment Form [F2].
  Assign by typing name into blank, or press [F2] to select from list.
  Change by typing new name, or press [Sh/F8] to select from list.
  Delete by pressing [Sh/F9] on name.
  Change assignment percentage by pressing [F2] on name.
  Assignments can also be made by pressing [F2] on Gantt Resource column.
+Quit,Index,Details,Default Assignment
=Quit,Index,TASK125,RSRC9
$TASK125
uResource/Cost Assignment (continued);Task Form
sh

  If resource is overscheduled, an arrow () appears to left of name.
  Resolve overscheduling by decreasing assignment percentage [F2],
!or assigning a replacement resource.
  Use Histogram view [F8] to display graphic view of up to five resources'
!work loads.  [Alt/F8] displays histograms for current task's resources.
  When manual methods exhausted, use Resource Leveling (Calculations
!Form) to resolve all remaining conflicts.
+Quit,Index,Histogram view
=Quit,Index,VIEWHis
$TASK127
>TASK125
$TASK129
>TASK125
$TASK131
>TASK125
$TASK133
>TASK125
$TASK135
>TASK125
$TASK137
>TASK125
$TASK139
>TASK125
$TASK141
>TASK125
$TASK143
>TASK125
$TASK145
>TASK125
$TASK147
>TASK125
$TASK149
>TASK125
$TASK151
>TASK125
$TASK153
>TASK125
$TASK155
>TASK125
$TASK157
>TASK125
$TASK159
>TASK125
$TASK161
>TASK125
$TASK163
>TASK125
$TASK165
>TASK125
$TASK167
>TASK125
$TASK169
>TASK125
$TASK171
>TASK125
$TASK20
>TASK10
$TASK21
>TASK11
$TASK22
>TASK12
$TASK23
>TASK13
$TASK24
>TASK14
$TASK25
>TASK15
$TASK26
>TASK16
$TASK27
>TASK17
$TASK28
>TASK18
$TASK29
>TASK19
$TASK210
>TASK110
$TASK211
>TASK111
$TASK212
>TASK112
$TASK225
>TASK125
$TASK227
>TASK125
$TASK229
>TASK125
$TASK231
>TASK125
$TASK233
>TASK125
$TASK235
>TASK125
$TASK237
>TASK125
$TASK239
>TASK125
$TASK241
>TASK125
$TASK243
>TASK125
$TASK245
>TASK125
$TASK247
>TASK125
$TASK249
>TASK125
$TASK251
>TASK125
$TASK253
>TASK125
$TASK255
>TASK125
$TASK257
>TASK125
$TASK259
>TASK125
$TASK261
>TASK125
$TASK263
>TASK125
$TASK265
>TASK125
$TASK267
>TASK125
$TASK269
>TASK125
$TASK271
>TASK125
$TLAR0
uGroup ByIAssignments Report Form
sh
  uTasks#uses tasks as the major heading.  Task columns are shown
+first, with resource and assignment columns to the right.
+Each new task produces a new section of the report.
  uResources uses resources/costs as the major heading.  Resource (and
+cost) columns are shown first, with task and assignment
+columns to the right.  Each resource produces a new section.
  Report includes closed tasks, but not tasks hidden by select filter.
$TLAR1
uShowMAssignments Report Form
sh
  For the resource section, choose to show just resources, or costs as
!well.
$TLAR2
uDate RangeGAssignments Report Form
sh
  Limit the report to tasks occurring within this date range.  Any tasks
!that start or end within the period will be shown.
  Use words such as "today" and "asof", and math such as "plus 2 weeks"
!to build flexibility into the report (dates will not have to be
!specifically entered).  This is especially helpful with report macros.
+Quit,Index,Entering Dates
=Quit,Index,.DTFRMTS
$TLAR3
>TLAR2
$TLAR4
uTask ColumnFAssignments Report Form
sh
  Press [F2] to select from a list of data columns.
  Report columns are arranged in the sequence entered on this form.
  Task Name, Abbreviated Name, or WBS should be chosen to identify tasks.
$TLAR5
uWidthLAssignments Report Form
sh
  Change the default column widths, if need be.
  Total of all columns cannot exceed 230 characters.
  Enter "B" after width number to produce a blank column of that width.
!(Useful for edit listings and turnaround reports.)
$TLAR6
>TLAR4
$TLAR7
>TLAR5
$TLAR8
>TLAR4
$TLAR9
>TLAR5
$TLAR10
>TLAR4
$TLAR11
>TLAR5
$TLAR12
>TLAR4
$TLAR13
>TLAR5
$TLAR14
uResource ColumnBAssignments Report Form
sh
  Press [F2] to select from a list of data columns.
  Report columns are arranged in the sequence entered on this form.
  Resource Name or Full Name should be chosen to identify resources.
$TLAR15
>TLAR5
$TLAR16
>TLAR14
$TLAR17
>TLAR5
$TLAR18
>TLAR14
$TLAR19
>TLAR5
$TLAR20
>TLAR14
$TLAR21
>TLAR5
$TLAR22
uAssignment Column@Assignments Report Form
sh
  Press [F2] to select from a list of data columns.
  Report columns are arranged in the sequence entered on this form.
  Assignment columns give information about the way resources and costs
!are assigned to tasks.
$TLAR23
>TLAR5
$TLAR24
>TLAR22
$TLAR25
>TLAR5
$TLAR26
>TLAR22
$TLAR27
>TLAR5
$TLAR28
>TLAR22
$TLAR29
>TLAR5
$TLAR30
>TLAR22
$TLAR31
>TLAR5
$TLAR32
>TLAR22
$TLAR33
>TLAR5
$TLAR34
>TLAR22
$TLAR35
>TLAR5
$TLAR36
>TLAR22
$TLAR37
>TLAR5
$TLAR38
>TLAR22
$TLAR39
>TLAR5
$TLAR40
>TLAR22
$TLAR41
>TLAR5
$TLDR0
uTask NamesLDetail Report Form
sh
  uFull Outline&precedes each task name with its parentage,
5using a multiple line, indented format.
  uAbbreviated Outline precedes names with single-line parentage, each
5parent's name abbreviated to six characters.
  uName Only)prints task name without parentage.
  uWBS & Name(print WBS & name, separated by dash.
$TLDR1
uTask DataMDetail Report Form
sh
  Press [F2] to select field from list.
  Data is printed in two columns, as arranged on form.
  If text data unable to fit in column, it is truncated at right.
  If numeric data unable to fit in column, it is replaced with asterisks.
  If a left column is selected with no accompanying right column, left
!column data can extend to right side of report, if necessary.
$TLDR2
>TLDR1
$TLDR3
>TLDR1
$TLDR4
>TLDR1
$TLDR5
>TLDR1
$TLDR6
>TLDR1
$TLDR7
>TLDR1
$TLDR8
>TLDR1
$TLDR9
>TLDR1
$TLDR10
>TLDR1
$TLDR11
uNotesQDetail Report Form
sh
  This field allows printing of each Task Note, no matter how many lines
!are used in the note.
  Enter "Yes" to print Notes, then enter a number to restrict the
!printing to a number of lines.
  If you leave the number of lines BLANK, all Note lines are printed.
$TLDR12
>TLDR11
$TLDR13
uAssignmentsKDetail Report Form
sh
  uNo&does not print resource assignment information.
  uSummarize shows names and assignment amounts of the resources assigned
+to each task.
  uDetails!shows resource names and assignment amounts, plus percentage
+and duration of assignment.
$TLDR14
uShow CostsLDetail Report Form
sh
  uNo  does not include cost information when printing assignments.
  uYes includes columns for assigned and spent cost when showing resource
%assignments.
$TLDR15
uPredecessorsJDetail Report Form
sh
  "Yes" prints all predecessors.
  Prints details of dependency in parentheses.
$TLDR16
uSuccessorsLDetail Report Form
sh
  "Yes" prints all successors.
  Prints details of dependency in parentheses.
$TLDR17
uPredecessor/Successor Task Names6Detail Report Form
sh
  When printing predecessors or successors, select format.
  Choices operate similarly to Task Names field.
+Quit,Index,Task Names
=Quit,Index,TLDR0
$TLDR18
uSuppress Section Headers>Detail Report Form
sh
  On a task-by-task basis, "Yes" will not print a heading for sections
!having no data.
$TLDR19
uPage BreaksKDetail Report Form
sh
  uNo  prints report in continuous strips, over paper perforations.
  uYes skips over paper perforations.
  On LaserJet and DeskJet, select "Yes".  These printers cannot print to
!edge of paper.
$TLDR20
uPage HeadingJDetail Report Form
sh
  Heading is created on Report Form, using keywords and notepad.
  If "First Page", heading is printed on first page only.
  If Page Breaks set to "No", heading is printed on first page only.
  Footing (report title, page number, strip number) printed on bottom of
!every page if Page Breaks set to "Yes".
$TLDR21
uOne Task per PageEDetail Report Form
sh
  If "Yes", printer skips to top of page for every new task.
$TLGGC00
  Press [F2] for color list.
  Greys are substituted for colors on monochrome devices.  See Manual.
$TLGGC0
uPalette NameDGantt Chart Palette Form
sh
  This name appears on the Gantt Chart Palette List.  It installs the
!color choices made on the rest of this form.
$TLGGC1
uNotesKGantt Chart Palette Form
sh
  Description of this palette.  [F2] displays notepad.
$TLGGC2
uTEXT: Title & Legend<Gantt Chart Palette Form
sh
  Affects title, notes, and legend text.  These are entered on the Chart
!Title Form, accessed by pressing [F2] on the Title & Legend field.
>TLGGC00
$TLGGC3
uTEXT: HeadingCGantt Chart Palette Form
sh
  Affects spreadsheet and task bar (date line) column headings.
  Also affects task bar labels.
>TLGGC00
$TLGGC4
uLINES: BordersBGantt Chart Palette Form
sh
  Affects lines drawn around chart and lines drawn between columns.
>TLGGC00
$TLGGC5
uLINES: As-of Date?Gantt Chart Palette Form
sh
  Affects vertical line indicating effective date of graph data.
  As-of Date is set on Options Form.
>TLGGC00
$TLGGC6
uLINES: Major grid?Gantt Chart Palette Form
sh
  Vertical lines in task bars area that mark major time periods.
  Shown on chart when "Vertical Grid" selected on Gantt Chart Form.
>TLGGC00
$TLGGC7
uLINES: Minor grid?Gantt Chart Palette Form
sh
  Vertical dashed lines in task bars area that mark minor time periods.
  Shown on chart when "Vertical Grid" selected on Gantt Chart Form.
>TLGGC00
$TLGGC8
uBACKGROUND: Page@Gantt Chart Palette Form
sh
  Affects area outside of the text border (title, notes, etc.)
>TLGGC00
$TLGGC9
uBACKGROUND: Heading=Gantt Chart Palette Form
sh
  Affects column headings above spreadsheet and task bars areas.
>TLGGC00
$TLGGC10
uBACKGROUND: Data Columns8Gantt Chart Palette Form
sh
  Affects text columns, such as task name, selected with Layout Form.
  Highlight filter background overrides this color for filtered tasks.
>TLGGC00
$TLGGC11
uBACKGROUND: Task Bars;Gantt Chart Palette Form
sh
  Affects the area behind the task bars themselves.
>TLGGC00
$TLGGC12
uFILTERS: Foreground=Gantt Chart Palette Form
sh
  Affects names and task bars for each of the three highlight filters.
  Does not affect task bar labels.
  If task is filtered by more than one highlight filter, color for
!lower-numbered filter is used.
>TLGGC00
$TLGGC13
uFILTERS: Background=Gantt Chart Palette Form
sh
  Affects the background of task names for each of the three highlight
!filters.
  Task bars area is not affected.
  If task is filtered by more than one highlight filter, color for
!lower-numbered filter is used.
>TLGGC00
$TLGGC14
>TLGGC12
$TLGGC15
>TLGGC13
$TLGGC16
>TLGGC12
$TLGGC17
>TLGGC13
$TLGGC18
uSPREADSHEET AREA: Open Summary Tasks,Gantt Chart Palette Form
sh
  Affects summary tasks whose details are shown.
  If summary is closed, it is colored with "All Other Tasks" color.
>TLGGC00
$TLGGC19
uSPREADSHEET AREA: All Other Tasks/Gantt Chart Palette Form
sh
  Affects detail tasks and closed summary tasks.
>TLGGC00
$TLGGC20
uTASK BAR AREA: Open Summary Bars0Gantt Chart Palette Form
sh
  Affects task bars for summary tasks whose details are shown.
  If closed summary, task bars are colored with "All Other Tasks" color.
  Achieved portion of task is colored with "Achievement" color.
>TLGGC00
$TLGGC21
uTASK BAR AREA: All Other Task Bars.Gantt Chart Palette Form
sh
  Affects task bars for detail tasks and closed summary tasks.
  Achieved portion of task is colored with "Achievement" color.
>TLGGC00
$TLGGC22
uTASK BAR AREA: Milestones7Gantt Chart Palette Form
sh
  Affects milestones other than those marked "Done".  (They are colored
!with "Achieved" color.)
>TLGGC00
$TLGGC23
uTASK BAR AREA: Baseline9Gantt Chart Palette Form
sh
  Affects baseline task bars, if shown.
  If progress shown on baseline, achieved portion shown in "Achieved"
!color.
>TLGGC00
$TLGGC24
uTASK BAR AREA: Achievement6Gantt Chart Palette Form
sh
  Affects portion of task bars representing achievement.
  Overrides any other task bar color.
>TLGGC00
$TLGGC25
uTASK BAR AREA: Slack<Gantt Chart Palette Form
sh
  Affects the symbol showing the late end date of a task with slack.
>TLGGC00
$TLGGT0
uLayout NameMGantt Chart Form
sh
  The Gantt Layout name to use for this graph.
  As with the on-screen Gantt view, affects text columns shown at left,
!plus other items such as scale and slack display.
  Press [F2] for Gantt Layout List.
  Changes made to layouts here affect layout when used on screen.
  If this field left blank, the active Gantt Layout is used.
$TLGGT1
uPalette NameLGantt Chart Form
sh
  The name of the color palette to use with this graph.
  Press [F2] for list of palettes.
  Palette should be appropriate for final destination (if sending to file
!for later printing on a laser printer, select "Laser Printers").
$TLGGT2
uTitle & LegendJGantt Chart Form
sh
  Press [F2] to display the Chart Title Form.
  Enter text to be displayed in the title, notes, and legend areas.
$TLGGT3
uPrint onPGantt Chart Form
sh
  uFirst Page prints titles, notes, and legend one time only.
! The page on which they print is determined by entries on the Chart
#Title Form.  A title at "Top Left", for instance, would print on the
#first page.  A legend at "Bottom Right" would print on the last page.
! The chart border is drawn around the entire chart.
! Prints separate sheets that must be taped together for a large chart.
  uEach Page  prints titles, notes, and legend on each chart page.
! The chart border is drawn around each page.
! The first text column is repeated on each page.
! Suitable for binding, or for copying and distributing in meetings.
$TLGGT4
uLINES: CornersJGantt Chart Form
sh
  uSquare outlines the entire chart with a square-cornered box.
  uRound  rounds the corners on the outline box.
$TLGGT5
uLINES: Borders (Thin, Thick, Double)4Gantt Chart Form
sh
  Affects the lines drawn around the chart and the lines within the
!chart (between columns of text).
  Double lines are drawn with shading between the lines, if the device
!supports it.
$TLGGT6
uLINES: Horizontal GridBGantt Chart Form
sh
  If "Yes", draws horizontal lines between tasks.
  Does not affect height of graph.
$TLGGT7
uLINES: Vertical GridDGantt Chart Form
sh
  If "Yes", draws vertical lines to mark time periods.
  Colors of lines are selected with "Major grid" and "Minor grid" on
!Palette Form.
$TLGGT8
uExtra SpacingKGantt Chart Form
sh
  If "Yes", places blank line between groups of tasks.
  Groups are determined by the "Through Outline Level" field.
! "1" places a blank line between outermost level summary tasks
! "2" places a blank line between all second level groups, and so on
$TLGGT9
>TLGGT8
$TLGGT10
uBaseline BarLGantt Chart Form
sh
  uOverlap  shows baseline as thicker task bar placed behind actual
*task bar.  This creates a "thermometer" effect.
  uSeparate shows baseline and actual task bars on separate lines.
*Actual task bars are lines with triangles at start and finish.
  For baseline bars to show, the Show Baseline field must be set to "Yes"
!on the layout selected in Layout Name above.
$TLGGT11
uAlways Show ActualsEGantt Chart Form
sh
  If "No", actual task bars are shown only when actual timing does NOT
!equal baseline.  When actual and baseline coincide, only baseline is
!shown.
$TLGGT12
uScaleSGantt Chart Form
sh
  Affects the size of the task bars area.
  Dimensions are accurate for a graph printed at 100% of original size
!(this may change if you elect to autoscale).
  This setting overrides any date range set with a Select Filter.
$TLGGT13
>TLGGT12
$TLGGT14
>TLGGT12
$TLGGT16
uDate RangeNGantt Chart Form
sh
  Affects the amount of time shown in the Task Bars area.
  Does not affect the selection of tasks to be shown.
  This setting overrides the date range set on the Layout Form.
+Quit,Index,Entering Dates
=Quit,Index,.DTFRMTS
$TLGGT17
>TLGGT16
$TLGGT18
uColumn NameMGantt Chart Form
sh
  As many as four task columns can be used to label task bars.
  Press [F2] to call up a list of column names to be displayed on the
!Task Bar area.  Select the placement of the label in the Position field.
  If more than one column is placed in a particular position, the items
!are separated by commas.
$TLGGT19
uWidthSGantt Chart Form
sh
  The number of characters to display.
  If text is too large to fit, only left-most characters are shown.
  If a number is too large, asterisks (***) are shown.
$TLGGT20
uPositionPGantt Chart Form
sh
  The position of the label, relative to the task bar.
  If more than one column is placed in a particular position, the items
!are separated by commas.
$TLGGT21
>TLGGT18
$TLGGT22
>TLGGT19
$TLGGT23
>TLGGT20
$TLGGT24
>TLGGT18
$TLGGT25
>TLGGT19
$TLGGT26
>TLGGT20
$TLGGT27
>TLGGT18
$TLGGT28
>TLGGT19
$TLGGT29
>TLGGT20
$TLGPC0
uPalette NameEPERT Chart Palette Form
sh
  This name appears on the PERT Chart Palette List.  It installs the
!color choices made on the rest of this form.
$TLGPC1
uNotesLPERT Chart Palette Form
sh
  Description of this palette.  [F2] displays notepad.
$TLGPC2
uTEXT: Title & Legend=PERT Chart Palette Form
sh
  Affects title, notes, and legend text.  These are entered on the Chart
!Title Form, accessed by pressing [F2] on the Title & Legend field.
>TLGGC00
$TLGPC3
uTEXT: HeadingDPERT Chart Palette Form
sh
  Affects date line above task boxes when "Periodic PERT" selected.
>TLGGC00
$TLGPC4
uLINES: BordersCPERT Chart Palette Form
sh
  Affects lines drawn around chart (and lines drawn down from date line
!when "Periodic PERT" selected).
>TLGGC00
$TLGPC5
uBACKGROUND: PageAPERT Chart Palette Form
sh
  Affects area outside of the text border (title, notes, etc.)
>TLGGC00
$TLGPC6
uBACKGROUND: Heading>PERT Chart Palette Form
sh
  Affects date line shown above task boxes when "Periodic PERT" selected.
>TLGGC00
$TLGPC7
uBACKGROUND: Chart@PERT Chart Palette Form
sh
  Affects the task box area.
>TLGGC00
$TLGPC8
uBACKGROUND: Task Boxes;PERT Chart Palette Form
sh
  Affects task boxes that are not highlighted with a filter.
>TLGGC00
$TLGPC9
uFILTERS: Foreground>PERT Chart Palette Form
sh
  Affects task box information for each of the three highlight filters.
  Affects lines around boxes, as well.
  If task is filtered by more than one highlight filter, color for
!lower-numbered filter is used.
>TLGGC00
$TLGPC10
uFILTERS: Background>PERT Chart Palette Form
sh
  Affects task box background for each of the three highlight filters.
  If task is filtered by more than one highlight filter, color for
!lower-numbered filter is used.
>TLGGC00
$TLGPC11
>TLGPC9
$TLGPC12
>TLGPC10
$TLGPC13
>TLGPC9
$TLGPC14
>TLGPC10
$TLGPC15
uDATA: Open Summary Tasks9PERT Chart Palette Form
sh
  Affects summary tasks whose details are shown.
  If summary is closed, it is colored with "All Other Tasks" color.
>TLGGC00
$TLGPC16
uDATA: All Other Tasks<PERT Chart Palette Form
sh
  Affects detail tasks and closed summary tasks.
>TLGGC00
$TLGPC17
uGRAPH SYMBOLS: Open Summary Boxes0PERT Chart Palette Form
sh
  Affects task boxes for summary tasks whose details are shown.
  If closed summary, task boxes are colored with "All Other Tasks" color.
>TLGGC00
$TLGPC18
uGRAPH SYMBOLS: All Other Boxes3PERT Chart Palette Form
sh
  Affects task bars for detail tasks and closed summary tasks.
>TLGGC00
$TLGPC19
uGRAPH SYMBOLS: Milestone Boxes3PERT Chart Palette Form
sh
  Affects boxes representing tasks with zero duration.
>TLGGC00
$TLGPC20
uGRAPH SYMBOLS: PERT Dependencies1PERT Chart Palette Form
sh
  Affects lines representing dependencies that are drawn between boxes.
>TLGGC00
$TLGPG1
uAutoscalePChart Size Form
sh
  "Yes" causes Time Line to reduce or enlarge chart proportionally so
!that it fits on one page.
  Changes in scale, width, and height are shown in Resize To and Reduce/
!Enlarge To fields below.
$TLGPG2
uResize toPChart Size Form
sh
  Either Pages Across or Pages Down can be entered.  An entry in one
!forces a calculated change to the other.
$TLGPG3
>TLGPG2
$TLGPG4
uReduce/Enlarge toHChart Size Form
sh
  Enter percent here to force recalculation of Pgs Across and Pgs Down.
$TLGPG5
uPreview on ScreenHChart Size Form
sh
  "Yes" shows the chart on screen before sending to output device.
  A chart shown on screen can be printed by pressing [F10].
$TLGPG6
uSave Schedule First?EChart Size Form
sh
  uYes saves the schedule before starting to send data to the output
%device.  (This is a safety measure that will save the schedule
%changes should problems arise using the output device.)
  uNo  does not save the schedule automatically.
$TLGPT0
uLayout NameNPERT Chart Form
sh
  The PERT Layout name to use for this graph.
  As with the on-screen PERT view, affects text shown in boxes and box
!borders.
  Press [F2] for PERT Layout List.
  Changes made to layouts here affect layout when used on screen.
  If this field is left blank, the active PERT Layout is used.
$TLGPT1
uPalette NameMPERT Chart Form
sh
  The name of the color palette to use with this graph.
  Press [F2] for list of palettes.
  Palette should be appropriate for final destination (if sending to file
!for later printing on a laser printer, select "Laser Printers").
$TLGPT2
uTitle & LegendKPERT Chart Form
sh
  Press [F2] to display the Chart Title Form.
  Enter text to be displayed in the title, notes, and legend areas.
$TLGPT3
uTASK BOXES: Style (Thin, Thick, Double)2PERT Chart Form
sh
  Affects boxes drawn around each task.
  Double lines are drawn with shading between the lines, if the device
!supports it.
$TLGPT4
uTASK BOXES: Corners (Square, Round)6PERT Chart Form
sh
  Affects the corners of task boxes.
  Task boxes with rounded corners cannot have shadows.
$TLGPT5
uTASK BOXES: ShadowsFPERT Chart Form
sh
  If "Yes", gives task boxes a 3-D quality.
  Shadows cannot be drawn on task boxes with rounded corners.
$TLGPT6
uDEPENDENCY LINES: Style (Thin, Thick, Double),PERT Chart Form
sh
  Affects lines drawn between tasks representing dependencies.
  Double lines are drawn with shading between the lines, if the device
!supports it.
$TLGPT7
uDEPENDENCY LINES: Corners (Square, Round)0PERT Chart Form
sh
  Affects the way dependency lines turn corners.
  Dependency lines with rounded corners cannot have shadows.
$TLGPT8
uDEPENDENCY LINES: Shadows@PERT Chart Form
sh
  If "Yes", adds a drop shadow to dependency lines, similar to task box
!shadows.
  Shadows cannot be drawn on task boxes with rounded corners.
$TLGPT9
uPeriodic PERTLPERT Chart Form
sh
  Time-phases the chart.  Time scale is placed above the chart (use Time
!Period field to control scale).  Boxes are placed within time frame of
!their start date.
$TLGPT10
uTime PeriodNPERT Chart Form
sh
  Controls the time periods placed above a periodic PERT Chart.
  Builds bands of time into which task boxes are placed, based on actual
!or baseline start date.
$TLGPT11
uArrange Tasks byIPERT Chart Form
sh
  uActual!places tasks into time periods based on the task's actual
*start date.
  uBaseline places tasks into time periods based on the task's
*baseline start date.
$TLGPT12
uEliminate Empty Time Periods to Save Space/PERT Chart Form
sh
  Selecting "Yes" here removes any time periods in which no tasks start.
!In a monthly chart, for instance, the time periods could go from May to
!July if no tasks start in June.
$TLGR0
uDate RangeMGantt Report Form
sh
The Date Range settings allow you to limit the Gantt Report to a specific 
period of time between the start and end dates you enter.

  The entire schedule prints if you do not enter a start or end date.
  This does not limit the task names that print, it just restricts the
!date range on the task bar area.
+Quit,Index,Entering Dates
=Quit,Index,.DTFRMTS
$TLGR1
>TLGR0
$TLGR2
uSpacingsOGantt Report Form
sh
  uSingle prints single-spaced, matching screen presentation.
  uDouble inserts a blank line between tasks, (or, if the report
(includes baseline tasks, after each task pair).
$TLGR3
uGridSGantt Report Form
sh
On Gantt Reports with many tasks, it is sometimes difficult to line up the
task bars with the dateline at the top of the page.  The grid makes it
easier for your eye to follow the position of the task bar up to the
dateline.

  Choose "Yes" to print a grid.
  If you are going to print your Gantt Report to a WordStar file, do
!not use a grid.  In some cases, the dots of the grid fall at the
!beginning of the line, and WordStar tries to interpret them as dot
!commands.
$TLGR4
uPage BreaksLGantt Report Form
sh
  "Yes" allows page breaks, and opens the next field to allow page breaks
!based on the outline structure.
  This also causes the printer to skip over perforations.
$TLGR5
uNew Page at Outline Level>Gantt Report Form
sh
  Enter the outline level number at which page breaks are to be taken.

!For example, if you enter "1", a page break is taken before each
!top-level task.  If you enter "2", page breaks are taken before each
!second-level task, and so on.

  The larger the number, the greater the number of page breaks.
  If you have multiple projects within a schedule, you can use this
!feature to separate the project reports.
$TLGR6
uHeadings/LegendHGantt Report Form
sh
  uYes prints each page of the Gantt Report with heading information,
%dateline, and legend.
  uNo  prints heading on first page, legend on last page, and column
%headings on every page.
$TLGTI0
uTitle AreaNChart Title Form
sh
  Text entered in these lines prints in title area.
  The 1st of these three lines is printed 50% larger than chart text.
  Lines 2 and 3 are printed 20% larger than chart text.
  Keywords can be inserted in titles.  See "Keywords" below.
+Quit,Index,Keywords
=Quit,Index,HDGCODES
$TLGTI1
>TLGTI0
$TLGTI2
>TLGTI0
$TLGTI3
uTitle atPChart Title Form
sh
  The title area can be printed at the utop or ubottom of the chart.
  uLeft!prints title area at left side; titles are left-justified.
  uCenter prints in center; titles are centered.
  uRight  prints at right side; titles are right-justified.
  Title area, notes, and legend must be placed in three different areas.
$TLGTI4
>TLGTI3
$TLGTI5
uNotes AreaNChart Title Form
sh
  The notes area can be used like another title area.
  Keywords can be inserted in notes.  See "Keywords" below.
  Select "Legend" to display chart symbols and their meanings.
+Quit,Index,Keywords
=Quit,Index,HDGCODES
$TLGTI6
>TLGTI5
$TLGTI7
>TLGTI5
$TLGTI8
>TLGTI5
$TLGTI9
>TLGTI5
$TLGTI10
uNotes atPChart Title Form
sh
  The notes can be printed at the utop or ubottom of the chart.
  uLeft!prints notes at left side; lines are left-justified.
  uCenter prints in center; lines are centered.
  uRight  prints at right side; lines are right-justified.
  Title area, notes, and legend must be placed in three different areas.
$TLGTI11
>TLGTI10
$TLGTI12
uLegendRChart Title Form
sh
  "Yes" displays the legend of symbols and colors used in the chart, plus
!filter information, if filters are active.
$TLGTI13
>TLGTI12
$TLGTI14
>TLGTI12
$TLHR0
uPage BreaksHHistogram Report Form
sh
  uYes causes page breaks and prints page numbers.
  uNo  avoids page breaks for a wall-chart type report.
$TLHR1
uSeparate Page for Each Histogram?2Histogram Report Form
sh
  This field allows each resource's histogram to be printed on a separate
!page.
  "Yes" here overrides the entry in the Spacing Between Histograms field.
$TLHR2
uIgnore Left Margin after 1st Strip?0Histogram Report Form
sh
  Select "Yes" if you are going to be joining strips for a large chart.
!All strips after strip 1 will print with no left margin, making it
!easier to tape the strips together.
$TLHR3
uPage HeadingsFHistogram Report Form
sh
  uFirst Page prints heading (from Report Form) on first page only.
  uEvery Page prints heading on each page of report.
$TLHR4
uPage FootingsFHistogram Report Form
sh
  uFirst Page prints footing (title, page, strip) on first page only.
  uEvery Page prints footing on each page of report.
$TLHR5
uRow HeadingsGHistogram Report Form
sh
  uFirst Page prints vertical scale on first page only.
  uEvery Page prints vertical scale on each page of report.
$TLHR6
uDate HeadingsFHistogram Report Form
sh
  uFirst Page prints horizontal scale (dates) on first page only.
  uEvery Page prints horizontal scale on each page of report.
$TLHR7
uVertical Step SizeAHistogram Report Form
sh
This field controls the vertical scale of the Histogram Report.  For
example, if Total Dollars were selected as the data to display, a step
size of "1" would cause each printer line to represent one dollar of cost
assigned to the resource; the histograms would be too tall.  In this case,
a step size of "100" might be more appropriate.

You may need to experiment with this field and the Time Period field on
the previous form to create an attractive report.  We suggest printing
the report to screen until you're close to the proper scaling.
$TLHR8
uSpacing Between Histograms9Histogram Report Form
sh
By default, the Histogram Report prints a histogram for each resource on
the project.  (Resource filters can be used to limit this.)  Use this
field to specify the number of blank lines to leave between adjacent
resource's histograms.
$TLHR9
uGrid LineJHistogram Report Form
sh
This field controls the horizontal lines printed in the background of the
histogram as a reference.  An entry of "5" here, for instance, would
print a horizontal line twice in a histogram that is 12 characters tall.
$TLHR10
uUnlimited Page Width?Histogram Report Form
sh
  uYes "prints" the report with an unlimited width for later printing
!with a sideways printing program.
$TLLOG0
uUser NameULogin Form
sh
This form only appears in the LAN Server version of Time Line.  Enter your
user name in the space provided.

  No one else can be using Time Line with the name you enter.
  Time Line gives three chances to enter a valid user name.  (Names are
!determined at time of original installation.)  If a valid name is not
!entered, you are returned to DOS.

!uIf you experience problems:
>.NETADMI
$TLPR0
uPage BreaksFPage Break Control Form
sh
This form appears automatically for several reports.  It allows you to
refine the layout of the report.

In this first Page Breaks field:

  uYes causes page breaks and prints page numbers on each page.
  uNo  avoids page breaks for a wall-chart type report.
$TLPR1
uOutline Level or Task/Resource Page Breaks'Page Break Control Form
sh
  uNew Page at Outline Level  allows control of page breaks to group
,families in the outline.  Enter the outline level at which
,page breaks should be taken.  Example:  "1" puts each
,top-level task on a new page.
  uOne Task/Resource per Page If Page Breaks set to "Yes", this field
,allows a new page for each task (if report grouped by task)
,or resource (if grouped by resource).
$TLPR2
uIgnore Left Margin?Page Break Control Form
sh
  Select "Yes" if you are going to be joining strips for a large chart.
!All strips after strip 1 will print with no left margin, making it
!easier to tape the strips together.
$TLPR3
uPage HeadingsDPage Break Control Form
sh
  uFirst Page prints heading (from Report Form) on first page only.
  uEvery Page prints heading on each page of report.
$TLPR4
uPage FootingsDPage Break Control Form
sh
  uFirst Page prints footing (title, page, strip) on first page only.
  uEvery Page prints footing on each page of report.
$TLPR5
uRow HeadingsEPage Break Control Form
sh
  uFirst Page prints the first column of report on first page only.
  uEvery Page prints first column on each page of report.
$TLPR6
uColumn HeadingsBPage Break Control Form
sh
  uFirst Page prints column headings on first page only.
  uEvery Page prints column headings on each page of report.
$TLPR7
uRow SpacingFPage Break Control Form
sh
  Type a "1" for single-spaced reports.
  Type "2" for double-spaced, "3" for triple-spaced.
$TLPR8
uColumn SpacingCPage Break Control Form
sh
Type a number from 1 to 72 that corresponds to the number of blank spaces
you want between columns.
$TLPR9
uPrint ZerosFPage Break Control Form
sh
In your cost reports, do you want Time Line to print the zeros when a
cost is zero, or leave the entry blank?
$TLPR10
uUnlimited Page Width=Page Break Control Form
sh
  uYes "prints" the report with an unlimited width for later printing
!with a sideways printing program.
$TLRA0
uDateQAvail. Profile Form
sh

  Enter the date that the new availability is to begin.
  All changes begin at midnight.
$TLRA1
uAvailabilityIAvail. Profile Form
sh
  This number and percentage determines when a resource is overscheduled.
  Tasks with overscheduled resources have an "R" in the Status column.
  If Resource Leveling is turned on (Options Form), tasks assigned to
!these overscheduled resources may be delayed.
  If resource is an individual, enter "1".  If a group, enter number.
$TLRA2
uPercentNAvail. Profile Form
sh
  The availability and percentage determines when a resource is
!overscheduled.
  Enter a number between 1 and 250%.
  If a person is available full-time, enter 100%.
$TLRC0
uDateSRate Profile Form
sh

  Enter the date that the new rate begins.
  All changes begin at midnight.
$TLRC1
uRateSRate Profile Form
sh
  This amount per period of time is used by resources and variable costs
!to determine the total task expense.  The cost is calculated as the
!Cost Rate multiplied by assigned percentage multiplied by task duration.
  The amount portion of this field is used by unit costs.  The cost is
!calculated as Cost Rate multiplied by the number of assigned units.
  Cost rates with more than two decimals (up to eight) can be entered.
$TLRC2
uPerTRate Profile Form
sh
  Unit of time for resources and variable cost rates.
$TLRC3
uUnitsRRate Profile Form
sh
  Unit of measure to be displayed for unit costs (for display only).
  Enter plural form of name if multiple units usually assigned (16 tons).
$TLSR0
uGroup ByNStatus Report Form
sh
  uTask#organizes the report by task.  Each new task produces a
*new section of the report.
  uResource organizes the report by resource.  Each new resource
*produces a new section of the report.
  Report includes only visible tasks in the Gantt view.  Hidden tasks
!("-" on summaries and those not shown by a select filter) are excluded.
$TLSR1
uShowRStatus Report Form
sh
  uResources'excludes costs from the report.
  uCosts & Resources includes costs.
$TLSR2
uDailyQStatus Report Form
sh
  Enter the starting date for a series of daily reports, and the number
!of days (reports) to print.
  Use words such as "today" and "asof", and math such as "plus 2 days"
!to build flexibility into the report (dates will not have to be
!specifically entered).  This is especially helpful with report macros.
  Each day is started at the top of a new page.
  Daily reports can be run WITH weekly and monthly reports, or not.
+Quit,Index,Entering Dates
=Quit,Index,.DTFRMTS
$TLSR3
>TLSR2
$TLSR4
uWeeklyPStatus Report Form
sh
  Enter the starting date for a series of weekly reports, and the number
!of weeks (reports) to print.
  Use words such as "today" and "asof", and math such as "plus 2 weeks"
!to build flexibility into the report (dates will not have to be
!specifically entered).  This is especially helpful with report macros.
  Each week is started at the top of a new page.
  Weekly reports can be run WITH daily and monthly reports, or not.
+Quit,Index,Entering Dates
=Quit,Index,.DTFRMTS
$TLSR5
>TLSR4
$TLSR6
uMonthlyOStatus Report Form
sh
  Enter the starting date for a series of monthly reports, and the number
!of months (reports) to print.
  Use words such as "today" and "asof", and math such as "plus 2 months"
!to build flexibility into the report (dates will not have to be
!specifically entered).  This is especially helpful with report macros.
  Each month is started at the top of a new page.
  Monthly reports can be run WITH daily and weekly reports, or not.
+Quit,Index,Entering Dates
=Quit,Index,.DTFRMTS
$TLSR7
>TLSR6
$TLSR8
uInclude Task Parentage@Status Report Form
sh
  uYes includes tasks' parentage in outline format.
  uNo  prints only task names on the report.
$TLSR9
uInclude Past Due Tasks@Status Report Form
sh
  uYes includes on the report tasks whose end date predates the report
%but have not been marked Done.
$TLSR10
uGroup by Start/Continue/End;Status Report Form
sh
  Within each time period printed on the report:
! If this field is "Yes", tasks are further broken out in these three
#status periods.
! If "No", tasks are arranged in same sequence as on Gantt view.
$TLSR11
uTask ColumnKStatus Report Form
sh
  Press [F2] to select from a list of data columns.
  Report columns are arranged in the sequence entered on this form.
  Be sure to include Task Name, Abbreviated Task Name, or WBS as a column
!to identify tasks.
$TLSR12
uWidthQStatus Report Form
sh
  The number of characters to display.
  Enter "B" after width number to produce a blank column of that width.
!(Useful for edit listings and turnaround reports.)
$TLSR13
>TLSR11
$TLSR14
>TLSR12
$TLSR15
>TLSR11
$TLSR16
>TLSR12
$TLSR17
>TLSR11
$TLSR18
>TLSR12
$TLSR19
>TLSR11
$TLSR20
>TLSR12
$TLSR21
>TLSR11
$TLSR22
>TLSR12
$TLSR23
uAssignment ColumnEStatus Report Form
sh
  Press [F2] to select from a list of data columns.
  Report columns are arranged in the sequence entered on this form.
  Assignment columns give information about the way resources and costs
!are assigned to tasks.
$TLSR24
>TLSR12
$TLSR25
>TLSR23
$TLSR26
>TLSR12
$TLSR27
>TLSR23
$TLSR28
>TLSR12
$TLSR29
>TLSR23
$TLSR30
>TLSR12
$TLSR31
>TLSR23
$TLSR32
>TLSR12
$TLSR33
>TLSR23
$TLSR34
>TLSR12
$TLSRR0
>TLPR0
$TLSRR1
>TLPR1
$TLSRR2
>TLPR2
$TLSRR3
>TLPR3
$TLSRR4
>TLPR4
$TLSRR5
>TLPR6
$TLSRR6
>TLPR10
$TLV20
uCopy NotesFImport Version 2 Options
sh
Time Line Version 2 used two lines of notes text in place of coding fields
such as Keyword, WBS, and OBS.  This facility allows you to transfer
notes text information into two of Version 4's coding fields.

  Specify a separate coding field for each of the notes text lines.
  If the notes text doesn't fit in a coding field, it will be truncated.
$TLV21
>TLV20
$TRAS11
uAssignment Number/Percentage4Resource Assignment Form
sh
  The number and percentage displayed come from the Resource/Cost Form.
!They can be changed for assignment to a specific task.
  Enter a number of resources up to the maximum allocation for this
!resource (as entered on the Resource/Cost Form).
  Enter the % of the resource you want to use for this task.
  Alternately, assignment may be entered in terms of time.  Use the
!Effort field for this.
$TRAS12
>TRAS11
$TRAS13
uEffortJResource Assignment Form
sh
  Assign the resource in terms of the time the resource is to spend.
!Time Line calculates the percentage equivalent.
  Assignment can be made EITHER by percentage or by time.  Small arrows
!next to the field(s) indicate which was used for a particular task.
+Quit,Index,Calculator,Driven By
=Quit,Index,CALC,TASK14
$TRAS14
>TRAS13
$TRAS18
uCostLResource Assignment Form
sh
  Enter the dollar value planned for this cost on this task.
  You can enter either effort or money.  When one is entered, the other
!is calculated.
  However, if the resource has varying rates, then the effort must be
!entered, and the cost will be computed after the task is scheduled at
!a particular date.
$TRAS19
uBillableHResource Assignment Form
sh
  uNo  does unot include the cost of this resource assignment
%in the calculations for cost reports.
  uYes includes the cost of this resource assignment in the
%calculations for cost reports.
$TRAS110
uSpent EffortDResource Assignment Form
sh
  For tracking purposes, enter the actual effort expended for this task.
  Effort can be entered as time (the usual method) or dollars.
  When you enter actual effort (or cost), Time Line calculates and
!displays To Go Effort and Cost at the bottom of the form.
  If the spent dollars include a rate variance from the usual rate, or
!any extra changes or credits, enter them into the Extra Dollars field.
$TRAS112
uSpent Extra $CResource Assignment Form
sh
  For tracking purposes, enter any money actually spent over and above
!what would be normal for the hours spent at the current cost rate. 
  Use this to enter variances from the usual cost rate of the resource,
!or extra charges or credits.
  Enter a negative number if the money spent is less than the hours would
!imply.
$TRAS113
uSpent CostFResource Assignment Form
sh
  For tracking purposes, enter the actual cost for this resource.
  Effort can be entered as time (the usual method) or dollars.
  When you enter actual effort (or cost), Time Line calculates and
!displays To Go Effort and Cost at the bottom of the form.
  If the spent dollars include a rate variance from the usual rate, or
!any extra chages or credits, enter them into the Extra Dollars field.
$TRAS21
>TRAS11
$TRAS22
>TRAS12
$TRAS23
>TRAS13
$TRAS24
>TRAS13
$TFCA11
uAssignment Dollars<Fixed Cost Assignment Form
sh
  Enter the amount planned for this cost on this task.
  This fixed cost will not vary as the task duration changes.
+Quit,Index,Calculator
=Quit,Index,CALC
$TFCA12
uBillableFFixed Cost Assignment Form
sh
  uNo  does unot include this cost assignment in the calculations
%for cost reports.
  uYes includes this fixed cost assignment in the calculations for
%cost reports.
$TFCA13
uSpent Dollars@Fixed Cost Assignment Form
sh
  When tracking actuals, enter the amount of the fixed cost spent
!to date.
  After you enter the spent expense, Time Line displays the To Go fixed
!cost (total minus spent) directly below the Actual.
  Numbers can added to and subtracted from a previously entered value.
+Quit,Index,Calculator
=Quit,Index,CALC
$TFCA21
>TFCA11
$TUCA12
uAssignment Units?Unit Cost Assignment Form
sh
  Enter the amount planned for this cost on this task.
  Unit costs can be entered in terms of units or dollars.  When one is
!entered, the other is calculated.
  However, if the unit cost has varying rates, then the units must be
!entered, and the cost will be computed after the task is scheduled at
!a particular date.
+Quit,Index,Calculator,Rates
=Quit,Index,CALC,RSRC7
$TUCA13
uAssignment Dollars=Unit Cost Assignment Form
sh
  Enter the dollar value planned for this cost on this task.
  Unit costs can be entered in terms of units or dollars.  When one is
!entered, the other is calculated.
  However, if the unit cost has varying rates, then the units must be
!entered, and the cost will be computed after the task is scheduled at
!a particular date.
+Quit,Index,Calculator
=Quit,Index,CALC
$TUCA14
uBillableGUnit Cost Assignment Form
sh
  uNo  does unot include this cost assignment in the calculations
%for cost reports.
  uYes includes this unit cost assignment in the calculations for
%cost reports.
$TUCA16
uSpent UnitsDUnit Cost Assignment Form
sh
  When tracking actuals, enter the number of units of the unit cost spent
!to date.
  After you enter the actual expense, Time Line displays the To Go cost
!(total minus spent) below the Spent amount.
  Numbers can added to and subtracted from a previously entered value.
+Quit,Index,Calculator
=Quit,Index,CALC
$TUCA17
uSpent DollarsBUnit Cost Assignment Form
sh
+Quit,Index,Calculator,Rates
=Quit,Index,CALC,RSRC7
  When tracking actuals, enter the dollar value (or number of units in
!the previous field) of the unit cost spent to date.
  After you enter the actual expense, Time Line displays the To Go cost
!(total minus actual) directly below the Actual.
  Numbers can added to and subtracted from a previously entered value.
  However, if the unit cost has varying rates, then the units must be
!entered, and the cost will be computed after the task is scheduled at
!a particular date.
$TUCA22
>TUCA12
$TUCA23
>TUCA13
$TVCS11
uAssignmentAVariable Cost Assignment Form
sh
  Enter the amount planned for this cost on this task.
  Variable costs can be entered in terms of a percentage or an amount of
!time.  When one is entered, the other is calculated.
  Commonly, variable costs are entered "1 @ 100%".  This multiplies the
!cost rate (Resource/Cost Form) by the task duration to arrive at a
!cost for the task.  As the duration changes, the cost changes as well.
  If the cost is entered as an amount of time, it will NOT change as the
!duration changes.
/4
  However, if the resource has varying rates, then the time must be
!entered, and the cost will be computed after the task is scheduled at
!a particular date.
+Quit,Index,Calculator,Rates
=Quit,Index,CALC,RSRC7
$TVCS12
>TVCS11
$TVCS13
>TVCS11
$TVCS14
>TVCS11
$TVCS18
uCostGVariable Cost Assignment Form
sh
  Enter the dollar value planned for this cost on this task.
  You can enter either time or money.  When one is entered, the other
!is calculated.
  However, if the resource has varying rates, then the time must be
!entered, and the cost will be computed after the task is scheduled at
!a particular date.
$TVCS19
uBillableCVariable Cost Assignment Form
sh
  uNo  does unot include this cost assignment in the calculations
%for cost reports.
  uYes includes this variable cost assignment in the calculations for
%cost reports.
$TVCS110
uSpent Effort?Variable Cost Assignment Form
sh
  When tracking actuals, enter the amount of time of the variable cost
!spent to date.
  After you enter the actual expense, Time Line displays the To Go effort
!(total minus spent) directly below the Actual.
  Numbers can added to and subtracted from a previously entered value.
  If the spent dollars include a rate variance from the usual rate, or
!any extra chages or credits, enter them into the Extra Dollars field.
+Quit,Index,Calculator
=Quit,Index,CALC
$TVCS112
uSpent Extra $CResource Assignment Form
sh
  For tracking purposes, enter any money actually spent over and 
!above what would be normal for the hours spent at the current cost 
!rate. 
  Use this to enter variances from the usual cost rate of the resource,
!or extra charges or credits.
  Enter a negative number if the money spent is less than the hours would
!imply.
$TVCS113
uSpent $IResource Assignment Form
sh
  When tracking actuals, enter the amount of dollar value of the variable
!cost spent to date.
  After you enter the actual expense, Time Line displays the To Go value
!(total minus spent) directly below the Actual.
  Numbers can added to and subtracted from a previously entered value.
  If the spent dollars include a rate variance from the usual rate, or
!any extra chages or credits, enter them into the Extra Dollars field.
+Quit,Index,Calculator
=Quit,Index,CALC
$TVCS114
>TVCS111
$TVCS115
>TVCS111
$TVCS21
>TVCS11
$TVCS22
>TVCS12
$TVCS23
>TVCS13
$TVCS24
>TVCS14
$TVSR0
>TVST0
$TVSR1
>TVST1
$TVSR2
>TVST2
$TVSR3
>TVST3
$TVSR4
>TVST4
$TVSR5
>TVST5
$TVSR6
>TVST6
$TVSR7
>TVST7
$TVSR8
>TVST8
$TVST0
uDuplicate on-screen Resource Histograms,Cross Tab / Histogram
sh
  If "Yes", protects the rest of the form's fields and sets them to print
!a report that approximates the current on-screen histogram.
  The date range fields remain open to restrict the time shown.
  If resources are select filtered, only those resource's histograms will
!be printed.
$TVST1
uDate RangeICross Tab / Histogram
sh
The Date Range settings allow you to limit the report to a specific 
period of time between the start and end dates you enter.

  The entire schedule prints if you do not enter a start or end date.
  This does not limit the task names considered for the report, it just
!restricts the date range on the data shown.
+Quit,Index,Entering Dates
=Quit,Index,.DTFRMTS
$TVST2
>TVST1
$TVST3
uPeriodMCross Tab / Histogram
sh
  Choose whether you want report columns to represent hourly, daily,
!weekly, monthly, or yearly periods.
  If "Yrs" selected, the months to be included in each "year" are
!determined by the First Month field on the Calendar Settings Form.
$TVST4
uReport DataHCross Tab / Histogram
sh
  Press [F2] from this field for a list of Report Data items.
  The selected data item shows in the cells of a Cross Tab Report, or
!is used to construct the barchart in the Histogram Report.
$TVST5
uWidthNCross Tab / Histogram
sh
  Controls the column width on Cross Tab Report.
$TVST6
uDigitsMCross Tab / Histogram
sh
  Controls the number of decimal places shown for numeric data columns.
  "9" is maximum.
$TVST7
uReport on (Resources, Costs & Resources)+Cross Tab / Histogram
sh
  uResources'excludes costs from the report.
  uCosts & Resources includes costs.
$TVST8
uShow as Hourly Rate@Cross Tab / Histogram
sh
If you choose "Yes" here, Time Line takes the total dollars spent on a
resource over a specific time period and converts it to the average spent
per hour (a more accurate measure of spending when comparing unequal time
periods).
/

February's fewer days would normally show a lower cost per month, but its
hourly rate would equal other, longer months.  In a Histogram Report, this
could falsely indicate a reduced work capacity or allocation.  The use of
an hourly rate for monthly comparison, however, would show the same level
of histogram for these hourly employees during months such as February.
/

  Set to Yes when "Work Hours/Max" selected as Report Data.
  Is automatically set to Yes when "Duplicate On-screen Histograms" is
!set to Yes.
$TVST9
uTotal by ColumnDCross Tab / Histogram
sh
  uYes in this field provides column totals for numeric report data
%selections.  If a task-oriented report, totals reflect top-level
%summaries only (identified with "*" to right of row).
  uNo  excludes column totals.
$TVST10
uTotal by RowGCross Tab / Histogram
sh
  uYes&in this field provides row totals for numeric report
,data selections.
  uNo'excludes row totals.
  uCumulative accumulates totals from column to column (each column
,becomes the total of current, plus all previous, data).
$WBSFM0
uPrefixRWBS Manager Form
sh
  Precedes all generated WBS codes for this schedule.
  Use to group all tasks from a particular schedule when combining
!multiple schedules.
  Question mark (?) can be used as wildcard during Verify process.
!Time Line ignores this character(s) when verifying valid WBS codes.
$WBSFM2
uCharacter SequenceFWBS Manager Form
sh
  Establishes lettering/numbering system to use for this segment.
!Examples:
! A..Z(If Start With field shows "A", uses "A" for first task
1at this level, then "B", and so on.
! 0..9(If Start With field shows "1", uses "1" for first task
1at this level, then "2", and so on.
! A..HJ..NP..Y  Similar to "A..Z", but skips I, O, and Z.
! 6..9(Uses "6" for first task at this level.
$WBSFM3
uStart WithNWBS Manager Form
sh
  First or second character of sequence established in previous field.
  For example, could be "0" or "1" for "0..9" sequence.
  Could be "6" or "7" for "6..9" sequence.
  Could be "A" or "B" for "A..HJ..NP..Y" sequence.
$WBSFM4
uSize Min.OWBS Manager Form
sh
  Minimum segment width.  If segment is less than this width, padding
!characters are added.
  Padding characters are "0" (numeric) and "A" (character).
$WBSFM5
uSize Max.OWBS Manager Form
sh
  Maximum segment width.  If segment is greater than this width, the
!segment width is expanded for the tasks that need it, and an error is
!displayed in the WBS Errors column (layout is added to Layout List).
$WBSFM6
uAlways Show?LWBS Manager Form
sh
  If "Y" for a particular segment, the segment is shown even for tasks
!above that level in the outline.
  In this case, the character entered in the Null field is used.
  When set to "N", lower segments' Always Show fields are unavailable.
!(They default to "N".)
$WBSFM7
uFillTWBS Manager Form
sh
  Character to be used as a place holder for an empty segment if Always
!Show is set to "Y".
$WBSFM8
uSeparate ByMWBS Manager Form
sh
  This character separates the current segment from the next.
  Example:  If segment 1 followed by "-", WBS might be "A-4".
+If segment 2 followed by ".", WBS might be "A-4.2".
  If entered for the last segment, this character is ignored.
$WBSFM9
>WBSFM2
$WBSFM10
>WBSFM3
$WBSFM11
>WBSFM4
$WBSFM12
>WBSFM5
$WBSFM13
>WBSFM6
$WBSFM14
>WBSFM7
$WBSFM15
>WBSFM8
$WBSFM16
>WBSFM2
$WBSFM17
>WBSFM3
$WBSFM18
>WBSFM4
$WBSFM19
>WBSFM5
$WBSFM20
>WBSFM6
$WBSFM21
>WBSFM7
$WBSFM22
>WBSFM8
$WBSFM23
>WBSFM2
$WBSFM24
>WBSFM3
$WBSFM25
>WBSFM4
$WBSFM26
>WBSFM5
$WBSFM27
>WBSFM6
$WBSFM28
>WBSFM7
$WBSFM29
>WBSFM8
$WBSFM30
>WBSFM2
$WBSFM31
>WBSFM3
$WBSFM32
>WBSFM4
$WBSFM33
>WBSFM5
$WBSFM34
>WBSFM6
$WBSFM35
>WBSFM7
$WBSFM36
>WBSFM8
$WBSFM37
>WBSFM2
$WBSFM38
>WBSFM3
$WBSFM39
>WBSFM4
$WBSFM40
>WBSFM5
$WBSFM41
>WBSFM6
$WBSFM42
>WBSFM7
$WBSFM43
>WBSFM8
$WBSFM44
>WBSFM2
$WBSFM45
>WBSFM3
$WBSFM46
>WBSFM4
$WBSFM47
>WBSFM5
$WBSFM48
>WBSFM6
$WBSFM49
>WBSFM7
$WBSFM50
>WBSFM8
$WBSFM51
>WBSFM2
$WBSFM52
>WBSFM3
$WBSFM53
>WBSFM4
$WBSFM54
>WBSFM5
$WBSFM55
>WBSFM6
$WBSFM56
>WBSFM7
$WBSFM57
>WBSFM8
$WBSFM58
>WBSFM2
$WBSFM59
>WBSFM3
$WBSFM60
>WBSFM4
$WBSFM61
>WBSFM5
$WBSFM62
>WBSFM6
$WBSFM63
>WBSFM7
$WBSFM64
>WBSFM8
$WBSFM65
>WBSFM2
$WBSFM66
>WBSFM3
$WBSFM67
>WBSFM4
$WBSFM68
>WBSFM5
$WBSFM69
>WBSFM6
$WBSFM70
>WBSFM7
$WBSFM71
>WBSFM8
$WBSFM72
>WBSFM2
$WBSFM73
>WBSFM3
$WBSFM74
>WBSFM4
$WBSFM75
>WBSFM5
$WBSFM76
>WBSFM6
$WBSFM77
>WBSFM7
$WBSFM78
>WBSFM8
$WBSFM79
>WBSFM2
$WBSFM80
>WBSFM3
$WBSFM81
>WBSFM4
$WBSFM82
>WBSFM5
$WBSFM83
>WBSFM6
$WBSFM84
>WBSFM7
$WBSFM85
>WBSFM8
$WBSFM86
>WBSFM2
$WBSFM87
>WBSFM3
$WBSFM88
>WBSFM4
$WBSFM89
>WBSFM5
$WBSFM90
>WBSFM6
$WBSFM91
>WBSFM7
$WBSFM92
>WBSFM8
$WBSFM93
>WBSFM2
$WBSFM94
>WBSFM3
$WBSFM95
>WBSFM4
$WBSFM96
>WBSFM5
$WBSFM97
>WBSFM6
$WBSFM98
>WBSFM7
$WBSFM99
>WBSFM8
$XCTAB0
uTask vs. TimeEExport Cross Tabs Form
sh
A matrix is exported showing task data for periods of time.

  Cross Tab Report Form is presented to allow selection of data.
  For spreadsheet export, output is similar to Cross Tab Report.
  For database & CSV, output is one record per task per time period.
  Only open summary tasks are exported.
  Only select filtered tasks are exported.
$XCTAB1
uTask vs. Time Filename<Export Cross Tabs Form
sh
>XPOCOMM
$XCTAB3
uResource vs. TimeAExport Cross Tabs Form
sh
A matrix is exported showing resource data for periods of time.

  Cross Tab Report Form is presented to allow selection of data.
  For spreadsheet export, output is similar to Cross Tab Report.
  For database & CSV, output is one record per resource per time period.
$XCTAB4
uResource vs. Time Filename8Export Cross Tabs Form
sh
>XPOCOMM
$XCTAB6
uTask vs. ResourceAExport Cross Tabs Form
sh
A matrix is exported showing resource data for each task.

  Cross Tab Report Form is presented to allow selection of data.
  For spreadsheet export, output is similar to Cross Tab Report.
  For database & CSV, output is one record per task per resource.
  Only open summary tasks are exported.
  Only select filtered tasks are exported.
$XCTAB7
uTask vs. Resource Filename8Export Cross Tabs Form
sh
>XPOCOMM
$XCTAB9
uExport FormatEExport Cross Tabs Form
sh
Format of exported file.

  Press [F2] from this field for list of available formats.
  Selection affects default extension attached to files.
  For CSV format, default extension may be changed in File Extension
!field.
$XCTAB10
uFile ExtensionDExport Cross Tabs Form
sh
Default extension to be attached to export filename(s).

  Can only be changed if either "CSV (Text)" format chosen.
  Entry here affects all exported filenames.
$XCTAB11
uExport DirectoryBExport Cross Tabs Form
sh
Drive/directory for exported file.

  Press [F2] from this field for Directory List.
  We suggest entering the data directory for the selected export format.
  Example:!C:\LOTUS\DATA
$XPORT0
uTaskRExport Tables Form
sh
  uNo      does not export task data.
  uAll     exports most of the columns available on Gantt layout.
.This can create a very large exported file.
  uBaseline   exports only those columns necessary to reconstruct
.a baseline schedule.  File/Import can then be used to
.import this into a schedule without a baseline.  This is
.used to create variance reports on multiple baselines.
  uGantt Layout exports columns included in current Gantt layout.
/4
  Only open summary tasks and select filtered tasks are exported.
  wCAUTION: If data is to be reimported, include WBS column in "Gantt
*Layout" or use "All".
$XPORT1
uTask FilenameIExport Tables Form
sh
>XPOCOMM
$XPOCOMM
Name of file to contain exported information.

  Default name can be overwritten.
  An overwritten name becomes the new default name.
  If file with entered name already exists, you'll be asked if OK to
!overwrite.
$XPORT2
uResourceNExport Tables Form
sh
  uNo    does not export resource data.
  uAll   brings up form for selecting resource columns to export.
  uBaseline exports only those columns necessary to reconstruct a
*baseline resource list.  File/Import can then be used to
*import this to create variance reports on multiple baselines.
  Only select filtered resources are exported.
$XPORT3
uResource FilenameEExport Tables Form
sh
>XPOCOMM
$XPORT4
uAssignmentLExport Tables Form
sh
  uNo    does not export assignment data.
  uAll   exports a selection of assignment columns.  Each exported
*record shows a single resource assignment.
  uBaseline exports only those columns necessary to reconstruct 
*baseline assignments.  File/Import can then be used to import
*this to create variance reports on multiple baselines.
  Only select filtered resource assignments are exported.
$XPORT5
uAssignment FilenameCExport Tables Form
sh
>XPOCOMM
$XPORT6
uDependencyLExport Tables Form
sh
  uNo  does not export dependencies.
  uYes exports a selection of dependency columns.  Each exported
%record shows a dependency between two tasks.
  Only dependencies between two visible tasks (select filtered or in open
!outline family) are exported.
$XPORT7
uDependency FilenameCExport Tables Form
sh
>XPOCOMM
$XPORT8
uAvail. ProfileHExport Tables Form
sh
  uNo  does not export availabilities.
  uYes exports a series of records for each resource showing the
%changing levels of availability and period of each level.
$XPORT9
uAvailability FilenameAExport Tables Form
sh
>XPOCOMM
$XPORT10
uRate ProfileJExport Tables Form
sh
  uNo  does not export rates.
  uYes exports a series of records for each cost type and resource
%showing the changing cost rates and period of each rate.
$XPORT11
uRates FilenameHExport Tables Form
sh
>XPOCOMM
$XPORT12
uResource CalendarsDExport Tables Form
sh
  uNo  does not export calendars.
  uYes exports a series of records for each resource showing the
%periods of vacation time marked for the resource.
$XPORT13
uCalendars FilenameDExport Tables Form
sh
>XPOCOMM
$XPORT14
uVariable AssignmentCExport Tables Form
sh
  uNo  does not export variable assignments.
  uYes exports a series of records for each task showing the resources
%assigned and, given vacations and percentage of assignment, the
%dates and percentages within which each resource works.
$XPORT15
uVariable Assignment Filename:Export Tables Form
sh
>XPOCOMM
$XPORT17
uVerify unique WBS codes for reimport?1Export Tables Form
sh
  If "Yes", Time Line checks to see that each task contains a unique
!WBS code.
  Since Time Line uses the WBS code as a task identifier, it is very
!important that WBS codes are in place before exporting.  Use Assist /
!WBS Manager to facilitate this process.
$XPORT18
uExport FormatIExport Tables Form
sh
Format of exported file.

  Press [F2] from this field for list of available formats.
  Selection affects default extension attached to files.
  For CSV format, default extension may be changed in File Extension
!field.
$XPORT19
uFile ExtensionHExport Tables Form
sh
Default extension to be attached to export filename(s).

  Can only be changed if either "CSV (Text)" format chosen.
  Entry here affects all exported filenames.
$XPORT20
uExport DirectoryFExport Tables Form
sh
Drive/directory for exported file.

  Press [F2] from this field for Directory List.
  We suggest entering the data directory for the selected export format.
  Example:!C:\LOTUS\DATA
$COMBTask
uCOMBINE:  Tasks/Resources/Costs
sh

This option combines all components of a schedule on disk into the current
schedule in memory.  It combines not only the tasks, but the Resource/Cost
List, Layout and Filter Lists, and Journal notes.  The calendar set up
for the current schedule is used; the calendar from the schedule on disk
is NOT combined.

  Use this option when combining two schedules for consolidation.
  If names on the two schedules' lists (Resource/Cost, Layout, Filter)
!are duplicated, Time Line gives you the choice of using the current
!schedules' lists, or those from the combined schedule.
  Master Calendar differences are reconciled by maintaining the tasks'
!start and end dates (changing duration, if need be) or maintaining
!duration (changing end dates, if need be).
  Combined schedule may be summarized with an added summary task, or not.
  Combined schedule is inserted just below the cursor task, at the same
!level.  Be sure to position your cursor before executing File/Combine.
$COMBRsrc
uCOMBINE:  Resources/Costs
sh

This option combines the Resource/Cost List from a schedule on disk with
the current schedules' Resource/Cost List.

  If names are duplicated in the two lists, Time Line asks which list
!should overwrite the other.
  Use this option to copy the resources and costs already defined in one
!schedule to a new schedule.  It saves retyping the list.
  If you have several schedules that share the same resources and costs,
!you may want to designate one of them as the "master resource/cost
!list", updating that schedule only and copying the updated list to the
!others with this File/Combine/Resources command.
$COMBCldr
uCOMBINE:  Master Calendar
sh

This option combines a master calendar from another file ONLY if the
current schedule is empty (has no tasks or resources yet).  It may NOT be
used to merge calendar information from one schedule to another that
already has tasks.

  Each time you save a file, Time Line copies its calendar information to
!the global configuration file.  If you then start a new schedule (by
!exiting and reentering Time Line or by executing Schedule/Erase), the
!previous schedules' calendar is used.  In this case, it is not
!necessary to combine calendars from the other file.
$2600
uGantt View Layout List
sh

This list shows all currently defined layout names.  You can select a
layout, change the definition of a layout name, add new names, or delete
existing names.  Names denoted with an asterisk (*) are "standard"; they
are linked into all schedules' Layout Lists and produce the same results.

  Select a layout               Move to name, press [Enter]
  Change a layout               Move to name, press [F2]
  Insert a new layout (this schedule only)   [Ins]
  Make a new standard layout (noted with *)  [Sh/Ins] on std layout name
  Delete a layout name             [Del]
  Move up and down the list          [/], [PgUp/Dn], [Hm/End]
  Jump to an item with QuickPick        Type 1st letter(s) of name
  Reverse the QuickPick process        [Backspace]
  Select an item                [Enter] or [F10]
  Cancel selection process           [Esc]
//
uGantt View Layout List (continued)
sh

  All starred layout names (standard layouts) are saved globally, in the
!TLCNFG5.DAT file (\TL5 directory).  They appear with all schedules, and
!produce the same result in all schedules.
! Make a new standard layout by pressing [Sh/Ins] on any standard
#layout name.
! When you copy schedules from one computer to another, standard
#layouts do not travel with them unless you copy TL5CNFG.DAT also.
! If you delete a standard layout on this list, it is deleted for all
#schedules.
  All non-starred layout names (schedule layouts) are saved locally, with
!the schedule file.  The name appears only with the current schedule.
! Make a new schedule layout by pressing [Ins] anywhere in the list.
! If you delete a schedule layout, it does not affect any other
#schedules.
$3000
uResource/Cost List
sh

Each schedule has its own Resource/Cost List.  You can retrieve a list
from another schedule with the File/Combine command, or build a new one
from scratch.  There is no limit to the number of resources and costs
on the list.

  Add a resource or cost            [Ins], complete the form
  Change a resource/cost            [F2], change the form
  Delete a resource/cost            [Del]
>.PICKLIS
+Quit,Index,Resource/Cost Form
=Quit,Index,RESOForm
$15600
uMacros List
sh

The Macros List displays all currently recorded macros.

  Move up and down the list          [/], [PgUp/Dn], [Hm/End]
  Play back a macro              [Enter] or [F10]
  Edit a macro's keystrokes          [F2]
  Delete a macro                [Del]
  Create a new macro              [Ins]
  View a macro's description & hot key     Move to name, look below
  Indent/outdent a macro name         [Sh/Rt] & [Sh/Lt]
!Note: Must use keypad, or "6" and "4".
  Jump to a particular macro          [F5], then type letter(s)
  Cancel selection process           [Esc]
$16300
uJournal List
sh

Notes listed on the Journal List are available from anywhere in Time Line.
The list can be displayed with [Alt/F2].  Journal notes are automatically
saved with the schedule, or can be individually saved as ASCII files.  The
list is an outline, so "titles" (first line of note) can be moved and
arranged in indented groups.

  Add a new note                [Ins]
  Change an existing one            [F2]
  Delete a note                 [Del]
  Move around the list             [/], [PgDn/Up], [Hm/End]
  Jump to a particular note           [F5], then type letter(s)
  Indent/outdent notes             [Sh/Rt], [Sh/Lft]
!Note: Must use keypad, or "6" and "4".
  Open/close summary notes           [+], [-]
$17100
uFilter List
sh

This list shows all currently defined filter names.  You can select a
filter, change the definition of a filter name, add new names, or delete
existing names.  Names denoted with an asterisk (*) are "standard"; they
are linked into all schedules' Layout Lists and produce the same results.

  Select a filter               Move to name, press [Enter]
  Change a filter               Move to name, press [F2]
  Insert a new filter (this schedule only)   [Ins]
  Make a new standard filter (noted with "*") [Sh/Ins] on std filter name
  Delete a filter name             [Del]
>.PICKLIS
$19800
>DEPELis
$19900
uTime Line List
sh

Time Line uses lists in many areas of the product to present options.  You
can move around this list and select an item in the following ways:

><.PICKLIS

  On Directory and Files Lists, select a new directory with [+] and [-]
!on directory names, or press [F2] to enter a new directory name.
$20800
uPERT and Work Tree Layout
sh

Layouts in the PERT and Work Tree views control the size of the task boxes
and the selection of information appearing in them.  Names denoted with an
asterisk (*) are "standard"; they are linked into all schedules' Layout
Lists and produce the same results in each schedule.

  Select a layout               Move to name, press [Enter]
  Change a layout               Move to name, press [F2]
  Insert a new layout (this schedule only)   [Ins]
  Make a new standard layout (noted with "*") [Sh/Ins] on std layout name
  Delete a layout name             [Del]
><.PICKLIS
  Switch between two layouts          [F8] while on view
$.27900

Check the supporting schedule independently to verify its accuracy.
$TCOL15
WBS Code
sh

 Indicates the Work Breakdown Structure of the task--its place
  in the hierarchy of tasks.
 Codes should be unique.
 Used for reporting and export; mandatory for import.
 Set using /Assist/WBS
$TCOL16
OBS Code
sh

 Organizational Breakdown Structure
 Enter a code here; use for filtering and reporting on selected tasks.
$TCOL17
>TASK13
$TCOL18
Status 
sh

?  =  Needs to be recalculated
C  =  Critical Path
R  =  An assigned resource is overscheduled (Alt-F8 for histograms).
r  =  Delayed during resource levelling
p  =  Predecessor of partial dependency
s  =  Successor of partial dependency
L  =  Involved in a dependency loop
$TCOL19
>TASK110
$TCOL20
>TASK14
$TCOL21
>TASK113
$TCOL22
>TASK122
$TCOL36
Bsln Total $ (BAC)
sh
 The task cost, established when the baseline was set.
 Aka "Budget at Completion," or "BAC".
 This is the amount that the task was planned to cost, if the project
  goes according to plan.
 Used as the weighting when computing Percent Achieved for summary tasks
  for Earned Value Analysis.
+Quit,Index,Achievement Rollup
=Quit,Index,CALF7
$TCOL37
Bsln Total $ (BAC)
sh
 The task effort, established when the baseline was set.
 This is the amount of effort (work-hours) that the task was planned
  to cost, if the project goes according to plan.
 Can be used as the weighting when computing Percent Achieved for
  summary tasks.
+Quit,Index,Achievement Rollup
=Quit,Index,CALF7
$TCOL44
Mathematical EAC
sh
 An uEstimate of the total cost of the task, uAt its uCompletion.
 Computed as SpentDollars + BaseLineTotalDollars - BCWP.
  =)Money Spent  + Money that still needs to be spent.
 Assumes that despite any history, the remainder of the work on the task
  will be performed exactly on budget.
$TCOL54
Achieved Dollars (BCWP)
sh
 The value of the work that has been accomplished so far.
 For detail tasks, = PercentAchieved * BaselineTotalDollars
 For summary tasks, this is computed based on your choice of
  weighting factors.
+Quit,Index,Achievement Rollup
=Quit,Index,CALF7
$TCOL61
Cost Variance Percent
sh

 Cost Variance divided by the Actual Achievement
 Calculated as (BCWP - ACWP) / BCWP
 Positive numbers indicate "cost less than planned"
 Negative numbers indicate "cost more than planned"
$TCOL62
Schedule Variance Percent
sh

 Schedule Variance divided by the Scheduled Achievement
 Calculated as (BCWP - BCWS) / BCWS
  (Your manual may have a typographical error; this is the correct
  formula.)
 Positive numbers indicate "ahead of schedule"
 Negative numbers indicate "behind schedule"
$TCOL103
>TASK19
$TCOL112
uForce CriticalNGantt Column
sh
  uNo  computes any slack appropriate for this task, considering the
%start dates of dependent tasks and resources assigned to other
%tasks.
  uYes Remove any slack from this task.  This may also reduce any
%utotal slack of antecedant tasks.

  Not on the Task Form.  Only available as a Gantt chart column, if
!included in a layout.
  When a Fixed task is created, Force Critical, for that task, will be
!set to either Yes or No, depending on the setting of the default on the
!Options Form.
+Quit,Index,Options Form,Critical Path,Slack
=Quit,Index,OPTN10,CRITPATH,SLACK
$TCOL113
uStart Date RestrictionFGantt Column
sh
  Controls the interpretation of the Entered Start Date field:
! uNo Sooner  schedules task at entered start date, or later if
.predecessors push back start date.
! uNo Later!schedules task at entered start date, or earlier if
.predecessors allow.
! uMust Start schedules task at entered start date.
  This selection is only available as a Gantt chart column.
  When a Fixed date task is created, it is set to either No Sooner or
!Must Start, depending on the setting of the default on the Options Form.
  Because No Later and Must Start override other important schedule
!constraints, they can lead to seriously inaccurate schedules.  Do not
!use these unless you understand and desire their effects.
+Quit,Index,Options Form
=Quit,Index,OPTN9
$CALLTEK
>.CALLTEK
$00000
  C*1*

  The Time Line program has detected an internal condition that prevents
  proper operation of the program.

  Results of calculations may not be correct.

  We advise you to save your work, and to call our technical support
  department.
><.CALLTEK
$0416
The duration entered is too long for Time Line to use.  Either use a
shorter duration, or reduce the calendar precision.

Time Line has a maximum calendar range from 1983 to 2017, but this full 
range is often restriced by your calendar precision.  The Calendar'
Settings Form controls the scheduling precison and, because the program 
can schedule a maximum of 65,535 distinct moments of time, the more
precise the scheduling and the fewer Non Work days, the less the total
calendar range.

See the Calendars chapter of the User Manual for a full discussion. 
$0701
uDependency Problem
sh

You are attempting to set a dependency for two tasks that are already
dependent.

  Press [F4] on the current task.  If its dependencies are OK, press
![F10] to leave the list, and continue with your work.

  To change a standard dependency to a partial dependency, press
![Sh/F3] instead of [F3].
  To delete a dependency, press [Ctl/F3] instead of [F3].
$1005
The calendar does not continue any farther to the right.  To get
a calendar with more dates to the right, please see the Calendars chapter
of the User Manual.
$1831
><.PROBLEM
I/O could not be done.

Perhaps:
  The file has been read completely, but the end of the file was
!reached sooner than the program expected.
  The file doesn't exist, or is not in the directory, or you are on
!a network and the file is protected against your use, or it is hidden.
  Something else, such as an open disk drive door is preventing the
!program from finding or reading the file.
$1832
><.PROBLEM
Not a supported operation.
>.CALLTEK
$1833
><.PROBLEM
Perhaps:
  Your disk or ram disk may be full.
  A previous file error may be making this file temporarily
!inaccessible.
  The file cannot be found.
$1834
><.PROBLEM
The drive that you addressed does not exist or is not known to the
program.

For example, if you refer to a drive "E:" when there is no "E:" accessible
to your computer, this warning message appears.
$1835
><.PROBLEM
The file mentioned does not exist, or is not accessible.
$1836
><.PROBLEM
Perhaps:
  The drive name or the directory path is not phrased correctly.
  When saving a file, the program attempted to move the temporary copy to
!a permanent copy in the data directory, and there was a problem with
!this, such as the directory is write protected, or your network system
!defaults to making temporary files protected.
  Time Line (for some reason) tried to read past the end of a file.
$1837
><.PROBLEM
Too many files open.

One of the following two situations have occurred:
  There are more files open than DOS can handle.
><.FILESEQ

  There is insufficient free memory to open a file.
!Each open file in Time Line requires a small amount of memory.  If you
!are using the PERT or Work Tree view, try switching to the Gantt view.
$1838
><.PROBLEM
Disk is full.

There is not enough room on the disk to:
  Finish writing a file.!
  Make a file larger.!
  Create a new file.

If you get this error on your virtual memory swap file, you will not be
able to continue adding more information to Time Line.  You will need to
restart Time Line, change the swap volume to a disk drive with more
room (using the SWAPVOL= command-line parameter) or else delete some files
from the disk.
$1839
><.PROBLEM
Device error.

$1840
><.PROBLEM
Access Error.

This can have several causes, but usually occurs on a network when:

  More than one computer is attempting to write to the same file.  For
!example, if you and another user are both in the same network
!directory, you will have a conflict with your virtual memory swap
!file.  In this case, either restart Time Line from another directory,
!or use the "SWAPVOL=" command-line parameter to relocate the swap file.

!Alternatively, you and another user may be both trying to save the
!same file to disk simultaneously.

  You may not be allowed to change the attribute of a file.  For example,
!Time Line cannot save a schedule file replacing an earlier one of the
!same name if that earlier file is Read-Only.

For further assistance:
>.NETADMI
$2614
Only columns that compute ratios between zero and one, and the special
column "Space", are allowed as Percent Achieved columns for filling-in
the Gantt bars.

Of these, the most useful columns are Percent Achieved, Proportional
Pct Achieved, and BsLn Proportional Pct Achieved.

To turn off showing progress by filling-in Gantt bars, choose "Space."
+Quit,Index,Showing Progress
=Quit,Index,DSPL7
$2725
><.PROBLEM
No Coprocessor.

Time Line was expecting a math coprocessor (such as an 80387) to be
installed in your computer, but it is not available.
>.CALLTEK
$2732
><.PROBLEM
FILE NOT FOUND

Time Line could not locate the needed overlay file.

Perhaps:
  It is not on the disk.
  Your PATH= command line parameter did not include the directory where
!the overlay files are.  DOS 2.x users need this parameter.
  Too few files are specified in the "FILES=" statement of the CONFIG.SYS
!file.
/
  Here is some information about the "FILES=" statement in CONFIG.SYS:
><.FILESEQ
/
><.NETADMI
!or
>.CALLTEK
$2734
><.PROBLEM
Out of memory.

There is not enough memory currently available to run the overlay.

  Please see Appendix C of the Time Line Manual.
  If you are using the PERT view, Histogram view, or any view other
!than the Gantt view, you may be able to obtain more room by switching
!to the Gantt view.
$2752
Time Line has attempted to use a special feature that, if it were
installed, would be in an "overlay" file.

However, if there were problems during installation of Time Line onto your
computer, and not all parts of the program were copied to your hard disk,
this error could happen during normal use of the program.  If
you suspect that such an error might have happened, use the INSTALL
program from your original Time Line diskettes to reinstall Time Line.
><.CALLTEK
$3101
The program has generated an internal menu code that it is not prepared
to process.  This usually indicates something wrong in the phrases file,
menus section.  Generally, the program will continue, ignoring the code. 
><.CALLTEK
$3122
>DEPENS
$3123
>DEPENS
$3124
uDependency Problem
sh

A task can be joined to any other task EXCEPT its own parent.

  Select another task for the dependency.
!or
  Outdent this task so that it is no longer a child of its parent,
!then make the dependency again.
/
>DEPEJoi
$3126
>DEPEJoi
$3300
While you are reviewing or editing a Time Line schedule, a working copy 
is held in the computer's "memory".  The original copy of it remains on
the disk, and the disk copy is not changed until you give the File/Save
command.

Schedule/Erase will remove the working copy from memory, but its previous
versions (if any) remain on the disk. 
$3305
Because the working copy of the schedule (in the computer memory) has been
changed and not saved onto your disk, you are asked to confirm your choice
before erasing it or leaving the Time Line program.

If you proceed, your working copy will be erased, and changes to it will 
be lost.

This command does not alter any copies of schedules on the disk. 
$3501
You have entered a start date and a task duration so long that it exceeds
the range of the Time Line calendar.

For further details, please see the Calendar chapter in the User Manual.
$3502
You are not allowed to enter an end date that is earlier that the start
date.

If you would like to enter an end date and a duration, and have Time Line
compute a matching start date, enter the duration, go to the start date
field first and make it blank, then enter the end date. 
$3516
>DEPENS
$3526
If you choose "Proceed", each predecessor of the deleted task will be
joined to each successor of the deleted task, thus bridging the
"dependency gap" left by the deleted task.

This helps keep the dependency network intact while deleting tasks.
$3530
The task that you are about to delete contains a link to another schedule
file.  Removing this task will remove that link, so the the current 
schedule will no longer have this reference to the other schedule.  This
can affect both dependencies and resources that are brought in by the link.

Other tasks in this schedule that are successors to this task will no
longer be successors to the linked schedule or task.
$3531
Accurate summarization of achievement percentage relies on the baseline
record of tasks' work-hours and estimated costs.  This technique supports 
Earned Value measurement.

However, Time Line also offers several other less-detailed methods of
rollup that you can choose from with the Weighting field (Calculations
Form).
+Quit help,Index,Weighting
=Quit,Index,CALF7
$3533
Only duration-driven tasks can be entered without resources assigned.

Effort-driven tasks require you to enter both a total task effort, and
specific resources who will work on the task. 
$3540
uExpenses Entered on Future Task
sh

You have a discrepancy here.  Some resources have accrued expenses, but
the task is still marked Future.

  You may have a good reason for this.  If so, select Allow the
!expenses.
  If the task has started, select Change status to started.
  If the expenses have been mistakenly entered, select Delete expenses.
  For other changes, select Edit task.
$3543
uWork Remains for Done Task
sh

You have a discrepancy here.  The task has been marked Done but work
remains.

  Select "Mark work/expense as complete" to automatically finish the
!work.
  Select "Edit task" to change task data, such as the duration.
  Select "Change status to started" to correct the status.
$3564
uProblem:  Incorrect Directory
sh

As part of a file management operation, you are trying to access a
directory that doesn't exist.

  Please change the current directory (File/Form).
  If you're not sure of the directory name, press [F2] on the Directory
!field for a list of directories and files.  Select a directory from
!the list.

/
>19431
$3570
uExpenses for Future Task
sh

Normally a Future task should not accrue expenses.  If there are special
circumstances that warrant your adding expenses to this future task,
select Cancel.

If you forgot the task status was future and do not really want this
expense item yet, choose "Proceed".
$3583
uInconsistent Start/End Dates
sh

Normally a Started or Done task should begin before the As-of Date, and a
Done Task should end before the As-of Date.  Doing so gives Time Line a
consistent set of data to work with, from which it can derive consistent 
results.

Choose "Cancel" to change the Start (or End) Date.  If you choose "Proceed",
Time Line will accept the Start (or End) Date as entered.

The As-of Date is set on the Options Form. You may change it if necessary.  
$3607
uRecommendation for using Assisted Update:
sh

1.  On the Options Form, 
" Check that the As-of Date is correct; change if necessary.
2.  On the Calculations Form, 
" Set the Recalculation field to Manual.
" Set Force Future Tasks After As-of Date to No.
3.  Use the Assist/Update menu option.  Update any task whose status
"requires changing.
4.  Recalculate the schedule by pressing the [F9] key.
5.  Review the results by using the Assist/Update menu option again.

You may want to repeat steps 4 and 5 until the schedule is correct.

When complete, return Force Future Tasks After As-of Date (Calculations
Form) to its previous setting.
$3610
uAssisted Update Options
sh

  uYes  updates the task's status to mark it Done, Started, or Future,
&so that its status reflects its current position relative to the
&As-of Date - then displays the Task Form for further editing.
  uEdit displays the Task Form, but does not change the status.
  uNo!leaves the task unchanged and continues checking.
  uStop leaves the task unchanged and ends the Assisted Update process.
$3620
uAssisted Update Options (with Cost Tracking or Large Task Form)
sh

If the Task Form field on the Options Form is set to "Large", or Cost
Tracking is set to "Yes", Assisted Update stops on ALL started tasks so 
that you can update their progress.

  uEdit displays the Task Form for updating.
& The Large Task Form option allows editing of the Percent 
(Achieved field.
& The Cost Tracking option allows updating of the actual costs.
  uNo!leaves the task unchanged and continues checking.
  uStop leaves the task unchanged and ends the Assisted Update process.
$3813
This is an internal program error.!While arranging edges to represent
the dependency of a summary task on its child tasks, the program was
unable to create an edge, Cprobably due to low memory conditions.
Recalculation will not be accurate.
><.CALLTEK 
$3814
This is an internal program error.!While arranging nodes to represent
the end of a summary task, the program was unable to create a node,
Cprobably due to low memory conditions.
Recalculation will not be accurate.
><.CALLTEK 
$4601
>3564
$4602
>3564
$4607
uFile in Use
sh

You are trying to retrieve a file that is write-protected.  This usually
occurs on a network when someone else has retrieved a file before you.
This safeguard, which prevents one person overwriting the changes made by
another, can be responded to as follows:

  Retrieve the file if you want only to view schedule information or
!print reports.  You will not be able to save any changes you might
!make, though.
  Retrieve the file, make changes, and save it under another name.
  Cancel the retrieve command.  Wait until the other person has finished
!using the file.
$4609
>4607
$4801
uFilename Already Exists
sh

When you change a name on the File Form, Time Line checks to see that the
name is not already being used.  In this case, Time Line has found another
file in the default directory with the name you've entered on the File
Form.  If you now save (and replace) this file, the other file will be
lost.
$4803
uFilename in Use
sh

Time Line does not overwrite a schedule if it is being used by another
person on the network, or if the directory is write-protected.  To save
this schedule, you must give it another filename.
$4911
Each resource can only be assigned to the same task once.  

If you want to assign the same resource twice, say to assign a person
for tracking overtime and regular hours separately, you will need to
create a second resource with a similar name, and use that to represent
the overtime assignment.

You may also want to use a summary task to enclose several child tasks
with separate assignments.
$5206
This task is done, but to-go effort remains on some assignments.

When you are tracking costs (Cost Tracking set to "Yes" on Options Form)
Time Line checks each assignment to see that all the estimated effort is
actually spent.  After all, a Done task with more work to go doesn't 
make sense.

If any assignment still shows work remaining, then you have three choices:

u Decrease Total effort to = Spent
$Removes any to go effort from the assignment.  Choose this if you
$have been entering the amount of effort spent on each assignment,
$and these amounts accurately reflect the spent total.
u Increase Spent to = Total
$Increases the spent effort on assignments to their full, estimated
$amounts.  This "spends" all the unspent effort.  (This is the 
$automatic behavior when Cost Tracking is off.)
u Return to Task Form
$Allows you to review and edit each assignment form to enter the
$exact amount of effort spent, and enter the total on the task form.
$5209
uNo Actuals Entered
sh

You have marked a task done.  It had effort planned (resources assigned)
but no actual effort was recorded on the Assignment Form.

Time Line only offers to adjust the planned amount to match the entered 
(actual) amounts when the Cost Tracking (No, Yes) field on the Options
Form has been set to Yes.

If you are not entering actual expenses of man hours or money, cancel this
process with [Esc].  Then, on the Options Form, set the Cost Tracking
field to No.
$5221
On this Done, Effort-Driven task, the amount of Spent effort entered
for the resource assignments exceeds the total effort planned for the
task.

For example, the assigments may show a total of 12 days spent, when the
task is estimated to take only 10 work-days of effort.

You have two choices:

u Increase Total Effort to = Spent
$Increases the estimated effort for the task to reflect that it
$really did take more than is currently entered.  (In the above
$example, this would change the task to a 12-workday task.)
u Return to Task Form
$Allows you to review and edit each assignment form to enter the
$exact amount of effort spent, and enter the total on the task form.
$5422
Time Line was unable to complete its analysis of your WBS numbers due
to insufficient memory.
><.CALLTEK 
$5426
The special character "?" is not allowed as part of a WBS number
definition.
$5430
WBS numbers are important to task and schedule linking, and also to
import and export of task data.  They are the single, reliable identifier
for a task.

If you plan to import existing data files, if your schedule is used by
other people or systems for import, export or linking, or if your schedule
supports other linked schedules, then erasing or changing your WBS 
numbers may cause references to your schedule to identify the wrong tasks.

If you use import/export or linkage, check other schedules before 
changing WBS numbers.

Perhaps, rather than erasing or changing all the WBS numbers, you can 
selectively change some of them? 

For more details, see the Export/Import and Multiple Projects chapters in
the User Manual.
$5440
>5430
$5474
>5426 
$5480   
Choose a range of tasks for which you want to transfer WBS numbers.  You may 
either transfer from the WBS column into an auxilary column, or from an 
auxilary column into the WBS column.

+Quit,Index
=Quit,Index
$6001
>6006
$6003
>6006
$6006
*1*

Time Line can only import Excel files created by version 2.1 of Excel.

Note to users of Excel version 3.0:

There are problems in the Excel 3.0 program which prevent it from creating
proper files in version 2.1 format.  Our solution to the problem:

#Save the Excel 3.0 worksheets in Lotus 1-2-3 version 2 format.
#Import these spreadsheets into Time Line with the Lotus 1-2-3
#import option.
$6400
*1*

Before you can print graphics, you need to choose a graphics device,
such as a printer, plotter or slide camera, with the Configure/Graphics
command.

If the graphics device you need is not listed, but is supported by 
Time Line, you will need to "Install" it.  Do this by running Time Line
INSTALL from the distribution disks.
><.CALLTEK
$6401
><.BAD5GP

The error is in section 1. 
$6500
><.BAD5GP

The error occurred while trying to phrase the device-specific questions.
$6501
><.BAD5GP

This error could also be caused by a problem with the values file,
whose extension is .5GV.
$6921
>7935
$7934
uMaximum Report Columns Exceeded
sh

You have specified column widths that, in total, exceed 255.

To correct:
  Select fewer columns for the report.
  Decrease the width of some of the columns.
$7935
><.HELP
When entering assignment columns, enter columns referring to EITHER
baseline or current assignment data, but not both in the same report.
$8703
The data file contains a record from a foreign or add-in product that
is too large to store.

This prevents proper loading of the schedule file.
><.CALLTEK
$8704
The data file contains a record from a foreign or add-in product, and
there is not enough virtual memory to store it.

This prevents proper loading of the schedule file.
><.CALLTEK
$10112
uDates - Workhours Conflict
sh

This message indicates a conflict between the Workhours and Dates
Calendars.  You have marked a date for WORK whose day of the week has
no workhours available.

  uLeave date as WORK   allows the conflict.  If you select this,
8be sure to change the Workhours Calendar to add
8hours to the appropriate day of the week.
  uChange date to NO WORK automatically toggles the conflicting date
8to a Non Work date.
  uStop checking     interrupts this process.  Select this if
8you want to exit immediately to change the
8Workhours Calendar.
$10132
Your Workhours Form contains start or stop times that are on half- or
quarter-hour boundaries, and these are incompatible with the schedule
precision you have chosen on the Calendar Settings Form.

For example, hourly precision cannot be used with a half-hour boundary.

  Adjust work hours:  changes the work hour boundaries to match the
5precision.

  Allow me to change precision: increases precision enough to represent
5the start and stop times you have entered.

Escape will change the precision.  
$10200
Time Line has a maximum calendar range from 1983 to 2017, but this full
range is often restriced by your calendar precision.  The Calendar
Settings Form controls the scheduling precison, and, because the program
can schedule a maximum of 65,535 distinct moments of time, the more
precise the scheduling and the fewer Non Work days, the less the total
calendar range.

If you choose CProceed, Time Line will remove most of the unused days
from the beginning of your calendar, up to the earlier of either the
As-of Date or the start of the first task.  It will do this by marking
them as "Non Work."  This frees up more moments of time to be used towards
the end of your schedule.

You can mark some of these as Work days again by using the Calendar Dates
Form, if you wish.

See the Calendars chapter of the User Manual for a full discussion.
$10210
*1*

Time Line is guessing at your typical work day and work week.  If the 
program is correct that these are usually what you mean when you say 
"day" and "week", select Yes.

If you have workhours defined on a day of the week that is not normally
a "work" day in your Dates Calendar, you will probably want to select No
to leave the definitions of Standard Workday and Workweek unchanged.

If incorrect, select No, and enter the correct numbers into the Calendar
Settings Form. 
$10220
uEffect of Change to Standard Settings
sh

You have changed the standard hours per day, or days per week.  Since
Time Line used the previous settings to schedule tasks, it needs to know
how to reschedule those tasks, given your new standards.

  If you have increased the standard workweek to shorten the schedule
!(do more work each week), answer "Keep".  This is also true for a
!shortened workweek or workday with less work accomplished.
!- Time Line will consider the tasks to represent the same amount of
#work as before; it will just schedule more work each week (or day).

  If you have changed the standards, but DON'T want the changes to affect
!tasks already scheduled, answer "Recompute".
!- Time Line will attempt to maintain the current start and end dates by
#considering each task to involve more or less work.
$10224
uStandard Workday/Workweek and Workhours/Dates Calendar Discrepancy
sh

This message is cautionary.  Time Line has detected a marked difference
between the hours you say you CAN work - Workhours and Dates Calendars - 
and the hours you say you usually DO work - Calendar Settings Form.

  In general, the hours marked for work (Workhours Calendar) and the
!standard workday (Calendar Settings Form) should closely agree.  (Time
!Line converts task durations or efforts expressed in "Days" or "Weeks"
!to an equivalent number of hours when scheduling.)
  You can ignore the warning if your workhours vary markedly from day to
!day and you've entered those differences correctly.  (In this case,
!entering task durations in hours might be best.)
  When checking for a discrepancy, Time Line looks at only a small part
!of the total calendar.  If the Calendar Settings are valid for the
!the calendar period that your schedule is active in, you can ignore
!this message.
$10235
When you are using a date format based on a week numbering system, a 
Fiscal Year cannot be defined.

If you want to define a Fiscal Year, you must use Configure/Date Formats
to choose another format.  You can then return to the Calendar Settings
Form and define the beginning of a Standard Year to a month other than  
January.

+Quit,Index,Week Numbers
=Quit,Index,WEEKNUM
$10503
uAbandon Schedule in Memory?
sh

You are about to retrieve a schedule that will replace the schedule
currently in memory.  However, Time Line has detected that you have made
changes to this schedule and have not saved it.  Retrieving the schedule
will therefore abandon the changes you have made.

  uCancel           stops the operation, saving your changes.
<You may then save the schedule with File/Save.
  uAbandon schedule in memory continues with the operation, losing the
<changes.
$10508
uSet Recalc to Manual?
sh

You are retrieving a schedule that was saved with Recalculation set to
"Automatic" and Resource Leveling "On".  Time Line would normally
recalculate such a schedule immediately, but this could take a long time
with a large schedule.  So you're given an option:

  uProceed sets Recalc to "Manual", and retrieves the schedule.
  uCancel  also retrieves the schedule, but leaves Recalc set to
)"Automatic".
$10905
><.PROBLEM
Serial printer not ready.  There is no Data-Set-Ready signal available on
the serial printer port.

  The printer is not turned on.
  Your cable is incorrect, or your printer does not support DSR.
!  Serial printing requires a null-modem cable or equivalent.
  There is no serial printer connected.
!  Attach your serial printer.
$or
!  Using Configure/Printer from the Main Menu, change to a parallel or
$DOS printer.
$10906
><.PROBLEM
There is some kind of error with your printer.

  The printer is not turned on.
  There is no printer connected.
  The interface options are not set correctly.
!  Using Configure/Printer from the Main Menu, select your printer, and
$the Parallel, Serial, or DOS output method.
$10907
><.PROBLEM
Serial printer not Clear-to-Send.  (There is no Clear-to-Send signal
available on the serial printer port.)

  The printer is not turned on.
  There is no serial printer connected.
!  Attach your serial printer.
!  Using Configure/Printer from the Main Menu, change to a parallel
$or DOS printer.
  Your printer does not support Clear-to-Send (CTS).
!  Change the switch settings on your printer (see your owner's manual).
!  Using Configure/Printer from the Main Menu, change to a protocol
$that your printer supports (such as XON/XOFF).
  Your cable is incorrect.
!  The CTS protocol requires a signal on the CTS wire.
$10909
>3564
$11750
Time Line cannot create the report because there are no tasks in 
the schedule.  You must create a schedule first, or use File/Retrieve
to obtain one. 
$11751
The predecessor and successor tasks are normally sorted by start date.
They will not be.
$11904
*1*

The file will be removed from the disk.  Undo will not bring it back.

If this is an important file, make sure you have backup copies before
removing it.

You can "Exit to DOS" to check files, make backups, etc. using the 
Utilities/Exit to DOS command.
$12306
><.PROBLEM
Neither the virtual memory swapfile nor EMS memory are available.
Time Line needs one or the other of these to manage its files.

  Quit the program.
  Check the "SWAPVOL=" parameter on the startup command line.
  If you are using EMS, reboot your computer.  A previous program may
!have used EMS and not returned it.
><.NETADMI
>.CALLTEK
$12322
Time Line stores information about your computer and your choices for
various options in a configuration file named "TLCNFG5.DAT."  

Either this file is missing, was not installed, is inaccessible or there
has been an error while reading it.

Some of the options it contains have not been loaded.
><.CALLTEK 
$12350
*1*
Only file names from the current version can be loaded from the command
line.  For earlier version files, use File/Import.  
$12407
uDuplicate names?
sh

  The schedule you're combining contains at least one resource, cost,
!layout, or filter name that duplicates a comparable name in the current
!schedule.  For instance, you may be combining a schedule with "Bob" as
!a resource into a schedule that also has "Bob" as a resource.
  Time Line is not sure whether you want to use the definitions in the
!combined schedule or retain the definitions of the current schedule.
  Answer "C" to use the definitions in the combined schedule.
  Answer "E" to retain the definitions of the current schedule.
$12433
uFILE/COMBINE:  Different Calendars
sh

This message always appears during File/Combine, but it is only important
when the combined schedule's master calendar differs from the current
schedule.  If a five-day task originally scheduled over a holiday is
combined into a schedule without that holiday, should it end at the same
time (becoming a six-day task) or be scheduled to end a day earlier.

  If you want to preserve timing estimates from the combined schedule,
!answer "Durations".  This is the usual selection.
!- Time Line will change the tasks' end dates, if need be, to conform
#to the current schedule's calendar.
  If you want to preserve the originally scheduled start and end dates
!from the combined schedule, answer "Start/End Dates".
!- Time Line will change the tasks' durations, if need be, to conform
#to the current schedule's calendar.  
$12436
uRestricted Time Line Version
sh

This version of Time Line limits the number of tasks possible in a
schedule.  The schedule you imported exceeded this limit, so was truncated
to the allowed maximum.  You can work with this schedule, but the file
integrity should not be trusted.  Messages regarding "missing tasks" may
be displayed.
$12438
uFILE/COMBINE:  Calendar Into Existing Schedule
sh

You cannot combine a calendar into a schedule that has existing tasks
and/or resources.  To combine a calendar, follow these steps:

  Save your current schedule (we'll call it "A").
  Select Schedule/Erase to clear memory.
  Select File/Combine (Calendar) to combine the calendar from the
!other schedule (we'll call it "B").
  Select File/Combine (Tasks/Resources/Costs) for the file ("A") you
!saved in step 1.  You now have B's calendar combined with A's tasks.
$12440
uFile Import Problem
sh

You have imported a schedule saved with a previous Time Line version that
links to other schedules of that version.  You need to convert (import and
save) those other linked schedules first for the links to operate properly.
$12444
uImporting Span Tasks
sh

You are importing a Version 2 schedule that contains "Span" tasks.  This
feature is not supported in the current version, so a conversion is made.

 Version 24Current Version
 -5&-<
 Task A(,Task A0
 Task B (span)!#(Task B (summary)&#
 Task C-)Task B1 (added ASAP)  
@Task B2 (added ALAP)$
>Task C5

>Task B1 is a successor of Task A.
>Task B2 is a predecessor of Task C.
$12454
*1*

When converting assigned percentages from the version 2 file, Time Line
has encountered a number that is too large or too small to represent
exactly.  It will be converted to a similar number, within range. 
$12475
uCOMBINE:  Options
sh

Time Line can combine entire schedules (for running consolidated reports,
for instance) or just certain components of a schedule (perhaps a resource
list from another project).

  uTasks/Resources/Costs combines all components of another schedule.
  uResources/Costs    combines just the Resource/Cost List.
  uCalendar       combines just the calendar (current schedule
7must be empty).
  uFilters        combines just the Filter Lists.
  uJournal Notes     combines just the notes in the Journal List.
  uLayouts        combines just the Layout Lists (Gantt & PERT).
  uGraph Palettes    combines just the list of Graph Palettes for
7graphic Gantt Chart and PERT Chart.
  uColumn Names     combines just the column headings.
+Quit,Index,Tasks,Resources/Costs,Calendar
=Quit,Index,COMBTask,COMBRsrc,COMBCldr
$12477
uFiscal Years
sh

Indicate a fiscal year calendar by entering any month OTHER than January
in the Standard Year Begins field of the Calendar Settings Form.  If you
do so, all dates displayed will include the notation "FY" as part of the
date format.

Note:  Not all date formats have room for this.  Before you can use a
fiscal year, you need to do two things:

1.  Using Configure / Date Formats, choose format 1, 2, 3, or 4.
2.  On the Calendar Settings Form, choose a starting month.
$12478
*1*

Schedules which had recalc errors at the time that they were saved
may not import task dates, durations or other information correctly.

To correct the problem, retrieve the schedule using the version of the
Time Line software corresponding to the current schedule file, recalculate,
correct any loop or other errors which prevent proper calculation, then
save the schedule.  It will now be ready for import.
$12502
>LOOP
$13305
uOne Alternate View
sh

The Histogram, PERT, and Work Tree views are known as "alternate views".
To switch between alternate views, you must change back to the Gantt view
first.

To switch from PERT to Work Tree views, for example, first select
Views/Gantt from the menu, then select Views/Work Tree.

To leave any of the alternate views and return to the Gantt view, select 
Views/Gantt or press [Ctl/F8].

To change the resource names displayed in the histograms, press [F8].
$13418
uLinked File No Longer Available
sh

You are retrieving or combining a file containing a link to a schedule
that no longer exists.

The following action is recommended:
  Continue with the file operation.
  Display a layout containing the Linked File column.
  Scan the Linked File column for the link in error.
  When found, change link or delete it if the linked file is unavailable.
$13730
*1*

Time Line cannot find a place in the schedule for this task.

There are several possible causes:
  A resource may be assigned in an amount larger than it is ever
!available for a sufficient interval (as specified on the Resource/Cost
!Form, Availabilities field).  Note: This is the probable cause if you
!have recently changed Availabilities.
  A detailed schedule precision (Calendar Settings Form) may have
!shortened the calendar to less time than is needed by the schedule.
  Extra, unneeded dependencies may be pushing the task past the end of
!the calendar.
  If this task is set No Later Start, that request may not be feasible.
/7
Use the following steps to eliminate the problem:
  For each assigned resource, note the Availability levels and periods
!(Resource/Cost Form), and compare them with the assignment amount (Task
!Form) to ensure that an availability of sufficient length exists.
  Change Precision field (Calendar Settings Form) to larger time period.
  Review dependencies [F4].  Also review parents (direct and indirect).
$13731
*1*

It is not possible to locate a date on which to schedule this task.

The most likely cause is a lack of resource availability.  A resource
has probably been assigned to the task in an amount larger than that
resource is ever available (for a sufficient interval).  For example,
if Joe were assigned to a task at 100%, but is not available at more than
80% at any date that meets other schedule requirements, the task could
not be scheduled.

Check the assignments, and the Availabilities field (Resource/Cost Form).

You may be able to cause Time Line to schedule the task by raising its
priority.
$13732
*1*

  The tasks you have entered cannot be scheduled within the range of the
!calendar.  Perhaps your project is too long.  See the Calendars
!chapter in the Manual.

  Resource vacations, or insufficient availability of some resources, may
!make it impossible to schedule certain tasks.  Check the Availabilities
!field on the Resource/Cost Form, and assignments within the Task Forms.

  Schedule precision may be too detailed to allow full schedule duration.
!Check the Calendar Settings Form.
$13733
*1*
#
  Partial dependencies may cause tasks to be scheduled before the start
!of the project.  Check using the Dependency List [F4].

  Task may have a required start before the start of the project.
!Check using a layout that shows Start Date Restriction.

  A required start date for a task may cause earlier tasks to be
!scheduled before the start of the work days in the master calendar.
!Check by viewing the Master Calendar, and by checking the dependencies
!and start date restrictions, as noted above.
+Quit Help,Index,Start Date Restriction
=QUIT,INDEX,TCOL113
$13734
*1*

The Time Line program could not compute a number of people to work on the 
task that, multiplied by the duration of the task, would add up to the 
amount of effort entered on the Assignment Form.

This can happen if the required effort is zero, but is more often
due the duration of the task being too short.

Time Line has a maximum of 256 people working at 250%.
$13735
*1*

The program was not able to obtain enough DOS memory to finish computing
the schedule.  Dates, costs, or status may not be accurate.

Please check Appendix C in the Time Line Manual for help on obtaining
more memory.
$13736
*1*

There is no period on the resources' calendars when this task could be
scheduled that does not violate the restrictions on its start date.

Check using a layout that shows Start Date Restriction.

Check the resources' calendars using the Resource Calendar field
(Resource/Cost Form).
+Quit Help,Index,Start Date Restriction
=QUIT,INDEX,TCOL113
$13737
*1*

Time Line contains a limit on the number of distinct resource per task
that can be levelled.  You have exceeded this limit.
$13738
*1*

There is no period on the resources' calendars that would allow the 
future work on this task to be scheduled so that it simultaneously meets
the two requirements of:

a.  the work ending by the entered end date of the task, and 

b.  not overlapping an unavalable period.

Or else, the task is marked Future, and the Schedule Calculations Form
says to schedule future tasks to the right of the As-Of date, but that
conflicts with the Start Date Restriction of the task.
+Quit Help,Index,Start Date Restriction,Force Future
=QUIT,INDEX,TCOL113,CALF1
$13739
*1*

Time Line cannot find a place in the schedule for this task.

There are several possible causes:
  A resource may be assigned in an amount larger than it is ever
!available for a sufficient interval (as specified on the Resource/Cost
!Form, Availabilities field).  Note: This is the probable cause if you
!have recently changed Availabilities.
  A detailed schedule precision (Calendar Settings Form) may have
!shortened the calendar to less time than is needed by the schedule.
  Extra, unneeded dependencies may be pushing the task past the end of
!the calendar.

Use the following steps to eliminate the problem:
  For each assigned resource, note the Availability levels and periods
!(Resource/Cost Form), and compare them with the assignment amount (Task
!Form) to ensure that an availability of sufficient length exists.
  Change Precision field (Calendar Settings Form) to larger time period.
  Review dependencies [F4].  Also review parents (direct and indirect).
$13740
*1*

The effort entered on the task form for the task cannot be divided evenly
among the entered resources.  For example, a seven-work-hour task 
cannot be divided among five resources into an integral number of hours.

In these cases, Time Line rounds the effort up or down.

With greater schedule precision (Master Calendar Settings Form) Time Line
will need to do less rounding, and, in some cases, may be able to 
allocate the effort exactly.  For example, hourly precision would prevent
dividing three hours among two resources, but half-hour precision would
permit it.

CIf the amount of the discrepancy is not significant to your schedule you
Cmay ignore it.  And, you can prevent the warning message by changing the
effort entered on the task form to the amount shown as actually allocated.
$13741
*1*

Because entering a task as both done, and ending in the future
involves a contradiction, the effort and expenses allocated on the task
may not match your expectations.

We recommend either changing the task's status, changing the As-of date,
or entering an actual end date.
$13742
*1*

Because entering a task as both Started, and starting in the future
involves a contradiction, the effort and expenses allocated on the task
may not match your expectations.

We recommend either changing the task's status, changing the As-of date,
or entering an actual start date.
$13743
*1*

Because entering a task as both Future, but with some spent effort,
involves a contradiction, the scheduling of the task, and/or effort and 
expenses allocated on the task, may not match your expectations.

We recommend either changing the task's status (to Started or Done), or
eliminating the spent effort.  If you are not Cost Tracking, eliminating 
the spent effort is accomplished by setting the Achievement percentage
("Percent Complete") to zero.  If you are Cost Tracking, you must edit
each of this task's assignments, setting the Spent effort to zero.  If
you are not sure which Tracking mode is active, check the Cost Tracking
setting on the schedule Options Form [Sh/F6].
$13744
*1*

You have selected to level tasks within slack (Calculations Form), but 
this request would require that the task start sooner than is allowed for
some other reasons, such as

  An entered Must Start or No Sooner Start date.
  The requirement that future tasks be scheduled on or after the As Of
!Date (selected on the Calculations Form).
  ASAP tasks without predecessors are scheduled on or after the As Of
!Date.
$13745
*1*

Tasks which are Done should not have remaining effort on them.

Please update the task to reflect that the effort is spent.  You may
need to adjust the total effort assigned to the task or some of the
assigned resources to match the effort that was actually spent on this
task.
$13746
*1*

When a task is a milestone (that is, the start and the end date are the
same, and the duration is zero) there is no time in which to allocate
spent amounts of resources or variable costs.

This situation can also arise on an effort-driven task that has all of 
its effort spent but is marked as "Future."

On a linked task, if the task occurs before the dates of work time on the
master calendar, you may receive this message.

Please review this task and determine if the costs were, in fact, spent.

Correct the problem by either removing the spent costs, changing the task
duration or effort to an amount greater than zero, or altering the task
status.
$14009
*1*

The parameters file, that defines the printer characteristics,
has an incorrect internal structure, or there is a file error 
reading it.

  You may be able to correct this by reinstalling your printers
!(*.5PP files) from the distribution diskettes.
><.CALLTEK
$14016
>14018
$14018
uError in TLPRINT5.CFG File
sh

Time Line has found a syntax error in the TLPRINT5.CFG file.

  If you have edited this file to add or change printer configurations,
!please review your changes for problems.
  If you have NOT edited the TLPRINT5.CFG file, call Time Line technical
!support:
>.CALLTEK
$14019
>14018
$14020
>14018
$14021
>14018
$14022
>14018
$14050
*1*

The parameters file that defines the printer characteristics cannot
be read.

You may be able to solve this by trying again, or consulting with your
network administrator.

Failing that, your may be able to correct this by reinstalling your 
printers from the distribution diskettes.
><.CALLTEK
$14051
>14050 
$14052
*1*

Time Line cannot write the file with your printer choices to disk.

Perhaps your disk is full, or write protected?

><.NETADMI
><.CALLTEK 
$14100
There are currently as many people using this copy of Time Line as
you have LAN registrations.

You can increase the number of registrations by using Time Line LAN Packs,
or additional copies of Time Line.

><.CUSTSER
$14103
*1*

><.NETADMI
><.CALLTEK
$14104
>14103 
$14107
All the authorized version 5 sessions are in use right now.  However,
you do have authorized sessions from version 4.  Upgrading to version
5 will give you the ability to use version 5 of Time Line.

><.CUSTSER
$14415
uFile Has Been Changed
sh

  If you are on a network, you should probably NOT save this schedule.
!Someone else was able to retrieve the file after you did; they made
!changes to the file and saved it.  When you save, your changes will
!overwrite theirs.
><.NETADMI
  If you are not on a network, this condition was probably caused by a
!hardware error.  We suggest running diagnostics on your hard drive.
$14501
>3564
$14511
uIncorrect Directory
sh

Press [F2] for the Directory List.  Use the [+] and [-] keys to
open and close directories within the list.

Press [Enter] when you have the cursor on the correct directory.
$15308

Text is printed to whichever printer is currently chosen for Reports.

  To change the destination of the printout to Printer, Disk File
!(or screen), use Reports/Form.

  To configure a new printer, or change hardware settings, use
!Configure/Printer.
$16407
uDelete Standard Filter
sh

Standard filters appear in all schedules' Filter Lists.  Because a
standard filter name might be used by any of your schedules, be very
careful about deleting them.  Especially on a network, be sure that the
standard filter name is not used by someone else in your network group.

If you accidentally delete ALL standard layouts or filters, you must
reload the original TLCNFG5.DAT file from the original Time Line
diskettes:
>.CALLTEK
$16610
*1*

This file is from a version of On Target that is more recent than your
copy of Time Line, and the Time Line program is not prepared to read it.

><.CUSTSER
$16611
*1*

The file does not appear to be an On Target file.

Either it is in fact not, or there is a problem with your disk files, or
it is from a version of On Target that this version of Time Line is not
prepared to read.

 Verify that the file can be read by On Target.
><.CALLTEK
$16612
>16611 
$16613
*1*

Time Line cannot convert dates before 1980.  The date has been changed to
1980.
$16614
Time Line is unable to convert an On Target date, probably because it 
is out of the range of the Time Line calendar.

Please see the Calendar chapter in the Users Manual. 
$16615
*1*

Time Line identifies specific tasks in the On Target files by finding 
their WBS numbers, looking for the particular WBS number entered on the 
Task Link Form.

Evidently there is no task in the On Target file having the same WBS 
number as was entered on the form.
+Link Types,WBS Link,Quit Help
=LINK2,LINK3,QUIT 
$16616
>16611 
$16701
*1*

Time Line cannot create your schedule.  Your computer system may have
run out of disk space, or if you run Time Line on a network, your network
access rights may have changed.
$16617 
*1*

Time Line can only record dates which are working dates in the schedule
Master Calendar.  Other dates, marked Non Work in the schedule Master
Calendar Dates form, or without working hours in the Master Calendar Workhours
form, cannot be scheduled.

You can add additional days needed by the linked On Target schedule by 
editing the Master Calendar.  Select the menu choice Schedule/Master Calendar.
$16702
Time Line could not find your On Target schedule.

 Verify that the schedule file exists and attempt to import the schedule
  again.
$16703
Time Line did not have enough memory available to import the On Target
schedule.

Please check Appendix C in the Time Line Manual for help on obtaining
more memory.
$16704
>16701
$16705
>16611 
$16706
>16611 
$16707
>16701
$17129
*1*

  Columns that contain text can only be compared to text.

  Columns that contain dates can only be compared to dates.

  Columns that contain numbers or money can only be compared to other
!numbers.  (However, text conditions such as "..9" can by used, which
!will format the number as text, and then make the comparison, finding
!numbers that end in "9".)

  Formulas cannot be used.
+Quit,Index,Conditions
=QUIT,INDEX,FLTR19
$17510
uMove After Sort
sh

You are attempting to move a task (with [Shift] and the arrow keys), but
you've sorted the task list at some time during this session.  The
question is: Are you using this sorted sequence as a basis for a new
manual sort order (in this case Time Line forgets the original manual
sort order) or do you wish to return to that original manual sort order
at some point?

  uCancel the move         stops this operation.
  uMove but keep last manual order allows the move, but does NOT
Bestablish a new manual order.
  uMove and make a new manual order allows the move, then uses the
Bresulting sequence as a new manual
Border (forgets the original sequence).
$17809
*1*

This resource has a single number entered into is Availability Profile on
its Resource Form, and that number is lower than the amount you have
entered.  In other words, you are assigning more people to work on this
task than are available.

  Lower the assigned percentage, or

  Increase the availability (Resource Form), or

  Change the availability profile to have more than one rate.
$17839
Effort, actual work, can only occur over a period of time.  Consequently,
tasks that have no duration do not allow assignment of effort. 
$18407
uDelete Standard Layout
sh

Standard layouts appear in all schedules' Layout Lists.  Because a
standard layout name might be used by any of your schedules, be very
careful about deleting them.  Especially on a network, be sure that the
standard layout name is not used by someone else in your network group.

The schedule called TEMPLATE contains a set of layouts identical to
the standard layouts except that they do not have an asterisk.  You
can combine a layout from template into another schedule, but it will
not have an asterisk (*) and it will not automatically appear in the
Filter Lists of your other schedules.
$18802
>SCHEBas
$18809
uModified Baseline Summaries
sh

If your schedule has an outline structure and you have added detail
tasks to existing baseline parent tasks, Time Line does not adjust
those baseline summary tasks to reflect any baseline additions or
changes you make to the children.

However, you may move to a summary task and update its baseline (using
the "Cursor Task Only" baseline option).
$18810
>18809
$18811
uBaseline Changes
sh

  uCosts resets the baseline costs to equal the current schedule
'costs, but does not change baseline dates.

  uDates resets the baseline dates to equal the current schedule
'dates, but does not change baseline costs.

  uBoth  resets the baseline costs and dates to equal the current
'schedule.
+Quit,Index,Baseline
=Quit,Index,SCHEBas
$18814
uRecord Exact Resource Assignments?
sh
Recording the task dates and costs is sufficient for almost all possible
baseline analysis and reporting.

However, Time Line offers the additional option to record for each task
not only when the task was scheduled, and its planned costs, but also the
detailed allocation of each resource assigned to each task.

Advantages: If you choose "Yes," these assignments will be recorded as 
*the number of resources assigned in each period of 
*assignment.  In other words, if a resource leaves a task 
*to go on vacation, or splits around a higher-priority task,
*the duration of that absence is noted.

*"Yes" enables Assignment and Cross-Tab reports of Baselines.

Drawbacks:  This extra data takes additional memory and will make your
*schedule files larger.  It is unnecessary unless you plan to
*print Baseline reports of Assignments, Cross-Tabs or Histograms.
$19419
><.PROBLEM
Attempt to write on write-protected diskette.

On a diskette, this means that the write-protect notch has been covered,
prohibiting writing of data.

  Verify that this is a diskette that you don't mind changing, then
!remove the protective tab.

On a network file, this means that you are not allowed to write to that
file or (perhaps) directory.

>.NETADMI
$19420
><.PROBLEM
Unknown unit.
>.CALLTEK
$19421
><.PROBLEM
Drive not ready.

>19431
$19422
><.PROBLEM
Unknown command.
>.CALLTEK
$19423
><.PROBLEM
Data error (CRC).

There is a problem with your disk drive or diskette.  This usually
indicates that the surface has become dirty or worn.

  Check the diskette for damage and retry.
  Clean the drive.
  Try another diskette.
$19424
><.PROBLEM
Bad request structure length.
>.CALLTEK
$19425
><.PROBLEM
Seek error.

>19431
$19426
><.PROBLEM
Unknown media type.
>.CALLTEK
$19427
><.PROBLEM
Sector not found.

>19431
$19428
><.PROBLEM
Printer out of paper.

  Check the paper supply and feed path, correct if necessary.
  Check the printer cables.
  Check power.
$19429
><.PROBLEM
Write fault.

>19431
$19430
><.PROBLEM
Read fault.

>19431
$19431
If you're trying to read from or write to a diskette, perhaps:
  The diskette is not properly in the drive, or the door is not shut.
! Fully insert the disk and shut the door.
  The disk is not formatted.
! Find a diskette that is formatted, or
! Use "Utilities/Exit to DOS" to run the DOS FORMAT program.
  The diskette and drive types do not match (for example, a 1.2 MB
!diskette in a 360KB drive).
! Change to a suitable (formatted) diskette.
  The disk or drive has a problem.
! Try a different drive.
! Use "Utilities/Exit to DOS" to run DOS CHKDSK on the diskette.
$19432
><.PROBLEM
Sharing violation.

Someone else is using the file.

>.NETADMI
$19433
><.PROBLEM
Lock violation.

>.NETADMI
$19434
><.PROBLEM
Invalid disk change.

>19431
$19435
><.PROBLEM
FCB unavailable.

With File Sharing loaded, you tried to concurrently open more files than
specified with the FCBS configuration command.

>.NETADMI
$19436
><.PROBLEM
Sharing buffer overflow.

>.NETADMI
$19450
><.PROBLEM
Network request not reported.

>.NETADMI
$19451
><.PROBLEM
Remote computer not listening.

>.NETADMI
$19452
><.PROBLEM
Duplicate name on network.

>.NETADMI
$19453
><.PROBLEM
Network name not found.

>.NETADMI
$19454
><.PROBLEM
Network busy.

>.NETADMI
$19455
><.PROBLEM
Network device no longer exists.

>.NETADMI
$19456
><.PROBLEM
Net BIOS command limit exceeded.

>.NETADMI
$19457
><.PROBLEM
Network adapter hardware error.

>.NETADMI
$19458
><.PROBLEM
Incorrect response from network.

>.NETADMI
$19459
><.PROBLEM
Unexpected network error.

>.NETADMI
$19460
><.PROBLEM
Incompatible remote adapter.

>.NETADMI
$19461
><.PROBLEM
Print queue full.

>.NETADMI
$19462
><.PROBLEM
Not enough space for print file.

>.NETADMI
$19463
><.PROBLEM
Print file was deleted.

>.NETADMI
$19464
><.PROBLEM
Network name was deleted.

>.NETADMI
$19465
><.PROBLEM
Access denied.

>.NETADMI
$19466
><.PROBLEM
Network device type incorrect.

>.NETADMI
$19467
><.PROBLEM
Network name not found.

>.NETADMI
$19468
><.PROBLEM
Network name limit exceeded.

>.NETADMI
$19469
><.PROBLEM
Net BIOS session limit exceeded.

>.NETADMI
$19470
><.PROBLEM
Temporarily paused.

>.NETADMI
$19471
><.PROBLEM
Network request not accepted.

>.NETADMI
$19472
><.PROBLEM
Print or disk redirection is paused.

>.NETADMI
$19480
><.PROBLEM
File exists.

You cannot create a file if another file of the same name exists and
you do not have permission to remove the original.

>.NETADMI
$19482
><.PROBLEM
Cannot make directory entry.

>.NETADMI
$19483
><.PROBLEM

Can be caused if the file is in use by some other user, or another
program on your computer.

The DOS error manuals call this error "Fail on INT 24" but the real
cause is not too well defined or documented.

>.NETADMI
$19484
><.PROBLEM
Too many redirections.

>.NETADMI
$19485
><.PROBLEM
Duplicate redirection.

>.NETADMI
$19486
><.PROBLEM
Invalid password.

>.NETADMI
$19487
><.PROBLEM
Invalid parameter.

>.NETADMI
$19488
><.PROBLEM
Network device fault.

>.NETADMI
$OVERLAY
><.PROBLEM
There is a problem with one of the overlay files that Time Line uses.
>.CALLTEK
$20201
uPrinting PERT and Work Tree Reports
sh

You may not print a Work Tree Report from within the PERT view, or a PERT
Report from within the Work Tree view.  Either report may be printed from
the Gantt or Histogram views, however.
$20228
Some tasks are scheduled to start sooner than one or more of their 
preceding tasks' end dates, and we cannot draw both the accurate start
date of the task box and the dependency lines.

This can be caused by valid, partial dependencies, or by a schedule that
has not been recalculated.  If the latter, recalculation (F9) will allow
the program to display a more accurate network diagram.

In either case, the program will place the task box as closely as it can
to the start date, but omit the dependency line.
$20250
><.PROBLEM
The number of tasks that can be displayed in the PERT and Work Tree views
is slightly less than can be displayed in the Gantt view.  If you have an
extremely large family, you need to close up the lower levels in order
to fit the family within the PERT display area.

If you continue to receive the message, you need to close more of the
family or you may have other families that need to be closed.
$20305
uPERT:  Problem with partial dependencies
sh

Your schedule contains at least one partial dependency from the start
or to the end of a summary task.

The Outline PERT will ignore any such dependencies, and the resulting
diagram may be drawn incorrectly.

  For a more accurate view of these partial dependencies, change the
!PERT style to Traditional mode.  This shows a summary task as two
!small partial boxes at either end of its family.  To do this, select
!Schedule/Options or press [Sh/F6], and change the Style field from
!"Outline" to "Traditional".
$20400
><.PROBLEM
There is not enough memory available to display the Work Tree view.

Since closing summary tasks lowers the memory required to display the 
Work Tree view, pressing "-" (minus) on some of the less important summary
tasks may allow the view to be displayed.
$20500
*1*

Time Line does not File/Retrieve files with this extension.  Only valid,
current Time Line files can be loaded.

For other file types, use the File/Import command.
$20606
>3564
$20607
*1*

This is an internal programming or installation problem.

The TLLINK overlay has detected that it has been asked to do an
incompatible action.
><.CALLTEK
$20609
*1*

You can create links to On Target schedules (extension TG1) and to 
Time Line schedules from versions 3, 4 and 5 (extensions T#0, T$0 and
5T0, respectively).

Pressing F2 from the file name or directory field will show you a
QuickPick list of file names to choose from.
$21211
>3564
$21215
>4607
$21400
*1*

  Dates must be formatted correctly.

  Start date must be earlier than end date.

+Quit,Index,Entering Dates,As-of Date
=Quit,Index,.DTFRMTS,OPTN3
$21407
uCross Tab Report:  Date Range Conflict
sh

Because the Cross Tab Report prints data in columns with date range
headings, it appears that each column's information reflects ALL tasks'
data pertaining to that time period.  However, entering a Date Range on
the Cross Tab Report Form can produce misleading data in certain columns.

For example, you would assume that a column labelled "1992" would contain
all 1992 data.  However, if a date range of 10/1/92 to 9/30/93 is entered,
the "1992" column would only reflect data from 10/1/92 to 12/31/92.

To correct this misleading presentation:
  Change the dates in the Date Range fields so that both start and end
!dates are on a Period boundary.
  Choose a smaller time unit in the Period field.  This prints more
!columns, each containing a more specific time range.
$21802
><.PROBLEM
Virtual memory swap file disk space is low.

>.SWAPDSK
$21805
><.PROBLEM
Virtual memory swap file disk is full.

>.SWAPDSK
$21806
><.PROBLEM
Virtual memory swap file disk does not exist.

  If you have EMS memory installed in your computer, you may be able
!to continue running this session of Time Line.
  This problem is caused by not having a DEFAULT disk drive, or the
!drive specified in the "SWAPVOL=" command line parameter does not
!exist.  For example, It may specify a RamDisk that is not currently
!configured on this computer, or the drive may be a removable disk drive
!without the disk (such as a floppy or cartridge drive).
  Time Line cannot continue running unless it has sufficient virtual
!swapping space.

/
What to do:

  Time Line will soon exit.
  Examine the TL.BAT file you are using to run Time Line, looking for the
!SWAPVOL=<existing drive> option.
  If the specified drive is "DK:", that means "the current disk".
  Either change the drive to one that exists, or, if it is DK:, change
!your current DOS disk to one that exists by typing the disk name (like
!"C:") at the DOS prompt.
  Restart Time Line.
>.CALLTEK
$22900
uExit to DOS
sh

You are about to exit to DOS.  There are several ways you might want to
do this.

  uProceed    exits to the DOS prompt, allowing as much memory as
/possible with which to run programs.  This option takes
/longer than "Quick Exit".
  uCancel     quits the Exit to DOS routine and returns you to
/Time Line.
  uRun a Program brings up the DOS Exit Form.  Type the name of a
/program to run immediately when exiting to DOS.
  uQuick Exit  exits to the DOS prompt quickly.  This option takes
/less time than "Proceed", but leaves less memory with
/which to run programs.
$22910
*1*

When running a program, or choosing "Proceed", Time Line frees up as 
much memory as possible for other programs to run by copying itself and
its data to a file on disk.  This file is copied back to memory, and 
Time Line resumes, after your other programs have finished.

This is also used when printing or viewing graphics in order to run as
fast as possible.

However, your disk does not have enough room on it.  (About 700K is
needed.)
/15
Possible cures:

  Use Quick Exit.  This does not free up any memory, so large programs
!cannot run.  However, small programs can.

  Use Utilities/Stats, and choose the Run Line Options topic to see which
!drive is assigned to MEMSWAP.  (If blank, the current drive is used.)

! Using Exit To DOS/Quick Exit, remove any unimportant files from that
#drive.

! Or, exit Time Line, and run it again, changing your command line to
#contain a run line option in the form MEMSWAP IS <drive>, where 
#<drive> is the name of a disk volume with more room.  For example,
#you might enter "TL ! MEMSWAP IS G:".
+Quit,Index,Exit To DOS
=QUIT,INDEX,UTILExi
$22923
*1*
><.CALLTEK

This is usually related to a failure of an EMS memory manager that will
not release its pages, or a prior failure of some part of the Time Line
program, that has left pages locked.
$23202
*1*

Most of the pages of EMS memory allocated to Time Line have been filled.
If possible, the program will switch to disk swapping, but this has a 
speed penalty.
><.MOREEMS
$.MOREEMS

Review the memory allocations in Time Line by using the Utilities/Stats
command.

To obtain more EMS memory, 

 If more is available, but not allocated to Time Line, exit the program
  and run it again, allocating more with the EMSPAGES IS command.

 If no more is available, either install more memory, or use a memory
  manager allocation command that assigns more to EMS.
><.CALLTEK
$23204
*1*

Before using EMS memory, Time Line runs several tests to ensure that it
is working reliably.  Yours is not.

Your EMS driver is not allocating or mapping pages correctly, or the 
memory chips are not accurately holding their contents.
><.CALLTEK
$23205
*1*

You have called for EMS memory with the EMSPAGES IS run-line option, but
not enough is available.

><.MOREEMS
$23206
*1*
><.CALLTEK 
$23207
>23206 
$23208
>23206 
$23601
uRead File From
sh

  uDisk        brings up a list of files (with .TXT extensions) in
4the default directory.  Select the file containing
4the outline.  If your file has another extension,
4press [F2] and enter it in the File Access Form.
  uKeystroke Transfer brings up the notepad.  Type an outline into the
4notepad and press [F10] to start the import.  When
4the import is complete, the outline is saved as a
4Journal note.
$24007
>7935
$24250
>3564
$24402
uMaximum Line Length
sh

Use this menu to select a maximum line length for the exported CSV file.
If, during the export operation, Time Line finds a line that exceeds the
length entered here, it breaks the line (inserts a CR/LF) and continues
the data on the next physical line of the file.  No data is ever lost
(truncated from the end of the line) from the export file.

  If you are going to be processing the export file with another
!program, "Unlimited" is probably the best choice.
  If you are going to be editing the file, select a line length that
!is appropriate for your text editor.
$25001
><6400
$25117
><6400
$26201
*1*

  On the Graphics/Gantt or PERT Form, edit the field "Title & Legend".
!Reduce the size or number of titles, notes or legends.

  Use a larger paper size if your printer is capable of that.  Using 
!Configure/Graphics, setup that larger size.
$26313
*1*

Time Line was unable to save your macros in their file.
><.CALLTEK 
$26904
>CONFDat
$26909
Date formats based on a week numbering system cannot be used when a Fiscal
Year has been defined.

If you want to use such a date format, you must first select one of the 
other formats (1, 2, 3, or 4), and then change the start of a Standard
Year to January on the Calendar Settings Form.  You will then be able to
return to Configure / Date Format and select a week number date format.

+Quit,Index,Week Numbers,Calendar Settings Form
=Quit,Index,WEEKNUM,CALN3
$26908
Date formats in Time Line have a maximum of 17 characters.

To shorten yours:

  On the Calendar Settings Form, check if you have a fiscal year, one
!that does not begin in January.  Fiscal years take extra length.

  Choose a shorter date and time format from Configure / Date Format.
!Formats 1, 2, 3 and 4 all work with fiscal years.

+Quit,Index,Calendar Settings Form
=Quit,Index,CALN3
$27904
C*1*

The supporting Time Line file has inconsistent data about its assignments.
><.27900
$27905
C*1*

Could be a memory problem.

More likely, there is a problem with the format of the supporting file.
><.27900
$27908
C*1*

There is no task in the supporting schedule with the indicated WBS number.

Perhaps someone renumbered the WBS codes?

You can view the supporting schedule by using the Task Link Form and
pressing [F2] from the WBS field.
$27909
C*1*

A supporting schedule must have some tasks.
><.27900
$27911
C*1*

If a task in the supporting schedule has the same resource assigned to
a task more than once, the rollup of that task may not be accurate.

><.27900
$27950
C*1*

><.27900
$29250
>3564
$29306
*1*

This is a cautionary note.  Normally, all changes to your schedule can
be backed-out by using the Undo command.  However, Undo does not 
counteract Import.

Importing new data can make large changes to a schedule.  Since Undo does
not reverse changes caused by import, you may want to save your current
schedule file as a precaution, in case the import changes the schedule
in a way you do not want.

This is entirely optional. 
$29307
*1*

The data table that you are importing contains columns of data, some of
which refer to the baseline schedule.

If you choose Proceed, you will allow these columns to override the 
baseline data currently stored in the schedule.  Unless you are certain
that this is what you intend, we recommend choosing Cancel, since the 
baseline is the original record of your schedule that you will use to
compare all subsequent schedules against.
$29310
*1*

The import data table has an invalid structure.  This is a programming
problem.  Please call Time Line technical support.
><.CALLTEK
$29601
><.BAD5GP
$29602
><.BAD5GP
$29603
><.CALLTEK
$29604
><.CALLTEK
$29605
><.CALLTEK
$29609
><.BAD5GP
$29610
><.CALLTEK
>19431
$COLORS
A ATest  B BTest  C CTest  D DTest  E ETest  F FTest  G GTest  H HTest  I ITest
J JTest  K KTest  L LTest  M MTest  N NTest  O OTest  P PTest  Q QTest  R RTest
S STest  T TTest  U UTest  V VTest  W WTest  X XTest  Y YTest  Z ZTest

[ [Test  \ \Test  ] ]Test  ^ ^Test  _ _Test  ` `Test

a aTest  b bTest  c cTest  d dTest  e eTest  f fTest  g gTest  h hTest  i iTest
j jTest  k kTest  l lTest  m mTest  n nTest  o oTest  p pTest  q qTest  r rTest
s sTest  t tTest  u uTest  v vTest  w wTest  x xTest  y yTest  z zTest

{ {Test  | |Test  } }Test  ~ ~Test   Test   Test   Test   Test   Test
 Test   Test   Test   Test   Test
$ZzZzZzZz

t
$ZzZzZzZz

